Sealed expansion joint (4 in) (sej - b) unit price, Texas
Low bidders on TxDOT contracts carried a median of $140.00 per LF for item 4546020, sealed expansion joint (4 in) (sej - b), from 09 JAN 2020 to 02 AUG 2024, across 49 low bids. Half of all 262 bids fell between $101.26 and $170.68.
- Owner
- Texas DOT
- Item
- 4546020
- Unit
- LF
- Latest letting
- 02 AUG 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 10 | 10 | $100.82 | 76 | $100.00 |
| 2021 | 8 | 8 | $115.00 | 48 | $110.00 |
| 2022 | 6 | 6 | $138.50 | 26 | $125.50 |
| 2023 | 16 | 16 | $155.00 | 65 | $159.10 |
| 2024 | 9 | 9 | $160.00 | 47 | $167.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Dallas District | 15 | $136.00 | 111 | $125.00 |
| Fort Worth District | 8 | $135.50 | 31 | $147.64 |
| El Paso District | 4 | $166.80 | 18 | $163.91 |
| Bryan District | 3 | $100.00 | 14 | $135.00 |
| Pharr District | 3 | $179.00 | 13 | $179.00 |
| Houston District | 3 | $300.00 | 11 | $125.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 12 to 90 | 12 | $135.00 |
| 91 to 160 | 12 | $160.00 |
| 163 to 254 | 12 | $125.50 |
| 284 to 2,393 | 13 | $136.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 02 AUG 2024 | 08243203 | San Angelo District | 92 | $330.00 | $300.00 | $300.00 | 5 | RK HALL, LLC | TxDOT |
| 10 JUL 2024 | 07243207 | Dallas District | 288 | $136.00 | $143.00 | $160.00 | 6 | HARPER BROTHERS CONSTRUCTION LLC | TxDOT |
| 09 JUL 2024 | 07243001 | Fort Worth District | 1,615 | $160.00 | $167.50 | $155.00 | 2 | ZACHRY CONSTRUCTION CORPORATION | TxDOT |
| 09 JUL 2024 | 07243019 | Bryan District | 140 | $120.00 | $175.00 | $166.00 | 7 | PMCO CONSTRUCTION LLC | TxDOT |
| 06 JUN 2024 | 06243228 | Fort Worth District | 102 | $250.00 | $250.00 | $145.00 | 2 | RAGLE CONSTRUCTION, INC. | TxDOT |
| 04 APR 2024 | 04243007 | Lufkin District | 82 | $200.00 | $200.00 | $200.00 | 2 | HODGES AND SON CONSTRUCTION COMPANY, INC. | TxDOT |
| 05 MAR 2024 | 03243004 | Dallas District | 306 | $140.00 | $144.03 | $110.00 | 7 | INDUS ROAD & BRIDGE, INC. | TxDOT |
| 02 FEB 2024 | 02243217 | Dallas District | 252 | $180.00 | $168.50 | $150.00 | 10 | HIGHWAY 19 CONSTRUCTION LLC | TxDOT |
| 04 JAN 2024 | 01243001 | Dallas District | 310 | $160.00 | $119.93 | $120.00 | 6 | MARIO SINACOLA & SONS EXCAVATING, INC. | TxDOT |
| 01 NOV 2023 | 11233007 | Dallas District | 109 | $135.00 | $600.00 | $160.00 | 5 | RAGLE CONSTRUCTION, INC. | TxDOT |
| 03 AUG 2023 | 08233205 | Fort Worth District | 314 | $105.29 | $154.55 | $190.00 | 4 | SEMA CONSTRUCTION, INC. | TxDOT |
| 28 JUN 2023 | 06233611 | Pharr District | 186 | $175.00 | $187.50 | $175.00 | 4 | FOREMOST PAVING, INC. | TxDOT |
| 28 JUN 2023 | 06233614 | Bryan District | 254 | $100.00 | $135.45 | $200.00 | 4 | A. L. HELMCAMP, INC. | TxDOT |
| 27 JUN 2023 | 06233418 | El Paso District | 136 | $160.00 | $205.00 | $300.00 | 2 | DAN WILLIAMS COMPANY | TxDOT |
| 27 JUN 2023 | 06233438 | Fort Worth District | 67 | $150.00 | $150.00 | $150.00 | 5 | HARPER BROTHERS CONSTRUCTION LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.