Relocate sm rd sn sup&am ty 10BWG unit price, Texas

Low bidders on TxDOT contracts carried a median of $607.50 per EACH for item 644-7065, relocate sm rd sn sup&am ty 10bwg, over the 24 months to 19 NOV 2026, across 172 low bids. Half of all 989 bids fell between $508.48 and $850.00.

Owner
Texas DOT
Item
644-7065
Unit
EACH
Latest letting
04 NOV 2026
$607.50Low bidder's median, per EACH
$660.00Median of all bids, per EACH
172Contracts in the window
$677.52Engineer's estimate, median per EACH

By year of letting

Relocate sm rd sn sup&am ty 10BWG, TxDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202466$560.5040$750.00
2025100100$625.57540$700.00
20267171$589.00440$648.00
Relocate sm rd sn sup&am ty 10BWG, TxDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Relocate sm rd sn sup&am ty 10BWG, TxDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Dallas District26$642.50154$703.30
Austin District20$497.50129$550.00
Paris District14$617.50105$669.00
Yoakum District9$574.3266$591.12
Houston District10$678.1258$628.07
Waco District9$500.0058$592.50
San Antonio District11$550.0055$650.00
Amarillo District12$733.7553$750.00
Bryan District6$517.5042$690.00
Odessa District8$699.3534$699.35
Lubbock District6$890.0034$752.00
Fort Worth District6$892.5033$650.00
Relocate sm rd sn sup&am ty 10BWG, TxDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Relocate sm rd sn sup&am ty 10BWG, TxDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 243$581.00
2 to 543$635.00
5 to 1243$650.00
12 to 13343$550.00
Relocate sm rd sn sup&am ty 10BWG, TxDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest TxDOT contracts carrying Relocate sm rd sn sup&am ty 10BWG
LetContractDistrictQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
04 NOV 2026A00206976Austin District3$635.00$605.00$500.009LONE STAR SITEWORK, LLCTxDOT
04 NOV 2026A00129572Dallas District4$635.00$581.50$610.004MARIO SINACOLA & SONS EXCAVATING, INC.TxDOT
03 NOV 2026A00184974Austin District29$350.00$368.11n/a6AUSTIN BRIDGE & ROAD SERVICES, LPTxDOT
03 NOV 2026A00206455Dallas District1$860.00$736.00$800.0013RCR TELECON LLCTxDOT
15 OCT 2026A00222534Waco District3$500.00$650.00$550.007RHINO EQUITY, LLCTxDOT
06 OCT 2026A00186301Waco District12$500.00$487.50$800.006BIG CREEK CONSTRUCTION, LTD.TxDOT
06 OCT 2026A00207050Lubbock District5$675.00$662.50$300.006GRATIOT CONSTRUCTION, LTD.TxDOT
03 SEP 2026A00191741Houston District4$500.00$500.00$750.007CASTILLO ARANDA LLCTxDOT
03 SEP 2026A00198323Dallas District1$500.00$735.00$750.008AMERICAN LIGHTING AND SIGNALIZATION, LLCTxDOT
03 SEP 2026A00139727Paris District2$880.00$550.00$500.008LONGVIEW BRIDGE AND ROAD, LTD.TxDOT
03 SEP 2026A00184246Lubbock District20$930.00$750.00$1,200.005GRATIOT CONSTRUCTION, LTD.TxDOT
03 SEP 2026A00207181Yoakum District30$547.30$545.72$600.0073LW CIVIL LLCTxDOT
02 SEP 2026A00206056Wichita Falls District5$650.00$768.90$700.007TIGHT LINE CONSTRUCTION, LLCTxDOT
11 AUG 2026A00221935Odessa District4$1,412.00$1,731.00$725.002SCOTT TUCKER CONSTRUCTION COMPANY, LLCTxDOT
06 AUG 2026A00197439Austin District2$574.46$565.41$500.007STX CIVILTxDOT
Latest TxDOT contracts carrying Relocate sm rd sn sup&am ty 10BWG

Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.

How these prices were read

TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy