Elc srv ty a 120/240 060(ns)ss(e)sp(o) unit price, Texas

Low bidders on TxDOT contracts carried a median of $7,015.00 per EACH for item 6286009, elc srv ty a 120/240 060(ns)ss(e)sp(o), from 09 JAN 2020 to 01 AUG 2024, across 47 low bids. Half of all 174 bids fell between $6,187.52 and $8,815.19.

Owner
Texas DOT
Item
6286009
Unit
EACH
Latest letting
01 AUG 2024
$7,015.00Low bidder's median, per EACH
$7,500.00Median of all bids, per EACH
47Contracts in the window
$6,166.67Engineer's estimate, median per EACH

By year of letting

Elc srv ty a 120/240 060(ns)ss(e)sp(o), TxDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20201111$6,100.0047$6,400.00
202188$5,695.8429$5,800.00
202288$7,335.0024$7,850.00
202388$8,200.0029$8,200.00
20241212$8,744.2745$8,668.29
Elc srv ty a 120/240 060(ns)ss(e)sp(o), TxDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Elc srv ty a 120/240 060(ns)ss(e)sp(o), TxDOT: unit prices by district, all lettings
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Yoakum District10$7,760.0036$8,336.99
Wichita Falls District6$7,507.5024$7,305.03
Laredo District6$6,118.7524$6,660.00
Lufkin District5$7,170.0014$7,335.00
Odessa District3$9,900.0012$7,115.00
Tyler District3$8,200.0012$8,000.00
Waco District3$8,200.0011$8,500.00
Amarillo District3$6,564.009$6,564.00
Elc srv ty a 120/240 060(ns)ss(e)sp(o), TxDOT: unit prices by district, all lettings

Districts with at least three low bids, over all lettings.

By quantity

Elc srv ty a 120/240 060(ns)ss(e)sp(o), TxDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 111$7,170.00
1 to 212$7,675.00
2 to 312$6,907.00
3 to 1312$6,694.70
Elc srv ty a 120/240 060(ns)ss(e)sp(o), TxDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest TxDOT contracts carrying Elc srv ty a 120/240 060(ns)ss(e)sp(o)
LetContractDistrictQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
01 AUG 202408243001Houston District1$8,000.00$8,150.00$8,363.002WEBBER, LLCTxDOT
06 JUN 202406243205Wichita Falls District1$17,000$17,000$6,166.673A. L. HELMCAMP, INC.TxDOT
05 JUN 202406243005Amarillo District1$7,350.00$7,746.00$7,400.002J. LEE MILLIGAN, INC.TxDOT
03 MAY 202405243201Yoakum District1$8,593.73$7,820.00$8,300.003PULICE CONSTRUCTION, INC.TxDOT
03 MAY 202405243234Laredo District1$6,500.00$7,225.00$6,600.007TEXAS MATERIALS GROUP, INC.TxDOT
04 APR 202404243014Austin District2$10,000$10,000$5,400.003APEX LANDSCAPE & IRRIGATION, LLCTxDOT
05 MAR 202403243001Tyler District3$9,000.00$8,000.00$6,600.005LAMAR COMPANIES LLCTxDOT
05 MAR 202403243008Yoakum District1$8,820.25$10,000$7,500.003HUNTER INDUSTRIES, LTD.TxDOT
01 FEB 202402243003Wichita Falls District1$19,400$18,200$6,166.672JAGOE-PUBLIC COMPANYTxDOT
01 FEB 202402243036Waco District1$10,000$9,500.00$7,300.004KNIFE RIVER CORPORATION - SOUTHTxDOT
05 JAN 202401243201Yoakum District3$8,668.29$8,668.29$8,500.007HUNTER INDUSTRIES, LTD.TxDOT
05 JAN 202401243229Yoakum District3$7,230.00$8,086.27$7,500.004TRAF-TEX, INC.TxDOT
06 DEC 202312233227Laredo District1$6,600.00$7,818.00$8,284.336D&G ENERGY CORPORATIONTxDOT
03 AUG 202308233211Yoakum District2$9,653.00$9,653.00$8,000.004HUNTER INDUSTRIES, LTD.TxDOT
03 AUG 202308233274Tyler District3$8,200.00$8,000.00$1,060.853EAST TEXAS BRIDGE, INC.TxDOT
Latest TxDOT contracts carrying Elc srv ty a 120/240 060(ns)ss(e)sp(o)

Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.

How these prices were read

TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy