Turnouts (surf treat) unit price, Texas
Low bidders on TxDOT contracts carried a median of $46.50 per SY for item 5306009, turnouts (surf treat), from 08 APR 2020 to 10 JUL 2024, across 50 low bids. Half of all 236 bids fell between $30.66 and $64.84.
- Owner
- Texas DOT
- Item
- 5306009
- Unit
- SY
- Latest letting
- 10 JUL 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 9 | 9 | $32.25 | 51 | $34.49 |
| 2021 | 11 | 10 | $31.00 | 58 | $37.00 |
| 2022 | 5 | 5 | $35.00 | 16 | $50.00 |
| 2023 | 14 | 14 | $47.40 | 45 | $50.00 |
| 2024 | 12 | 12 | $76.21 | 66 | $52.80 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Yoakum District | 10 | $38.84 | 52 | $42.25 |
| Corpus Christi District | 5 | $32.00 | 35 | $38.00 |
| Lufkin District | 11 | $70.00 | 34 | $66.21 |
| Austin District | 4 | $28.62 | 31 | $33.00 |
| San Antonio District | 3 | $56.60 | 20 | $50.02 |
| Brownwood District | 5 | $32.00 | 16 | $35.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (SY) | Low bids | Low-bid median |
|---|---|---|
| 11 to 220 | 12 | $40.20 |
| 278 to 383 | 13 | $50.00 |
| 448 to 684 | 12 | $60.70 |
| 688 to 2,419 | 13 | $45.80 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 10 JUL 2024 | 07243208 | San Antonio District | 457 | $56.60 | $53.38 | $85.27 | 8 | ACME BRIDGE COMPANY, INC. | TxDOT |
| 10 JUL 2024 | 07243213 | Lufkin District | 552 | $72.42 | $58.71 | $70.00 | 2 | PINTO CONSTRUCTION CO., INC. | TxDOT |
| 06 JUN 2024 | 06243215 | San Antonio District | 320 | $95.28 | $41.00 | $40.00 | 8 | SALINAS CONSTRUCTION TECHNOLOGIES, LTD. | TxDOT |
| 06 JUN 2024 | 06243233 | Lufkin District | 138 | $146.51 | $134.25 | $90.00 | 2 | PINTO CONSTRUCTION CO., INC. | TxDOT |
| 06 JUN 2024 | 06243246 | Corpus Christi District | 278 | $89.59 | $38.00 | $70.00 | 7 | CLARK CONSTRUCTION OF TEXAS, INC. | TxDOT |
| 05 JUN 2024 | 06243021 | Atlanta District | 480 | $80.00 | $77.50 | $80.00 | 6 | TRUE ROADS, LLC | TxDOT |
| 02 MAY 2024 | 05243018 | Corpus Christi District | 73 | $26.00 | $50.70 | $32.00 | 8 | CK NEWBERRY, LLC | TxDOT |
| 05 APR 2024 | 04243209 | Yoakum District | 305 | $40.00 | $49.00 | $45.00 | 11 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 05 APR 2024 | 04243213 | Atlanta District | 335 | $150.00 | $112.50 | $75.00 | 2 | A. K. GILLIS & SONS, LLC | TxDOT |
| 05 MAR 2024 | 03243008 | Yoakum District | 688 | $47.20 | $50.00 | $45.00 | 3 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 01 FEB 2024 | 02243008 | Yoakum District | 582 | $64.79 | $52.75 | $40.00 | 6 | CLARK CONSTRUCTION OF TEXAS, INC. | TxDOT |
| 05 JAN 2024 | 01243205 | Lufkin District | 1,432 | $140.00 | $70.00 | $93.00 | 3 | A. L. HELMCAMP, INC. | TxDOT |
| 05 DEC 2023 | 12233003 | Yoakum District | 214.60 | $41.39 | $43.20 | $35.00 | 4 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 06 SEP 2023 | 09233014 | Abilene District | 179 | $25.00 | $32.82 | $40.00 | 2 | BONTKE BROTHERS CONSTRUCTION COMPANY | TxDOT |
| 03 AUG 2023 | 08233204 | Yoakum District | 1,894 | $45.80 | $45.80 | $35.00 | 1 | HUNTER INDUSTRIES, LTD. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.