Elec condr (no.8) bare unit price, Texas

Low bidders on TxDOT contracts carried a median of $1.60 per LF for item 6206007, elec condr (no.8) bare, from 09 JAN 2020 to 02 AUG 2024, across 481 low bids. Half of all 1,931 bids fell between $1.30 and $2.15.

Owner
Texas DOT
Item
6206007
Unit
LF
Latest letting
02 AUG 2024
$1.60Low bidder's median, per LF
$1.64Median of all bids, per LF
481Contracts in the window
$1.50Engineer's estimate, median per LF

By year of letting

Elec condr (no.8) bare, TxDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20209696$1.30442$1.30
2021130130$1.45575$1.50
20227272$1.77278$1.85
20239090$1.88298$1.90
20249393$2.00338$2.00
Elec condr (no.8) bare, TxDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Elec condr (no.8) bare, TxDOT: unit prices by district, all lettings
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Houston District49$1.50238$1.50
Austin District50$1.50214$1.52
Dallas District39$1.88196$1.61
Fort Worth District44$2.04186$1.85
San Antonio District30$1.36150$1.40
Pharr District28$1.62105$1.60
Amarillo District34$1.9498$2.00
Yoakum District28$1.7998$1.90
Waco District22$1.5080$1.62
Tyler District22$2.6571$2.75
Laredo District18$1.5068$1.59
Beaumont District17$1.6062$1.50
Elec condr (no.8) bare, TxDOT: unit prices by district, all lettings

Districts with at least three low bids, over all lettings.

By quantity

Elec condr (no.8) bare, TxDOT: low bidder's median by quantity band
Quantity (LF)Low bidsLow-bid median
10 to 751120$2.00
755 to 2,242120$1.71
2,277 to 6,920120$1.60
6,971 to 93,089121$1.40
Elec condr (no.8) bare, TxDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest TxDOT contracts carrying Elec condr (no.8) bare
LetContractDistrictQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
02 AUG 202408243201Pharr District8,398$1.60$1.50$1.503FOREMOST PAVING, INC.TxDOT
02 AUG 202408243202Houston District530$2.26$2.16$2.004JAMES CONSTRUCTION GROUP, LLCTxDOT
01 AUG 202408243001Houston District18,686$1.75$1.75$1.802WEBBER, LLCTxDOT
10 JUL 202407243201Dallas District7,610$2.65$2.65$4.002AUSTIN BRIDGE & ROAD SERVICES, LPTxDOT
10 JUL 202407243213Lufkin District225$4.00$3.50$2.002PINTO CONSTRUCTION CO., INC.TxDOT
10 JUL 202407243220Houston District4,550$1.60$1.71$1.604STATEWIDE TRAFFIC SIGNAL COMPANYTxDOT
10 JUL 202407243227Fort Worth District600$4.80$4.40$3.502YUNEX LLCTxDOT
10 JUL 202407243230Tyler District180$3.50$3.15$2.004MARCOM'S MOWING SERVICE, LLCTxDOT
09 JUL 202407243001Fort Worth District32,301$2.37$2.36$3.002ZACHRY CONSTRUCTION CORPORATIONTxDOT
09 JUL 202407243004Laredo District5,200$1.50$1.90$1.502HUNTER INDUSTRIES, LTD.TxDOT
09 JUL 202407243005Abilene District11,230$1.50$1.64$2.003FNF CONSTRUCTION, INC.TxDOT
09 JUL 202407243008Fort Worth District1,000$2.20$2.20$2.601LIGHT IT UP ELECTRICTxDOT
09 JUL 202407243014Houston District3,445$1.50$1.68$2.252STATEWIDE TRAFFIC SIGNAL COMPANYTxDOT
09 JUL 202407243030Amarillo District2,770$2.25$2.62$3.004VACA UNDERGROUND UTILITIES INCTxDOT
06 JUN 202406243201San Antonio District10,498$1.55$1.65$4.205WEBBER, LLCTxDOT
Latest TxDOT contracts carrying Elec condr (no.8) bare

Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.

How these prices were read

TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy