Tray cable (3 condr) (12 awg) unit price, Texas
Low bidders on TxDOT contracts carried a median of $3.50 per LF for item 621-7002, tray cable (3 condr) (12 awg), over the 24 months to 19 NOV 2026, across 43 low bids. Half of all 219 bids fell between $2.75 and $4.00.
- Owner
- Texas DOT
- Item
- 621-7002
- Unit
- LF
- Latest letting
- 04 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2024 | 1 | 1 | $2.00 | 4 | $2.71 |
| 2025 | 22 | 22 | $3.38 | 87 | $3.20 |
| 2026 | 21 | 21 | $3.55 | 132 | $3.25 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Dallas District | 11 | $3.96 | 60 | $3.80 |
| Laredo District | 9 | $3.25 | 36 | $3.23 |
| San Antonio District | 6 | $2.48 | 35 | $2.50 |
| Paris District | 4 | $3.75 | 25 | $3.50 |
| Fort Worth District | 5 | $4.33 | 25 | $3.20 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 25 to 400 | 10 | $3.52 |
| 430 to 1,075 | 11 | $4.00 |
| 1,170 to 2,485 | 11 | $3.97 |
| 2,606 to 7,626 | 11 | $3.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 04 NOV 2026 | A00196925 | Paris District | 540 | $3.25 | $3.50 | $3.13 | 9 | HIGHWAY 19 CONSTRUCTION LLC | TxDOT |
| 03 SEP 2026 | A00198323 | Dallas District | 750 | $7.00 | $3.48 | $3.50 | 8 | AMERICAN LIGHTING AND SIGNALIZATION, LLC | TxDOT |
| 06 AUG 2026 | A00193006 | Amarillo District | 915 | $4.00 | $3.94 | n/a | 3 | J. LEE MILLIGAN, INC. | TxDOT |
| 06 AUG 2026 | A00119935 | Laredo District | 4,775 | $5.89 | $3.31 | $5.00 | 4 | PULICE CONSTRUCTION, INC. | TxDOT |
| 02 JUL 2026 | A00220099 | Dallas District | 100 | $6.00 | $3.75 | $4.00 | 4 | AMERICAN LIGHTING AND SIGNALIZATION, LLC | TxDOT |
| 01 JUL 2026 | A00008199 | Fort Worth District | 1,720 | $2.90 | $2.76 | $3.50 | 6 | INDUS ROAD & BRIDGE, INC. | TxDOT |
| 01 JUL 2026 | A00193476 | San Antonio District | 1,360 | $1.50 | $2.50 | $2.40 | 7 | E-Z BEL CONSTRUCTION, LLC | TxDOT |
| 02 JUN 2026 | A00133020 | Laredo District | 223 | $3.55 | $3.63 | $3.25 | 7 | JAMES CONSTRUCTION GROUP, LLC | TxDOT |
| 02 JUN 2026 | A00064555 | Fort Worth District | 2,245 | $4.40 | $3.20 | $3.50 | 8 | REYES TX, INC. | TxDOT |
| 07 MAY 2026 | A00031457 | San Antonio District | 5,205 | $3.20 | $4.00 | $2.30 | 3 | WEBBER, LLC | TxDOT |
| 06 MAY 2026 | A00218096 | Dallas District | 5,377 | $3.96 | $3.96 | $4.00 | 7 | ICOS MANAGEMENT, LLC | TxDOT |
| 06 MAY 2026 | A00062245 | Fort Worth District | 1,775 | $4.33 | $4.17 | $3.00 | 6 | ED BELL CONSTRUCTION COMPANY | TxDOT |
| 06 MAY 2026 | A00059994 | San Antonio District | 2,485 | $2.35 | $2.55 | $3.00 | 5 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 08 APR 2026 | A00215203 | Laredo District | 25 | $4.50 | $4.50 | $3.36 | 3 | THE LEVY COMPANY, LLC | TxDOT |
| 07 APR 2026 | A00084334 | Laredo District | 4,335 | $3.00 | $3.24 | $2.80 | 7 | HUNTER INDUSTRIES, LTD. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.