Port ctb (des source)(f-shape)(ty 1) unit price, Texas
Low bidders on TxDOT contracts carried a median of $18.15 per LF for item 5126017, port ctb (des source)(f-shape)(ty 1), from 07 FEB 2020 to 05 JUN 2024, across 84 low bids. Half of all 383 bids fell between $11.75 and $29.75.
- Owner
- Texas DOT
- Item
- 5126017
- Unit
- LF
- Latest letting
- 05 JUN 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 21 | 21 | $19.25 | 117 | $20.00 |
| 2021 | 26 | 25 | $12.00 | 132 | $18.00 |
| 2022 | 13 | 13 | $15.00 | 44 | $20.00 |
| 2023 | 15 | 15 | $20.00 | 59 | $25.00 |
| 2024 | 10 | 10 | $22.50 | 31 | $25.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| El Paso District | 25 | $10.00 | 105 | $11.00 |
| Paris District | 18 | $24.95 | 78 | $25.00 |
| Fort Worth District | 8 | $15.75 | 61 | $20.00 |
| Amarillo District | 15 | $16.50 | 59 | $20.00 |
| Lubbock District | 4 | $45.25 | 19 | $25.00 |
| Tyler District | 4 | $20.50 | 18 | $25.00 |
| Houston District | 3 | $25.00 | 11 | $30.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 30 to 570 | 21 | $22.50 |
| 570 to 977 | 21 | $25.00 |
| 1,000 to 2,640 | 21 | $13.50 |
| 2,640 to 36,170 | 21 | $11.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 05 JUN 2024 | 06243020 | Lubbock District | 750 | $85.80 | $25.00 | $35.00 | 5 | TI-ZACK CONCRETE, LLC | TxDOT |
| 02 MAY 2024 | 05243003 | Waco District | 360 | $20.00 | $20.50 | $19.00 | 4 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 02 MAY 2024 | 05243006 | El Paso District | 6,840 | $15.00 | $15.00 | $12.00 | 3 | JAMES HAMILTON CONSTRUCTION CO. | TxDOT |
| 02 MAY 2024 | 05243008 | El Paso District | 8,580 | $12.27 | $12.27 | $7.91 | 1 | VEMAC, LLC | TxDOT |
| 04 APR 2024 | 04243017 | El Paso District | 720 | $9.00 | $18.38 | $3.00 | 4 | DAN WILLIAMS COMPANY | TxDOT |
| 05 MAR 2024 | 03243001 | Tyler District | 240 | $35.00 | $35.00 | $30.00 | 5 | LAMAR COMPANIES LLC | TxDOT |
| 05 MAR 2024 | 03243010 | Amarillo District | 600 | $35.19 | $28.20 | $30.00 | 4 | ALTUS CONSTRUCTION LLC | TxDOT |
| 02 FEB 2024 | 02243216 | Wichita Falls District | 175 | $50.00 | $82.50 | $20.00 | 2 | JAGOE-PUBLIC COMPANY | TxDOT |
| 01 FEB 2024 | 02243011 | Amarillo District | 600 | $25.00 | $24.50 | $30.00 | 2 | GILVIN-TERRILL, LTD. | TxDOT |
| 05 JAN 2024 | 01243208 | El Paso District | 1,620 | $10.00 | $10.00 | $11.50 | 1 | DAN WILLIAMS COMPANY | TxDOT |
| 05 DEC 2023 | 12233007 | Amarillo District | 1,620 | $25.00 | $25.00 | $35.00 | 5 | BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC | TxDOT |
| 05 DEC 2023 | 12233022 | Paris District | 1,000 | $15.00 | $24.11 | $23.00 | 6 | GARRET SHIELDS INFRASTRUCTURE | TxDOT |
| 02 NOV 2023 | 11233217 | Lubbock District | 880 | $55.00 | $41.00 | $35.00 | 7 | ICOS MANAGEMENT, LLC | TxDOT |
| 01 NOV 2023 | 11233005 | El Paso District | 7,410 | $3.25 | $15.00 | $15.00 | 3 | LESNA CONSTRUCTION, INC. | TxDOT |
| 01 NOV 2023 | 11233006 | Tyler District | 630 | $29.00 | $30.00 | $20.00 | 5 | MADDEN CONTRACTING COMPANY, LLC. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way