Elec condr (no.10) bare unit price, Texas
Low bidders on TxDOT contracts carried a median of $1.30 per LF for item 6206005, elec condr (no.10) bare, from 10 JAN 2020 to 01 AUG 2024, across 41 low bids. Half of all 171 bids fell between $1.13 and $1.65.
- Owner
- Texas DOT
- Item
- 6206005
- Unit
- LF
- Latest letting
- 01 AUG 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 9 | 9 | $1.03 | 55 | $1.15 |
| 2021 | 11 | 11 | $1.30 | 51 | $1.30 |
| 2022 | 4 | 4 | $1.47 | 10 | $1.90 |
| 2023 | 11 | 11 | $1.50 | 38 | $1.50 |
| 2024 | 6 | 6 | $1.50 | 17 | $1.70 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Fort Worth District | 8 | $1.29 | 34 | $1.30 |
| San Antonio District | 5 | $1.27 | 25 | $1.30 |
| Austin District | 7 | $1.20 | 22 | $1.29 |
| Beaumont District | 3 | $1.20 | 16 | $1.31 |
| Corpus Christi District | 3 | $5.00 | 13 | $1.30 |
| Odessa District | 3 | $1.05 | 12 | $1.34 |
| Houston District | 3 | $1.40 | 11 | $1.40 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 45 to 397 | 10 | $1.19 |
| 435 to 995 | 10 | $1.27 |
| 1,000 to 3,205 | 10 | $1.59 |
| 3,321 to 37,959 | 11 | $1.25 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 01 AUG 2024 | 08243001 | Houston District | 3,205 | $1.40 | $1.40 | $1.30 | 2 | WEBBER, LLC | TxDOT |
| 10 JUL 2024 | 07243227 | Fort Worth District | 1,000 | $2.60 | $2.80 | $1.81 | 2 | YUNEX LLC | TxDOT |
| 06 JUN 2024 | 06243201 | San Antonio District | 3,184 | $1.60 | $1.70 | $1.80 | 5 | WEBBER, LLC | TxDOT |
| 05 APR 2024 | 04243202 | Wichita Falls District | 1,155 | $1.34 | $2.00 | $2.50 | 2 | AUSTIN BRIDGE & ROAD SERVICES, LP ZACHRY CONSTRUCTION CORPORATION | TxDOT |
| 04 APR 2024 | 04243036 | Austin District | 455 | $5.00 | $2.50 | $1.80 | 3 | ENCINO LANDSCAPE, INC. | TxDOT |
| 01 FEB 2024 | 02243025 | Austin District | 200 | $1.00 | $1.35 | $1.32 | 3 | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. | TxDOT |
| 02 NOV 2023 | 11233201 | Odessa District | 1,705 | $1.00 | $1.00 | $2.00 | 5 | SUNDT CONSTRUCTION, INC. | TxDOT |
| 03 AUG 2023 | 08233203 | Dallas District | 3,810 | $2.10 | $2.55 | $2.00 | 2 | WEBBER, LLC | TxDOT |
| 02 AUG 2023 | 08233001 | Laredo District | 2,763 | $1.58 | $1.64 | $1.50 | 4 | JAMES CONSTRUCTION GROUP, LLC | TxDOT |
| 02 AUG 2023 | 08233057 | Laredo District | 970 | $1.50 | $1.26 | $1.75 | 2 | ANDERSON COLUMBIA CO., INC. | TxDOT |
| 02 AUG 2023 | 08233061 | Waco District | 3,356 | $1.00 | $1.65 | $1.50 | 2 | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. | TxDOT |
| 28 JUN 2023 | 06233625 | Fort Worth District | 1,000 | $2.50 | $2.25 | $1.81 | 2 | YUNEX LLC | TxDOT |
| 02 JUN 2023 | 06233207 | Houston District | 16,700 | $1.35 | $1.13 | $1.59 | 7 | THIRD COAST SERVICES LLC | TxDOT |
| 01 JUN 2023 | 06233002 | San Antonio District | 4,150 | $1.27 | $1.80 | $1.90 | 3 | WEBBER, LLC | TxDOT |
| 04 MAY 2023 | 05233002 | Fort Worth District | 3,321 | $1.30 | $1.24 | $1.50 | 6 | SEMA CONSTRUCTION, INC. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.