Joint sealant unit price, Texas
Low bidders on TxDOT contracts carried a median of $16.75 per LF for item 4546009, joint sealant, from 07 FEB 2020 to 03 MAY 2024, across 66 low bids. Half of all 296 bids fell between $12.61 and $30.00.
- Owner
- Texas DOT
- Item
- 4546009
- Unit
- LF
- Latest letting
- 03 MAY 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 10 | 10 | $12.25 | 45 | $16.00 |
| 2021 | 22 | 22 | $15.18 | 126 | $18.00 |
| 2022 | 20 | 20 | $20.00 | 76 | $23.88 |
| 2023 | 10 | 10 | $43.20 | 35 | $25.52 |
| 2024 | 4 | 4 | $18.70 | 14 | $18.70 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| San Antonio District | 11 | $10.00 | 63 | $13.00 |
| Abilene District | 7 | $20.00 | 33 | $25.52 |
| Odessa District | 4 | $19.53 | 26 | $21.12 |
| Waco District | 8 | $14.50 | 25 | $15.00 |
| Fort Worth District | 3 | $20.00 | 17 | $23.74 |
| Beaumont District | 5 | $14.60 | 16 | $15.50 |
| Austin District | 5 | $13.00 | 16 | $18.99 |
| Amarillo District | 4 | $132.30 | 13 | $178.20 |
| Dallas District | 4 | $41.75 | 12 | $26.80 |
| Tyler District | 3 | $13.00 | 9 | $20.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 52 to 205 | 16 | $30.70 |
| 208 to 528 | 17 | $18.00 |
| 565.60 to 1,252.45 | 16 | $16.00 |
| 1,429 to 9,622 | 17 | $10.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 03 MAY 2024 | 05243212 | Abilene District | 400 | $19.80 | $19.80 | $27.00 | 1 | RK HALL, LLC | TxDOT |
| 06 MAR 2024 | 03243220 | Waco District | 266 | $25.00 | $42.00 | $20.00 | 4 | AMERICAN INFRASTRUCTURE MAINTENANCE MANAGEMENT LLC | TxDOT |
| 04 JAN 2024 | 01243015 | Austin District | 2,787 | $1.00 | $8.00 | $25.00 | 3 | LONE STAR PAVING COMPANY | TxDOT |
| 04 JAN 2024 | 01243021 | San Antonio District | 528 | $17.60 | $16.68 | $15.00 | 6 | CLARK CONSTRUCTION OF TEXAS, INC. | TxDOT |
| 07 SEP 2023 | 09233203 | Amarillo District | 162 | $170.00 | $174.10 | $40.00 | 4 | DUININCK, INC. | TxDOT |
| 07 SEP 2023 | 09233204 | San Antonio District | 2,156 | $7.50 | $7.50 | $20.00 | 6 | TEXAS MATERIALS GROUP, INC. | TxDOT |
| 27 JUN 2023 | 06233402 | Lufkin District | 205 | $100.00 | $52.50 | $50.00 | 2 | WEBBER, LLC | TxDOT |
| 02 JUN 2023 | 06233210 | Amarillo District | 160 | $187.92 | $185.00 | $45.00 | 3 | RK HALL, LLC | TxDOT |
| 01 JUN 2023 | 06233002 | San Antonio District | 2,731 | $12.50 | $12.50 | $8.00 | 3 | WEBBER, LLC | TxDOT |
| 01 JUN 2023 | 06233004 | Dallas District | 2,740 | $60.00 | $39.00 | $40.00 | 3 | FNH CONSTRUCTION, LLC | TxDOT |
| 05 MAY 2023 | 05233205 | San Angelo District | 6,418 | $10.00 | $10.33 | $10.50 | 3 | LONE STAR PAVING COMPANY | TxDOT |
| 05 MAY 2023 | 05233228 | Abilene District | 76 | $102.00 | $55.00 | $25.00 | 5 | SCR CIVIL CONSTRUCTION, LLC | TxDOT |
| 04 MAY 2023 | 05233014 | Abilene District | 160 | $26.40 | $63.20 | $38.00 | 2 | RK HALL, LLC | TxDOT |
| 08 MAR 2023 | 03233207 | Waco District | 132 | $15.00 | $15.00 | $16.18 | 4 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 02 DEC 2022 | 12223223 | Abilene District | 52 | $20.00 | $44.34 | $50.00 | 5 | CROSS PLUS CONSTRUCTION, LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way