Port ctb (fur & inst)(low prof)(ty 2) unit price, Texas
Low bidders on TxDOT contracts carried a median of $56.00 per LF for item 5126010, port ctb (fur & inst)(low prof)(ty 2), from 09 JAN 2020 to 02 AUG 2024, across 237 low bids. Half of all 1,115 bids fell between $37.38 and $84.00.
- Owner
- Texas DOT
- Item
- 5126010
- Unit
- LF
- Latest letting
- 02 AUG 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 46 | 46 | $37.25 | 255 | $49.08 |
| 2021 | 60 | 60 | $40.00 | 354 | $50.83 |
| 2022 | 45 | 45 | $68.50 | 179 | $61.00 |
| 2023 | 42 | 42 | $61.50 | 147 | $70.00 |
| 2024 | 45 | 44 | $77.15 | 180 | $75.20 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| San Antonio District | 39 | $32.00 | 239 | $45.00 |
| Dallas District | 24 | $50.00 | 125 | $50.00 |
| Houston District | 23 | $51.30 | 107 | $62.00 |
| Austin District | 18 | $45.02 | 95 | $45.47 |
| Fort Worth District | 17 | $70.00 | 77 | $65.00 |
| Yoakum District | 16 | $77.15 | 73 | $60.00 |
| Bryan District | 10 | $31.10 | 59 | $60.00 |
| Odessa District | 10 | $79.50 | 49 | $61.48 |
| Pharr District | 12 | $44.50 | 48 | $35.00 |
| Corpus Christi District | 9 | $25.00 | 36 | $48.77 |
| Laredo District | 9 | $50.00 | 36 | $57.00 |
| Wichita Falls District | 8 | $85.25 | 34 | $75.50 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 20 to 80 | 59 | $75.00 |
| 80 to 160 | 59 | $63.00 |
| 160 to 440 | 59 | $44.00 |
| 460 to 4,400 | 60 | $53.73 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 02 AUG 2024 | 08243202 | Houston District | 300 | $70.67 | $75.34 | $69.00 | 4 | JAMES CONSTRUCTION GROUP, LLC | TxDOT |
| 01 AUG 2024 | 08243001 | Houston District | 320 | $95.03 | $67.52 | $57.00 | 2 | WEBBER, LLC | TxDOT |
| 10 JUL 2024 | 07243201 | Dallas District | 980 | $85.00 | $72.50 | $45.00 | 2 | AUSTIN BRIDGE & ROAD SERVICES, LP | TxDOT |
| 10 JUL 2024 | 07243207 | Dallas District | 100 | $61.00 | $72.50 | $40.00 | 6 | HARPER BROTHERS CONSTRUCTION LLC | TxDOT |
| 10 JUL 2024 | 07243208 | San Antonio District | 80 | $40.80 | $105.00 | $56.12 | 8 | ACME BRIDGE COMPANY, INC. | TxDOT |
| 09 JUL 2024 | 07243001 | Fort Worth District | 500 | $91.67 | $100.84 | $70.00 | 2 | ZACHRY CONSTRUCTION CORPORATION | TxDOT |
| 09 JUL 2024 | 07243005 | Abilene District | 40 | $140.00 | $105.00 | $35.00 | 3 | FNF CONSTRUCTION, INC. | TxDOT |
| 06 JUN 2024 | 06243201 | San Antonio District | 840 | $74.23 | $103.00 | $100.00 | 5 | WEBBER, LLC | TxDOT |
| 06 JUN 2024 | 06243203 | Houston District | 2,820 | $35.26 | $71.63 | $15.00 | 2 | JAMES CONSTRUCTION GROUP, LLC | TxDOT |
| 06 JUN 2024 | 06243205 | Wichita Falls District | 40 | $120.00 | $120.00 | $52.00 | 3 | A. L. HELMCAMP, INC. | TxDOT |
| 06 JUN 2024 | 06243208 | Houston District | 740 | $30.00 | $68.74 | $20.00 | 6 | R CONSTRUCTION CIVIL, LLC | TxDOT |
| 06 JUN 2024 | 06243215 | San Antonio District | 160 | n/a | $47.00 | $80.00 | 7 | SALINAS CONSTRUCTION TECHNOLOGIES, LTD. | TxDOT |
| 06 JUN 2024 | 06243228 | Fort Worth District | 40 | $120.00 | $110.00 | $65.00 | 2 | RAGLE CONSTRUCTION, INC. | TxDOT |
| 06 JUN 2024 | 06243254 | Yoakum District | 40 | $88.00 | $88.00 | $70.00 | 5 | STX CIVIL | TxDOT |
| 05 JUN 2024 | 06243008 | Wichita Falls District | 40 | $175.00 | $132.80 | $140.00 | 4 | A. L. HELMCAMP, INC. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.