Low bidders on TxDOT contracts carried a median of $1.10 per LF for item 620-7002, elec condr (no.14) insulated, over the 24 months to 19 NOV 2026, across 65 low bids. Half of all 326 bids fell between $0.98 and $1.70.
- Owner
- Texas DOT
- Item
- 620-7002
- Unit
- LF
- Latest letting
- 06 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2024 | 4 | 4 | $1.00 | 26 | $1.40 |
| 2025 | 33 | 33 | $1.25 | 151 | $1.20 |
| 2026 | 30 | 30 | $1.01 | 158 | $1.19 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Houston District | 25 | $1.03 | 155 | $1.17 |
| Austin District | 8 | $1.02 | 39 | $1.12 |
| San Antonio District | 7 | $1.00 | 38 | $1.10 |
| Dallas District | 5 | $2.50 | 24 | $2.50 |
| El Paso District | 5 | $1.80 | 15 | $1.78 |
| Beaumont District | 3 | $1.00 | 10 | $1.03 |
| Pharr District | 3 | $1.00 | 9 | $0.85 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 20 to 1,000 | 16 | $2.00 |
| 1,170 to 5,865 | 16 | $1.54 |
| 6,150 to 23,685 | 16 | $1.10 |
| 24,445 to 191,620 | 17 | $0.91 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 06 OCT 2026 | A00186301 | Waco District | 11,407 | $1.65 | $1.65 | $1.00 | 6 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 03 SEP 2026 | A00223018 | Maintenance Division District | 12,400 | $3.00 | $3.00 | $1.15 | 2 | LIGHT IT UP ELECTRIC | TxDOT |
| 06 AUG 2026 | A00191470 | Houston District | 5,865 | $1.58 | $1.58 | $1.00 | 9 | JAMES CONSTRUCTION GROUP, LLC | TxDOT |
| 06 AUG 2026 | A00216599 | Austin District | 100 | $0.50 | $1.00 | $0.25 | 5 | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., LLC | TxDOT |
| 06 AUG 2026 | A00119935 | Laredo District | 23,685 | $1.00 | $1.10 | $1.00 | 4 | PULICE CONSTRUCTION, INC. | TxDOT |
| 06 AUG 2026 | A00218304 | San Antonio District | 40,085 | $0.67 | $1.00 | $1.06 | 7 | SICE, INC. | TxDOT |
| 05 AUG 2026 | A00191471 | Houston District | 6,710 | $1.55 | $1.57 | n/a | 8 | JAMES CONSTRUCTION GROUP, LLC | TxDOT |
| 05 AUG 2026 | A00068611 | Houston District | 14,360 | $1.10 | $1.55 | $0.80 | 7 | SER CONSTRUCTION PARTNERS, LLC | TxDOT |
| 05 AUG 2026 | A00206808 | Houston District | 150,300 | $0.91 | $0.85 | $0.45 | 7 | ALBATROSS CONSTRUCTION LLC | TxDOT |
| 05 AUG 2026 | A00187841 | Odessa District | 1,000 | $3.00 | $3.00 | $0.91 | 1 | FNF CONSTRUCTION, INC. | TxDOT |
| 02 JUL 2026 | A00124174 | Lubbock District | 50,781 | $1.00 | $1.12 | $2.00 | 4 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. | TxDOT |
| 01 JUL 2026 | A00190685 | Houston District | 1,427 | $0.79 | $0.83 | $1.00 | 11 | HARPER BROTHERS CONSTRUCTION LLC | TxDOT |
| 03 JUN 2026 | A00063871 | El Paso District | 12,735 | $2.90 | $2.90 | $1.60 | 4 | JORDAN FOSTER CONSTRUCTION, LLC | TxDOT |
| 07 MAY 2026 | A00183308 | Pharr District | 18,099 | $1.00 | $0.75 | $1.00 | 5 | IOC COMPANY LLC | TxDOT |
| 07 MAY 2026 | A00031457 | San Antonio District | 39,193 | $0.95 | $1.00 | $1.20 | 3 | WEBBER, LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.