Drill seed (temp)(warm or cool) unit price, Texas
Low bidders on TxDOT contracts carried a median of $0.19 per SY for item 1646051, drill seed (temp)(warm or cool), from 07 FEB 2020 to 01 AUG 2024, across 215 low bids. Half of all 1,130 bids fell between $0.11 and $0.35.
- Owner
- Texas DOT
- Item
- 1646051
- Unit
- SY
- Latest letting
- 01 AUG 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 29 | 29 | $0.13 | 195 | $0.15 |
| 2021 | 49 | 49 | $0.12 | 307 | $0.13 |
| 2022 | 49 | 48 | $0.18 | 240 | $0.18 |
| 2023 | 55 | 52 | $0.25 | 206 | $0.25 |
| 2024 | 37 | 37 | $0.20 | 182 | $0.25 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Dallas District | 99 | $0.18 | 558 | $0.18 |
| Houston District | 42 | $0.20 | 236 | $0.20 |
| San Antonio District | 26 | $0.17 | 148 | $0.20 |
| Corpus Christi District | 9 | $0.19 | 53 | $0.18 |
| Waco District | 11 | $0.15 | 39 | $0.16 |
| Lubbock District | 6 | $0.40 | 19 | $0.30 |
| Abilene District | 4 | $0.33 | 15 | $0.45 |
| Wichita Falls District | 3 | $0.22 | 12 | $0.23 |
| Fort Worth District | 4 | $0.19 | 10 | $0.18 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (SY) | Low bids | Low-bid median |
|---|---|---|
| 14 to 7,346 | 53 | $0.50 |
| 7,893 to 40,683 | 54 | $0.22 |
| 42,049 to 128,926 | 54 | $0.15 |
| 132,172 to 1,996,127 | 54 | $0.12 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 01 AUG 2024 | 08243001 | Houston District | 49,169 | $0.22 | $0.21 | $0.30 | 2 | WEBBER, LLC | TxDOT |
| 10 JUL 2024 | 07243201 | Dallas District | 437,989 | $1.52 | $0.81 | $0.25 | 2 | AUSTIN BRIDGE & ROAD SERVICES, LP | TxDOT |
| 10 JUL 2024 | 07243207 | Dallas District | 61,264 | $1.00 | $0.30 | $1.00 | 6 | HARPER BROTHERS CONSTRUCTION LLC | TxDOT |
| 06 JUN 2024 | 06243201 | San Antonio District | 78,053 | $0.16 | $0.20 | $0.15 | 5 | WEBBER, LLC | TxDOT |
| 06 JUN 2024 | 06243203 | Houston District | 265,793 | $0.20 | $0.20 | $0.13 | 2 | JAMES CONSTRUCTION GROUP, LLC | TxDOT |
| 06 JUN 2024 | 06243213 | Dallas District | 7,149 | $1.00 | $1.00 | $0.30 | 3 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 06 JUN 2024 | 06243215 | San Antonio District | 64,684 | $0.18 | $0.20 | $0.30 | 8 | SALINAS CONSTRUCTION TECHNOLOGIES, LTD. | TxDOT |
| 06 JUN 2024 | 06243240 | Dallas District | 17,683 | $0.20 | $0.20 | $0.20 | 3 | JAGOE-PUBLIC COMPANY | TxDOT |
| 05 JUN 2024 | 06243002 | Houston District | 86,850 | $0.20 | $0.25 | $1.90 | 7 | SER CONSTRUCTION PARTNERS, LLC | TxDOT |
| 05 JUN 2024 | 06243007 | Dallas District | 102,863 | $0.28 | $0.28 | $0.65 | 3 | KNIFE RIVER CORPORATION - SOUTH | TxDOT |
| 05 JUN 2024 | 06243010 | Houston District | 1,224 | $0.29 | $1.00 | $0.15 | 5 | R CONSTRUCTION CIVIL, LLC | TxDOT |
| 05 JUN 2024 | 06243025 | Dallas District | 11,964 | $0.35 | $0.35 | $0.60 | 3 | SELECT MAINTENANCE, L.L.C. | TxDOT |
| 05 JUN 2024 | 06243032 | San Antonio District | 29,225 | $0.27 | $0.27 | $0.19 | 10 | ROADWAY SPECIALTIES, INC. | TxDOT |
| 02 MAY 2024 | 05243002 | Laredo District | 1,996,127 | $0.10 | $0.11 | $0.20 | 2 | WEBBER, LLC | TxDOT |
| 02 MAY 2024 | 05243015 | Fort Worth District | 77,221 | $0.18 | $0.17 | $0.24 | 4 | JAY MILLS CONTRACTING, INCORPORATED | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.