Drill seeding (temp) (warm) unit price, Texas
Low bidders on TxDOT contracts carried a median of $700.00 per ACRE for item 1646042, drill seeding (temp) (warm), from 07 FEB 2020 to 10 JUL 2024, across 39 low bids. Half of all 197 bids fell between $475.00 and $1,000.00.
- Owner
- Texas DOT
- Item
- 1646042
- Unit
- ACRE
- Latest letting
- 10 JUL 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 5 | 5 | $600.00 | 30 | $492.78 |
| 2021 | 14 | 14 | $500.00 | 80 | $574.69 |
| 2022 | 7 | 7 | $475.00 | 29 | $500.00 |
| 2023 | 8 | 8 | $925.00 | 29 | $849.14 |
| 2024 | 6 | 5 | $900.00 | 29 | $1,500.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Laredo District | 15 | $888.00 | 69 | $825.00 |
| Childress District | 8 | $662.50 | 46 | $646.74 |
| San Angelo District | 5 | $700.00 | 37 | $462.15 |
| Abilene District | 4 | $825.00 | 16 | $800.00 |
| Amarillo District | 3 | $393.75 | 12 | $421.89 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (ACRE) | Low bids | Low-bid median |
|---|---|---|
| 0.30 to 4 | 9 | $1,650.00 |
| 5.25 to 13.36 | 10 | $527.50 |
| 13.54 to 32.50 | 10 | $537.50 |
| 37.20 to 115.60 | 10 | $720.50 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 10 JUL 2024 | 07243205 | Laredo District | 39.80 | $900.00 | $800.00 | $1,000.00 | 4 | ANDERSON COLUMBIA CO., INC. | TxDOT |
| 10 JUL 2024 | 07243211 | Childress District | 1.35 | $1,507.96 | $1,800.00 | $1,500.00 | 5 | C. E. BARKER, LTD. | TxDOT |
| 05 JUN 2024 | 06243029 | Laredo District | 11.20 | $888.00 | $1,504.00 | $910.00 | 7 | J. CARROLL WEAVER, INC. | TxDOT |
| 05 JUN 2024 | 06243049 | Laredo District | 5.71 | $1,665.00 | $1,672.50 | $1,500.00 | 6 | J. CARROLL WEAVER, INC. | TxDOT |
| 05 MAR 2024 | 03243007 | Abilene District | 7.30 | n/a | $943.10 | $800.00 | 4 | FOUTSCO PAVING COMPANY, LLC | TxDOT |
| 05 MAR 2024 | 03243021 | Abilene District | 19 | $800.00 | $700.00 | $1,000.00 | 3 | GILVIN-TERRILL, LTD. | TxDOT |
| 03 AUG 2023 | 08233216 | Abilene District | 9.04 | $1,000.00 | $955.00 | $850.00 | 2 | GILVIN-TERRILL, LTD. | TxDOT |
| 02 AUG 2023 | 08233057 | Laredo District | 73.80 | $1,000.00 | $997.50 | $400.00 | 2 | ANDERSON COLUMBIA CO., INC. | TxDOT |
| 28 JUN 2023 | 06233602 | Yoakum District | 66 | $741.00 | $720.50 | $460.00 | 2 | WEBBER, LLC | TxDOT |
| 02 JUN 2023 | 06233205 | Abilene District | 21.79 | $850.00 | $787.50 | $475.00 | 4 | BONTKE BROTHERS CONSTRUCTION COMPANY | TxDOT |
| 01 JUN 2023 | 06233011 | Laredo District | 1.60 | $4,500.00 | $2,999.00 | $1,825.00 | 5 | RELMCO, INC. | TxDOT |
| 01 JUN 2023 | 06233018 | Laredo District | 53 | $700.00 | $746.58 | $525.00 | 3 | CK NEWBERRY, LLC | TxDOT |
| 05 MAY 2023 | 05233204 | Zapata | 104 | $1,000.00 | $950.00 | $700.00 | 4 | IOC COMPANY LLC | TxDOT |
| 02 FEB 2023 | 02233245 | San Angelo District | 115.60 | $700.00 | $700.00 | $550.00 | 7 | MASSANA CONSTRUCTION INC. | TxDOT |
| 01 DEC 2022 | 12223010 | Laredo District | 2.20 | $1,650.00 | $1,825.00 | $500.00 | 2 | RELMCO, INC. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.