Low bidders on TxDOT contracts carried a median of $20.00 per CY for item 1106002, excavation (channel), from 09 JAN 2020 to 02 AUG 2024, across 330 low bids. Half of all 1,610 bids fell between $15.39 and $40.00.
- Owner
- Texas DOT
- Item
- 1106002
- Unit
- CY
- Latest letting
- 02 AUG 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 46 | 46 | $20.00 | 261 | $20.00 |
| 2021 | 70 | 69 | $15.00 | 387 | $20.00 |
| 2022 | 65 | 65 | $18.00 | 299 | $23.00 |
| 2023 | 85 | 85 | $27.00 | 335 | $30.00 |
| 2024 | 65 | 65 | $22.59 | 328 | $29.85 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Paris District | 46 | $22.50 | 207 | $25.00 |
| Yoakum District | 38 | $18.00 | 176 | $23.40 |
| Houston District | 29 | $13.08 | 156 | $16.57 |
| San Antonio District | 16 | $20.00 | 111 | $25.90 |
| Waco District | 22 | $20.00 | 100 | $22.00 |
| Bryan District | 15 | $20.80 | 90 | $28.50 |
| Fort Worth District | 13 | $27.00 | 77 | $20.00 |
| Wichita Falls District | 18 | $40.00 | 76 | $40.00 |
| Childress District | 13 | $20.00 | 69 | $25.00 |
| Austin District | 14 | $33.50 | 66 | $29.02 |
| Atlanta District | 10 | $17.00 | 64 | $20.00 |
| Tyler District | 10 | $22.50 | 59 | $25.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 5 to 195 | 82 | $38.75 |
| 195 to 540 | 83 | $20.00 |
| 540 to 1,618.40 | 82 | $20.00 |
| 1,650 to 528,844 | 83 | $14.10 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 02 AUG 2024 | 08243202 | Houston District | 24,762 | $15.57 | $21.50 | $14.00 | 4 | JAMES CONSTRUCTION GROUP, LLC | TxDOT |
| 01 AUG 2024 | 08243001 | Houston District | 528,844 | $15.48 | $17.74 | $25.00 | 2 | WEBBER, LLC | TxDOT |
| 10 JUL 2024 | 07243211 | Childress District | 3,827 | $34.55 | $25.00 | $20.00 | 5 | C. E. BARKER, LTD. | TxDOT |
| 10 JUL 2024 | 07243215 | Wichita Falls District | 98 | $75.00 | $125.00 | $50.00 | 4 | ZACK BURKETT CO. | TxDOT |
| 10 JUL 2024 | 07243219 | Austin District | 357 | $120.00 | $135.00 | $31.67 | 2 | SCR CIVIL CONSTRUCTION, LLC | TxDOT |
| 10 JUL 2024 | 07243224 | Childress District | 1,510 | $15.00 | $23.93 | $20.00 | 6 | SKYLINE BRIDGE LLC | TxDOT |
| 10 JUL 2024 | 07243228 | Paris District | 302 | $13.00 | $37.50 | $25.00 | 6 | L & N BRIDGE, LLC | TxDOT |
| 09 JUL 2024 | 07243010 | Beaumont District | 5 | $1,420.76 | $1,000.00 | $25.00 | 3 | TEXAS MATERIALS GROUP, INC. | TxDOT |
| 09 JUL 2024 | 07243015 | Yoakum District | 979 | $30.00 | $39.42 | $15.00 | 8 | STX CIVIL | TxDOT |
| 09 JUL 2024 | 07243019 | Bryan District | 540 | $24.00 | $30.00 | $50.00 | 7 | PMCO CONSTRUCTION LLC | TxDOT |
| 09 JUL 2024 | 07243025 | Childress District | 270 | $18.00 | $33.44 | $20.00 | 6 | SKYLINE BRIDGE LLC | TxDOT |
| 06 JUN 2024 | 06243202 | Houston District | 352,149 | $20.00 | $20.00 | $14.00 | 3 | HARPER BROTHERS CONSTRUCTION LLC | TxDOT |
| 06 JUN 2024 | 06243205 | Wichita Falls District | 3,490 | $26.00 | $30.00 | $8.00 | 3 | A. L. HELMCAMP, INC. | TxDOT |
| 06 JUN 2024 | 06243216 | Bryan District | 6,474 | $14.00 | $15.50 | $10.00 | 6 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 06 JUN 2024 | 06243218 | Waco District | 2,819 | $36.00 | $37.50 | $38.00 | 4 | KNIFE RIVER CORPORATION - SOUTH | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.