Low bidders on TxDOT contracts carried a median of $2,500.00 per EACH for item 644-7061, in bridge mnt clearance sgn assm(ty n), over the 24 months to 19 NOV 2026, across 69 low bids. Half of all 376 bids fell between $2,175.00 and $3,334.95.

Owner
Texas DOT
Item
644-7061
Unit
EACH
Latest letting
04 NOV 2026
$2,500.00Low bidder's median, per EACH
$2,700.00Median of all bids, per EACH
69Contracts in the window
$2,500.00Engineer's estimate, median per EACH

By year of letting

In bridge mnt clearance sgn assm(ty n), TxDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202433$3,990.0010$3,245.00
20253434$2,400.00177$2,800.00
20263333$2,500.00194$2,607.27
In bridge mnt clearance sgn assm(ty n), TxDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

In bridge mnt clearance sgn assm(ty n), TxDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Dallas District14$3,259.0066$3,287.72
Austin District9$1,800.0061$2,200.00
San Antonio District9$2,200.0054$2,278.86
Houston District10$1,700.0050$2,825.00
Waco District4$2,593.5024$3,080.05
Fort Worth District3$3,200.0024$2,875.00
Pharr District4$2,500.0018$2,500.00
El Paso District3$2,700.0014$2,947.50
In bridge mnt clearance sgn assm(ty n), TxDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

In bridge mnt clearance sgn assm(ty n), TxDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 217$3,200.00
2 to 417$2,500.00
4 to 617$2,354.40
6 to 5018$2,084.55
In bridge mnt clearance sgn assm(ty n), TxDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest TxDOT contracts carrying In bridge mnt clearance sgn assm(ty n)
LetContractDistrictQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
04 NOV 2026A00212892Dallas District2$3,400.00$3,340.00$2,200.006INDUS ROAD & BRIDGE, INC.TxDOT
03 NOV 2026A00215476Austin District50$1,800.00$2,000.00$1,900.007RHINO EQUITY, LLCTxDOT
03 NOV 2026A00184974Austin District14$2,800.00$2,345.06$3,700.006AUSTIN BRIDGE & ROAD SERVICES, LPTxDOT
15 OCT 2026A00222534Waco District3$1,800.00$2,200.00$2,200.007RHINO EQUITY, LLCTxDOT
13 OCT 2026A00223740Houston District20$1,800.00$2,329.37$1,769.202RHINO EQUITY, LLCTxDOT
09 SEP 2026A00215473Austin District27$1,250.00$1,425.00$2,100.004RARE EARTH LANDSCAPE SOLUTIONS LLCTxDOT
02 SEP 2026A00121174Pharr District4$2,250.00$2,497.50$2,800.007IOC COMPANY LLCTxDOT
06 AUG 2026A00062075Fort Worth District2$3,200.00$3,170.00$2,500.007INDUS ROAD & BRIDGE, INC.TxDOT
06 AUG 2026A00119935Laredo District6$2,354.40$2,400.92$3,220.004PULICE CONSTRUCTION, INC.TxDOT
05 AUG 2026A00128458Amarillo District4$3,475.00$1,935.00$3,000.004J. LEE MILLIGAN, INC.TxDOT
05 AUG 2026A00007222Fort Worth District4$3,200.00$2,617.04n/a11INDUS ROAD & BRIDGE, INC.TxDOT
05 AUG 2026A00219217Waco District1$4,000.00$5,750.00$2,500.004SCR CIVIL CONSTRUCTION, LLCTxDOT
14 JUL 2026A00218978Houston District30$1,600.00$1,740.20$2,000.003RHINO EQUITY, LLCTxDOT
02 JUL 2026A00124174Lubbock District7$2,175.00$2,305.47$2,900.004WILLIAMS BROTHERS CONSTRUCTION CO., INC.TxDOT
01 JUL 2026A00190685Houston District2$2,850.00$2,900.00$6,000.0011HARPER BROTHERS CONSTRUCTION LLCTxDOT
Latest TxDOT contracts carrying In bridge mnt clearance sgn assm(ty n)

Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.

How these prices were read

TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy