Rock filter dams (install) (ty 3) unit price, Texas
Low bidders on TxDOT contracts carried a median of $77.00 per LF for item 506-7003, rock filter dams (install) (ty 3), over the 24 months to 19 NOV 2026, across 113 low bids. Half of all 738 bids fell between $60.00 and $100.00.
- Owner
- Texas DOT
- Item
- 506-7003
- Unit
- LF
- Latest letting
- 12 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2024 | 7 | 7 | $109.10 | 42 | $95.43 |
| 2025 | 65 | 64 | $80.00 | 397 | $80.63 |
| 2026 | 48 | 46 | $69.55 | 321 | $79.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Dallas District | 48 | $74.00 | 315 | $78.00 |
| Houston District | 5 | $102.00 | 52 | $76.00 |
| San Antonio District | 9 | $88.00 | 51 | $88.00 |
| Tyler District | 7 | $53.50 | 51 | $55.00 |
| Waco District | 6 | $60.00 | 44 | $78.50 |
| Bryan District | 4 | $89.50 | 27 | $81.00 |
| Fort Worth District | 5 | $92.00 | 26 | $82.50 |
| Abilene District | 3 | $85.00 | 25 | $100.00 |
| Laredo District | 5 | $90.00 | 21 | $90.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 20 to 72 | 28 | $75.00 |
| 75 to 158 | 28 | $82.50 |
| 160 to 347 | 28 | $77.10 |
| 348 to 10,715 | 29 | $75.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 12 NOV 2026 | A00219681 | Dallas District | 50 | $65.00 | $65.00 | $25.00 | 5 | ROAD DOCTORS LLC | TxDOT |
| 04 NOV 2026 | A00212892 | Dallas District | 45 | $128.00 | $109.74 | $75.00 | 6 | INDUS ROAD & BRIDGE, INC. | TxDOT |
| 04 NOV 2026 | A00129572 | Dallas District | 490 | $40.00 | $85.25 | $61.00 | 4 | MARIO SINACOLA & SONS EXCAVATING, INC. | TxDOT |
| 03 NOV 2026 | A00184974 | Austin District | 25 | $98.00 | $152.76 | n/a | 6 | AUSTIN BRIDGE & ROAD SERVICES, LP | TxDOT |
| 06 OCT 2026 | A00066946 | Dallas District | 180 | $65.00 | $71.88 | $65.00 | 8 | A. K. GILLIS & SONS, LLC | TxDOT |
| 09 SEP 2026 | A00218652 | Dallas District | 100 | $20.00 | $75.00 | $75.00 | 5 | GARRET SHIELDS INFRASTRUCTURE | TxDOT |
| 03 SEP 2026 | A00184830 | Amarillo District | 257 | $37.00 | $156.00 | $70.00 | 7 | GILVIN-TERRILL, LTD. | TxDOT |
| 03 SEP 2026 | A00206794 | San Antonio District | 99 | $128.70 | $109.85 | $100.00 | 6 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 06 AUG 2026 | A00189724 | Laredo District | 129 | $85.00 | $85.00 | $109.00 | 3 | ANDERSON COLUMBIA CO., INC. | TxDOT |
| 06 AUG 2026 | A00187792 | Dallas District | 2,240 | $65.00 | $65.00 | $70.00 | 7 | D. L. LENNON INCORPORATED - CONTRACTOR | TxDOT |
| 06 AUG 2026 | A00062075 | Fort Worth District | 70 | $95.00 | $89.00 | $90.00 | 7 | INDUS ROAD & BRIDGE, INC. | TxDOT |
| 06 AUG 2026 | A00206263 | Odessa District | 46 | $45.00 | $100.00 | $85.00 | 5 | DELGADO'S CONTRACTORS, LLC | TxDOT |
| 06 AUG 2026 | A00211130 | Dallas District | 60 | $75.00 | $82.50 | $80.00 | 8 | REAR CONTRACTORS LLC | TxDOT |
| 05 AUG 2026 | A00191471 | Houston District | 100 | $42.00 | $54.34 | n/a | 8 | JAMES CONSTRUCTION GROUP, LLC | TxDOT |
| 05 AUG 2026 | A00068611 | Houston District | 180 | $103.00 | $68.42 | $100.00 | 7 | SER CONSTRUCTION PARTNERS, LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.