Driveways (conc) (hes) unit price, Texas
Low bidders on TxDOT contracts carried a median of $110.00 per SY for item 5306017, driveways (conc) (hes), from 06 FEB 2020 to 09 JUL 2024, across 113 low bids. Half of all 581 bids fell between $95.00 and $140.00.
- Owner
- Texas DOT
- Item
- 5306017
- Unit
- SY
- Latest letting
- 09 JUL 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 22 | 22 | $87.50 | 137 | $99.00 |
| 2021 | 31 | 31 | $100.00 | 187 | $100.00 |
| 2022 | 18 | 18 | $107.50 | 90 | $120.00 |
| 2023 | 23 | 23 | $150.00 | 85 | $150.50 |
| 2024 | 19 | 19 | $120.00 | 82 | $132.50 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Dallas District | 37 | $110.00 | 216 | $109.33 |
| Tyler District | 38 | $110.00 | 194 | $120.00 |
| Waco District | 12 | $121.34 | 46 | $125.00 |
| San Antonio District | 5 | $80.00 | 33 | $96.00 |
| Bryan District | 6 | $88.75 | 32 | $118.50 |
| Houston District | 6 | $104.15 | 23 | $95.91 |
| Fort Worth District | 3 | $90.00 | 16 | $108.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (SY) | Low bids | Low-bid median |
|---|---|---|
| 14 to 153 | 28 | $147.27 |
| 158 to 543 | 28 | $118.50 |
| 587 to 1,625 | 28 | $105.00 |
| 1,655 to 15,063 | 29 | $85.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 09 JUL 2024 | 07243002 | El Paso District | 4,340 | $140.00 | $105.96 | $150.00 | 2 | SUNDT CONSTRUCTION, INC. | TxDOT |
| 09 JUL 2024 | 07243018 | Bryan District | 140 | $250.00 | $211.00 | $125.00 | 4 | LARRY YOUNG PAVING, INC. | TxDOT |
| 06 JUN 2024 | 06243213 | Dallas District | 133 | $250.00 | $250.00 | $140.00 | 3 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 03 MAY 2024 | 05243207 | Tyler District | 781 | $204.00 | $145.00 | $175.00 | 4 | BAKER & COMPANY CONSTRUCTION, LLC | TxDOT |
| 02 MAY 2024 | 05243003 | Waco District | 201 | $125.00 | $163.00 | $135.00 | 4 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 02 MAY 2024 | 05243017 | Dallas District | 1,587 | $120.00 | $120.00 | $125.00 | 5 | JAGOE-PUBLIC COMPANY | TxDOT |
| 04 APR 2024 | 04243001 | Dallas District | 7,395 | $118.84 | $122.42 | $85.00 | 2 | SEMA CONSTRUCTION, INC. | TxDOT |
| 04 APR 2024 | 04243024 | Waco District | 1,974 | $117.69 | $137.50 | $135.00 | 6 | TI-ZACK CONCRETE, LLC | TxDOT |
| 04 APR 2024 | 04243030 | Dallas District | 52 | $204.00 | $150.00 | $150.00 | 5 | BAKER & COMPANY CONSTRUCTION, LLC | TxDOT |
| 06 MAR 2024 | 03243201 | Odessa District | 1,689 | $84.00 | $84.00 | $260.00 | 3 | SUNDT CONSTRUCTION, INC. | TxDOT |
| 05 MAR 2024 | 03243001 | Tyler District | 687 | $105.00 | $135.00 | $175.00 | 5 | LAMAR COMPANIES LLC | TxDOT |
| 02 FEB 2024 | 02243201 | Waco District | 271 | $84.33 | $84.33 | $139.00 | 3 | JAMES CONSTRUCTION GROUP, LLC | TxDOT |
| 01 FEB 2024 | 02243001 | Dallas District | 6,640 | $66.80 | $75.25 | $120.00 | 3 | FLATIRON CONSTRUCTORS, INC. | TxDOT |
| 01 FEB 2024 | 02243039 | Waco District | 32 | $175.00 | $285.00 | $90.00 | 3 | E-Z BEL CONSTRUCTION, LLC | TxDOT |
| 05 JAN 2024 | 01243216 | Tyler District | 436 | $100.00 | $165.00 | $150.00 | 6 | TRUE ROADS CONSTRUCTION, LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.