Elc srv ty a 240/480 060(ns)ss(e)sp(o) unit price, Texas
Low bidders on TxDOT contracts carried a median of $10,038 per EACH for item 628-7048, elc srv ty a 240/480 060(ns)ss(e)sp(o), over the 24 months to 19 NOV 2026, across 44 low bids. Half of all 244 bids fell between $8,500.00 and $11,702.
- Owner
- Texas DOT
- Item
- 628-7048
- Unit
- EACH
- Latest letting
- 03 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2024 | 3 | 3 | $9,300.00 | 18 | $9,281.84 |
| 2025 | 16 | 16 | $10,077 | 73 | $10,000 |
| 2026 | 27 | 27 | $10,075 | 165 | $9,680.10 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Fort Worth District | 5 | $9,300.00 | 41 | $10,000 |
| Odessa District | 11 | $13,000 | 36 | $11,936 |
| Yoakum District | 4 | $10,612 | 31 | $9,816.40 |
| Amarillo District | 6 | $9,925.00 | 30 | $9,470.38 |
| San Antonio District | 3 | $6,900.00 | 20 | $7,517.50 |
| Lufkin District | 3 | $9,182.00 | 18 | $9,291.00 |
| Waco District | 3 | $8,950.00 | 14 | $9,263.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 11 | $9,300.00 |
| 1 to 2 | 11 | $10,304 |
| 2 to 3 | 11 | $10,384 |
| 3 to 11 | 11 | $10,000 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 03 NOV 2026 | A00211505 | Amarillo District | 1 | $15,000 | $12,587 | n/a | 8 | COPPELL CONSTRUCTION CO., INC. | TxDOT |
| 03 SEP 2026 | A00184830 | Amarillo District | 2 | $7,725.00 | $8,000.00 | $12,000 | 7 | GILVIN-TERRILL, LTD. | TxDOT |
| 06 AUG 2026 | A00199843 | Odessa District | 2 | $8,675.00 | $8,675.00 | $13,750 | 5 | DAN WILLIAMS COMPANY | TxDOT |
| 06 AUG 2026 | A00203348 | Atlanta District | 3 | $13,000 | $10,663 | $9,770.00 | 4 | EAST TEXAS BRIDGE, INC. | TxDOT |
| 06 AUG 2026 | A00207005 | Yoakum District | 1 | $13,645 | $10,000 | $10,500 | 3 | STX CIVIL | TxDOT |
| 05 AUG 2026 | A00128458 | Amarillo District | 5 | $9,225.00 | $8,385.00 | $12,000 | 4 | J. LEE MILLIGAN, INC. | TxDOT |
| 05 AUG 2026 | A00191471 | Houston District | 1 | $8,450.00 | $8,800.00 | $11,000 | 8 | JAMES CONSTRUCTION GROUP, LLC | TxDOT |
| 05 AUG 2026 | A00213321 | Fort Worth District | 2 | $8,500.00 | $10,160 | $7,500.00 | 10 | VACA UNDERGROUND UTILITIES INC | TxDOT |
| 05 AUG 2026 | A00007222 | Fort Worth District | 2 | $13,500 | $12,600 | n/a | 11 | INDUS ROAD & BRIDGE, INC. | TxDOT |
| 05 AUG 2026 | A00218301 | San Antonio District | 1 | $9,341.00 | $7,830.82 | $12,500 | 12 | ELECNOR BELCO ELECTRIC, INC. | TxDOT |
| 02 JUL 2026 | A00064356 | Lufkin District | 2 | $8,500.00 | $8,500.00 | $10,000 | 6 | POSILLICO CIVIL, INC. | TxDOT |
| 02 JUL 2026 | A00187816 | Odessa District | 1 | $10,485 | $10,485 | $12,002 | 3 | JASCO | TxDOT |
| 01 JUL 2026 | A00128943 | Odessa District | 2 | $11,000 | $11,413 | $13,750 | 2 | A. L. HELMCAMP, INC. | TxDOT |
| 01 JUL 2026 | A00219976 | Yoakum District | 2 | $10,384 | $10,192 | $7,200.00 | 10 | TEXAS STEEL INDUSTRIAL PLACING, LLC | TxDOT |
| 01 JUL 2026 | A00008199 | Fort Worth District | 1 | $9,300.00 | $8,944.03 | $10,500 | 6 | INDUS ROAD & BRIDGE, INC. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way