Zinc-coat stl wire strand (3/8") unit price, Texas
Low bidders on TxDOT contracts carried a median of $3.00 per LF for item 6256003, zinc-coat stl wire strand (3/8"), from 09 JAN 2020 to 09 JUL 2024, across 65 low bids. Half of all 254 bids fell between $2.50 and $4.34.
- Owner
- Texas DOT
- Item
- 6256003
- Unit
- LF
- Latest letting
- 09 JUL 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 17 | 17 | $3.49 | 81 | $3.07 |
| 2021 | 14 | 14 | $2.75 | 55 | $3.00 |
| 2022 | 7 | 7 | $2.27 | 27 | $4.00 |
| 2023 | 16 | 16 | $2.94 | 57 | $3.00 |
| 2024 | 11 | 11 | $3.65 | 34 | $4.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Pharr District | 22 | $2.55 | 79 | $2.80 |
| Corpus Christi District | 6 | $3.25 | 34 | $3.56 |
| Houston District | 5 | $2.52 | 27 | $3.00 |
| Bryan District | 5 | $2.15 | 24 | $1.75 |
| Dallas District | 7 | $4.10 | 21 | $4.10 |
| Fort Worth District | 5 | $5.25 | 19 | $6.00 |
| Waco District | 3 | $4.00 | 12 | $4.03 |
| Laredo District | 3 | $3.65 | 12 | $4.50 |
| Austin District | 5 | $2.00 | 9 | $3.40 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 80 to 350 | 16 | $3.55 |
| 350 to 842 | 16 | $2.75 |
| 880 to 2,000 | 16 | $2.98 |
| 2,130 to 10,000 | 17 | $2.60 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 09 JUL 2024 | 07243004 | Laredo District | 350 | $3.65 | $5.33 | $5.00 | 2 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 09 JUL 2024 | 07243008 | Fort Worth District | 100 | $12.00 | $12.00 | $4.30 | 1 | LIGHT IT UP ELECTRIC | TxDOT |
| 06 JUN 2024 | 06243241 | Pharr District | 5,164 | $2.40 | $2.60 | $2.75 | 3 | TRAF-TEX, INC. | TxDOT |
| 05 JUN 2024 | 06243015 | Pharr District | 80 | $2.50 | $2.55 | $3.00 | 3 | FOREMOST PAVING, INC. | TxDOT |
| 03 MAY 2024 | 05243234 | Laredo District | 350 | $4.25 | $4.70 | $3.00 | 7 | TEXAS MATERIALS GROUP, INC. | TxDOT |
| 04 APR 2024 | 04243001 | Dallas District | 3,545 | $14.17 | $9.04 | $1.75 | 2 | SEMA CONSTRUCTION, INC. | TxDOT |
| 04 APR 2024 | 04243019 | Dallas District | 780 | $7.80 | $6.00 | $5.00 | 3 | YUNEX LLC | TxDOT |
| 04 APR 2024 | 04243027 | Pharr District | 2,860 | $3.56 | $2.62 | $3.00 | 3 | THE LEVY COMPANY, INC. | TxDOT |
| 05 MAR 2024 | 03243035 | Austin District | 250 | $5.00 | $4.20 | $3.00 | 2 | ELECNOR BELCO ELECTRIC, INC. | TxDOT |
| 01 FEB 2024 | 02243025 | Austin District | 400 | $2.00 | $4.00 | $2.63 | 3 | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. | TxDOT |
| 05 JAN 2024 | 01243209 | Pharr District | 1,100 | $2.75 | $3.00 | $3.11 | 5 | ASAGO, LLC | TxDOT |
| 01 NOV 2023 | 11233026 | Corpus Christi District | 2,590 | $2.80 | $3.53 | $3.50 | 3 | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. | TxDOT |
| 07 SEP 2023 | 09233211 | Pharr District | 3,270 | $3.00 | $3.00 | $2.69 | 4 | TEXAS CORDIA CONSTRUCTION, LLC | TxDOT |
| 06 SEP 2023 | 09233005 | Pharr District | 1,830 | $3.30 | $2.90 | $3.00 | 4 | REIM CONSTRUCTION, INC. | TxDOT |
| 06 SEP 2023 | 09233017 | Dallas District | 500 | $5.00 | $7.50 | $5.00 | 2 | DURABLE SPECIALTIES, INC. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.