Tma (mobile operation) unit price, Texas
Low bidders on TxDOT contracts carried a median of $81.82 per HR for item 505-7002, tma (mobile operation), over the 24 months to 19 NOV 2026, across 268 low bids. Half of all 1,315 bids fell between $58.10 and $144.95.
- Owner
- Texas DOT
- Item
- 505-7002
- Unit
- HR
- Latest letting
- 17 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2024 | 23 | 18 | $74.00 | 73 | $100.00 |
| 2025 | 170 | 142 | $85.00 | 696 | $85.00 |
| 2026 | 130 | 116 | $78.75 | 582 | $90.05 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Dallas District | 33 | $65.00 | 207 | $80.00 |
| Waco District | 35 | $80.00 | 174 | $85.00 |
| Austin District | 24 | $102.03 | 150 | $100.00 |
| Houston District | 26 | $53.00 | 140 | $75.95 |
| Paris District | 21 | $90.00 | 139 | $100.00 |
| Amarillo District | 25 | $95.00 | 123 | $97.76 |
| San Antonio District | 14 | $87.50 | 70 | $97.50 |
| Corpus Christi District | 5 | $100.00 | 36 | $74.55 |
| Laredo District | 10 | $77.50 | 36 | $82.50 |
| Bryan District | 5 | $100.00 | 36 | $100.00 |
| Tyler District | 8 | $71.75 | 31 | $75.00 |
| Lubbock District | 13 | $115.00 | 26 | $145.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (HR) | Low bids | Low-bid median |
|---|---|---|
| 2 to 40 | 67 | $100.00 |
| 40 to 126 | 67 | $73.50 |
| 136 to 672 | 67 | $80.00 |
| 700 to 25,000 | 67 | $77.50 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 17 NOV 2026 | A00224263 | Bryan District | 40 | n/a | $150.00 | $150.00 | 5 | ORTEGA'S LAWN AND LANDSCAPING, LLC | TxDOT |
| 12 NOV 2026 | A00222854 | Amarillo District | 30 | $58.75 | $125.00 | $125.00 | 6 | TI-ZACK CONCRETE, LLC | TxDOT |
| 05 NOV 2026 | A00224316 | Lubbock District | 750 | $150.00 | $150.00 | $180.00 | 3 | FC TRAFFIC CONTROL, LLC | TxDOT |
| 05 NOV 2026 | A00224318 | Lubbock District | 400 | $140.00 | $150.00 | $175.00 | 3 | FC TRAFFIC CONTROL, LLC | TxDOT |
| 04 NOV 2026 | A00196925 | Paris District | 160 | $50.00 | $105.00 | $200.00 | 7 | HIGHWAY 19 CONSTRUCTION LLC | TxDOT |
| 04 NOV 2026 | A00188206 | Austin District | 144 | $105.24 | $55.00 | $150.00 | 6 | BOBCAT SERVICES, INC. | TxDOT |
| 04 NOV 2026 | A00129572 | Dallas District | 276 | $200.00 | $150.00 | $80.00 | 4 | MARIO SINACOLA & SONS EXCAVATING, INC. | TxDOT |
| 04 NOV 2026 | A00223370 | Waco District | 750 | $80.00 | $95.00 | $78.08 | 2 | AWP SAFETY | TxDOT |
| 04 NOV 2026 | A00224031 | Waco District | 6,000 | $80.00 | $84.56 | $78.08 | 3 | AWP SAFETY | TxDOT |
| 04 NOV 2026 | A00224104 | Tyler District | 100 | $70.00 | $81.75 | $75.00 | 4 | HIGHWAY 19 CONSTRUCTION LLC | TxDOT |
| 04 NOV 2026 | A00224201 | Waco District | 60 | $90.00 | $90.00 | $128.65 | 3 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 04 NOV 2026 | A00224204 | Waco District | 25 | $20.00 | $50.00 | $91.15 | 3 | TEXAS MATERIALS GROUP, INC. | TxDOT |
| 03 NOV 2026 | A00219247 | Laredo District | 16 | $300.00 | $209.00 | n/a | 4 | HJC FARMS, INC. | TxDOT |
| 03 NOV 2026 | A00223911 | Odessa District | 60 | $64.00 | $73.50 | $100.00 | 4 | RAGLE CONSTRUCTION, INC. | TxDOT |
| 03 NOV 2026 | A00223921 | Tyler District | 100 | $70.00 | $80.00 | $70.00 | 4 | HIGHWAY 19 CONSTRUCTION LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.