Construction exits (install) (ty 1) unit price, Texas
Low bidders on TxDOT contracts carried a median of $35.00 per SY for item 506-7020, construction exits (install) (ty 1), over the 24 months to 19 NOV 2026, across 281 low bids. Half of all 1,787 bids fell between $28.00 and $44.00.
- Owner
- Texas DOT
- Item
- 506-7020
- Unit
- SY
- Latest letting
- 04 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2024 | 11 | 10 | $29.70 | 57 | $34.00 |
| 2025 | 163 | 148 | $32.85 | 907 | $35.30 |
| 2026 | 146 | 131 | $35.00 | 870 | $37.28 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Dallas District | 66 | $35.00 | 451 | $37.00 |
| San Antonio District | 32 | $25.96 | 236 | $25.70 |
| Houston District | 17 | $28.80 | 125 | $32.35 |
| Fort Worth District | 19 | $33.50 | 120 | $38.37 |
| Austin District | 15 | $40.00 | 105 | $37.00 |
| Lufkin District | 15 | $38.00 | 101 | $38.00 |
| Bryan District | 11 | $36.00 | 80 | $38.00 |
| Lubbock District | 15 | $31.00 | 71 | $45.10 |
| Laredo District | 13 | $40.15 | 67 | $40.00 |
| Corpus Christi District | 9 | $43.56 | 59 | $42.00 |
| Paris District | 4 | $35.60 | 55 | $40.00 |
| Tyler District | 8 | $46.00 | 53 | $36.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (SY) | Low bids | Low-bid median |
|---|---|---|
| 10 to 156 | 70 | $35.00 |
| 156 to 311 | 70 | $35.00 |
| 312 to 587 | 70 | $34.25 |
| 600 to 10,296 | 71 | $31.25 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 04 NOV 2026 | A00193521 | Corpus Christi District | 112 | $62.00 | $56.94 | $35.00 | 5 | J E CONSTRUCTION SERVICES, LLC | TxDOT |
| 04 NOV 2026 | A00124162 | Bryan District | 336 | $50.00 | $41.47 | $36.00 | 12 | FLUOR ENTERPRISES, INC. | TxDOT |
| 04 NOV 2026 | A00206631 | Bryan District | 278 | $20.00 | $38.00 | $32.00 | 7 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 04 NOV 2026 | A00212892 | Dallas District | 10,296 | $43.00 | $38.06 | $26.00 | 6 | INDUS ROAD & BRIDGE, INC. | TxDOT |
| 04 NOV 2026 | A00129572 | Dallas District | 328 | $31.00 | $31.25 | $30.00 | 4 | MARIO SINACOLA & SONS EXCAVATING, INC. | TxDOT |
| 03 NOV 2026 | A00184974 | Austin District | 10 | $50.00 | $52.62 | $42.25 | 6 | AUSTIN BRIDGE & ROAD SERVICES, LP | TxDOT |
| 07 OCT 2026 | A00209154 | Laredo District | 77 | $35.00 | $46.28 | $45.00 | 6 | PRESIDIO CONTRACTING, LLC | TxDOT |
| 07 OCT 2026 | A00135746 | Dallas District | 122 | $30.00 | $36.00 | $40.00 | 9 | GARRET SHIELDS INFRASTRUCTURE | TxDOT |
| 07 OCT 2026 | A00132124 | Lufkin District | 1,000 | $50.00 | $38.00 | $28.00 | 7 | LONGVIEW BRIDGE AND ROAD, LTD. | TxDOT |
| 07 OCT 2026 | A00191892 | Odessa District | 160 | $45.00 | $45.00 | $34.00 | 7 | RELMCO, INC. | TxDOT |
| 07 OCT 2026 | A00196909 | Dallas District | 88 | $54.00 | $44.85 | $30.00 | 8 | XIT PAVING AND CONSTRUCTION INC. | TxDOT |
| 07 OCT 2026 | A00064192 | San Antonio District | 678 | $49.99 | $32.50 | $34.00 | 8 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 06 OCT 2026 | A00066946 | Dallas District | 187 | $10.00 | $38.00 | $30.00 | 8 | A. K. GILLIS & SONS, LLC | TxDOT |
| 03 SEP 2026 | A00184830 | Amarillo District | 156 | $39.00 | $39.00 | $40.00 | 7 | GILVIN-TERRILL, LTD. | TxDOT |
| 03 SEP 2026 | A00206794 | San Antonio District | 78 | $32.10 | $36.00 | n/a | 6 | HUNTER INDUSTRIES, LTD. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.