Excavation (roadway) unit price, Texas
Low bidders on TxDOT contracts carried a median of $15.86 per CY for item 1106001, excavation (roadway), from 09 JAN 2020 to 02 AUG 2024, across 1,210 low bids. Half of all 5,806 bids fell between $11.41 and $30.00.
- Owner
- Texas DOT
- Item
- 1106001
- Unit
- CY
- Latest letting
- 02 AUG 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 228 | 228 | $12.88 | 1,334 | $15.00 |
| 2021 | 289 | 289 | $12.18 | 1,581 | $15.00 |
| 2022 | 216 | 216 | $15.00 | 954 | $18.25 |
| 2023 | 281 | 280 | $22.00 | 1,068 | $25.00 |
| 2024 | 197 | 197 | $20.00 | 869 | $24.22 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Dallas District | 116 | $20.00 | 629 | $19.45 |
| Houston District | 102 | $17.50 | 542 | $16.93 |
| San Antonio District | 83 | $15.00 | 479 | $20.00 |
| Austin District | 84 | $15.12 | 451 | $16.94 |
| Yoakum District | 94 | $14.85 | 445 | $18.00 |
| Fort Worth District | 73 | $22.00 | 368 | $20.00 |
| Bryan District | 53 | $17.86 | 289 | $21.00 |
| Corpus Christi District | 44 | $12.96 | 237 | $15.00 |
| Tyler District | 41 | $17.00 | 209 | $20.00 |
| Abilene District | 49 | $20.00 | 202 | $24.87 |
| Waco District | 46 | $15.00 | 197 | $20.00 |
| Odessa District | 41 | $12.00 | 170 | $12.43 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 1 to 521 | 302 | $30.00 |
| 522 to 3,803 | 303 | $19.72 |
| 3,857 to 20,769 | 302 | $14.72 |
| 20,771 to 1,326,352 | 303 | $10.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 02 AUG 2024 | 08243201 | Pharr District | 57,260 | $7.50 | $5.00 | $6.00 | 3 | FOREMOST PAVING, INC. | TxDOT |
| 02 AUG 2024 | 08243202 | Houston District | 9,759 | $6.31 | $23.50 | $24.00 | 4 | JAMES CONSTRUCTION GROUP, LLC | TxDOT |
| 02 AUG 2024 | 08243203 | San Angelo District | 100 | $277.92 | $100.00 | $20.00 | 5 | RK HALL, LLC | TxDOT |
| 01 AUG 2024 | 08243001 | Houston District | 53,412 | $15.71 | $20.36 | $25.00 | 2 | WEBBER, LLC | TxDOT |
| 01 AUG 2024 | 08243002 | Pharr District | 123,179 | $4.50 | $8.00 | $6.00 | 5 | FOREMOST PAVING, INC. | TxDOT |
| 10 JUL 2024 | 07243201 | Dallas District | 607,316 | $21.70 | $21.70 | $15.00 | 2 | AUSTIN BRIDGE & ROAD SERVICES, LP | TxDOT |
| 10 JUL 2024 | 07243203 | Pharr District | 71,696 | $5.00 | $5.92 | $8.50 | 4 | FOREMOST PAVING, INC. | TxDOT |
| 10 JUL 2024 | 07243204 | Yoakum District | 19,705 | $17.50 | $15.00 | $23.00 | 6 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 10 JUL 2024 | 07243205 | Laredo District | 7,205 | $22.00 | $19.40 | $13.00 | 4 | ANDERSON COLUMBIA CO., INC. | TxDOT |
| 10 JUL 2024 | 07243207 | Dallas District | 14,324 | $20.00 | $20.00 | $30.00 | 6 | HARPER BROTHERS CONSTRUCTION LLC | TxDOT |
| 10 JUL 2024 | 07243208 | San Antonio District | 11,822 | $10.30 | $29.06 | $24.88 | 8 | ACME BRIDGE COMPANY, INC. | TxDOT |
| 10 JUL 2024 | 07243211 | Childress District | 5,746 | $30.85 | $25.00 | $25.00 | 5 | C. E. BARKER, LTD. | TxDOT |
| 10 JUL 2024 | 07243212 | Bryan District | 18,936 | $15.00 | $19.50 | $27.00 | 5 | LARRY YOUNG PAVING, INC. | TxDOT |
| 10 JUL 2024 | 07243215 | Wichita Falls District | 3,995 | $30.81 | $51.50 | $35.00 | 4 | ZACK BURKETT CO. | TxDOT |
| 10 JUL 2024 | 07243218 | Lufkin District | 1,175 | $64.03 | $40.00 | $35.00 | 3 | TI-ZACK CONCRETE, LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.