Elec condr (no.4) bare unit price, Texas

Low bidders on TxDOT contracts carried a median of $2.40 per LF for item 6206011, elec condr (no.4) bare, from 09 JAN 2020 to 02 AUG 2024, across 183 low bids. Half of all 809 bids fell between $1.74 and $2.95.

Owner
Texas DOT
Item
6206011
Unit
LF
Latest letting
02 AUG 2024
$2.40Low bidder's median, per LF
$2.19Median of all bids, per LF
183Contracts in the window
$2.00Engineer's estimate, median per LF

By year of letting

Elec condr (no.4) bare, TxDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20205252$1.75295$1.71
20214848$2.10221$2.18
20222727$3.00113$2.70
20233232$2.57106$2.63
20242424$3.0874$2.91
Elec condr (no.4) bare, TxDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Elec condr (no.4) bare, TxDOT: unit prices by district, all lettings
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Houston District84$2.12443$2.05
Fort Worth District22$2.7786$2.32
Austin District15$2.3157$2.28
Dallas District14$3.1547$3.00
Odessa District7$3.0028$3.00
Yoakum District7$2.7024$2.50
San Antonio District4$1.9523$2.00
Laredo District6$2.2620$2.10
Beaumont District4$2.6218$2.56
Lubbock District6$2.2516$2.20
Pharr District4$2.3816$2.15
Wichita Falls District3$1.839$1.83
Elec condr (no.4) bare, TxDOT: unit prices by district, all lettings

Districts with at least three low bids, over all lettings.

By quantity

Elec condr (no.4) bare, TxDOT: low bidder's median by quantity band
Quantity (LF)Low bidsLow-bid median
15 to 18545$2.47
190 to 50046$2.55
500 to 2,14546$2.28
2,176 to 30,27546$2.19
Elec condr (no.4) bare, TxDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest TxDOT contracts carrying Elec condr (no.4) bare
LetContractDistrictQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
02 AUG 202408243202Houston District3,110$3.05$2.92$2.654JAMES CONSTRUCTION GROUP, LLCTxDOT
01 AUG 202408243001Houston District3,556$2.75$2.75$2.702WEBBER, LLCTxDOT
10 JUL 202407243201Dallas District8,185$3.25$3.25$3.002AUSTIN BRIDGE & ROAD SERVICES, LPTxDOT
10 JUL 202407243227Fort Worth District600$5.90$5.95$2.822YUNEX LLCTxDOT
09 JUL 202407243001Fort Worth District2,054$3.10$3.10$3.502ZACHRY CONSTRUCTION CORPORATIONTxDOT
09 JUL 202407243008Fort Worth District100$3.00$3.00$3.251LIGHT IT UP ELECTRICTxDOT
06 JUN 202406243203Houston District360$2.60$2.45$1.752JAMES CONSTRUCTION GROUP, LLCTxDOT
06 JUN 202406243222Dallas District295$5.00$5.08$4.004DURABLE SPECIALTIES, INC.TxDOT
06 JUN 202406243227Dallas District1,080$3.00$2.69$2.902FNH CONSTRUCTION, LLCTxDOT
06 JUN 202406243231Houston District15$2.30$2.83$2.906SER CONSTRUCTION PARTNERS, LLCTxDOT
06 JUN 202406243248Beaumont District2,105$3.20$2.97$2.885TRAF-TEX, INC.TxDOT
05 JUN 202406243043San Antonio District1,090$3.35$2.92$2.904E-Z BEL CONSTRUCTION, LLCTxDOT
05 JUN 202406243052San Angelo District2,800$3.80$4.34$2.902LIGHT IT UP ELECTRICTxDOT
03 MAY 202405243201Yoakum District4,570$3.16$2.85$2.703PULICE CONSTRUCTION, INC.TxDOT
03 MAY 202405243202Fort Worth District231$2.92$2.90$2.705ZACHRY CONSTRUCTION CORPORATIONTxDOT
Latest TxDOT contracts carrying Elec condr (no.4) bare

Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.

How these prices were read

TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy