Prime coat (ae-p) unit price, Texas
Low bidders on TxDOT contracts carried a median of $5.50 per GAL for item 310-7001, prime coat (ae-p), over the 24 months to 19 NOV 2026, across 63 low bids. Half of all 286 bids fell between $5.00 and $10.50.
- Owner
- Texas DOT
- Item
- 310-7001
- Unit
- GAL
- Latest letting
- 04 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2024 | 3 | 3 | $6.00 | 10 | $5.55 |
| 2025 | 34 | 34 | $4.69 | 144 | $5.65 |
| 2026 | 28 | 28 | $7.05 | 137 | $7.75 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Odessa District | 28 | $4.91 | 79 | $5.29 |
| Beaumont District | 12 | $6.59 | 52 | $7.50 |
| Austin District | 6 | $4.47 | 49 | $5.00 |
| Bryan District | 4 | $8.25 | 28 | $9.75 |
| Fort Worth District | 3 | $12.00 | 22 | $20.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (GAL) | Low bids | Low-bid median |
|---|---|---|
| 19 to 470 | 15 | $12.00 |
| 473 to 1,908 | 16 | $8.00 |
| 2,012 to 9,667 | 16 | $4.63 |
| 11,763 to 98,092 | 16 | $4.69 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 04 NOV 2026 | A00124162 | Bryan District | 266 | $6.50 | $9.47 | n/a | 12 | FLUOR ENTERPRISES, INC. | TxDOT |
| 03 NOV 2026 | A00188510 | Fort Worth District | 290 | $9.00 | $9.50 | $10.00 | 8 | JAY MILLS CONTRACTING, INCORPORATED | TxDOT |
| 03 NOV 2026 | A00223911 | Odessa District | 813 | $10.70 | $8.15 | $6.50 | 4 | RAGLE CONSTRUCTION, INC. | TxDOT |
| 11 AUG 2026 | A00221935 | Odessa District | 160 | $28.00 | $41.50 | $18.00 | 2 | SCOTT TUCKER CONSTRUCTION COMPANY, LLC | TxDOT |
| 06 AUG 2026 | A00193144 | Austin District | 1,908 | $5.17 | $5.10 | $5.00 | 7 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 06 AUG 2026 | A00192187 | Beaumont District | 139 | $10.00 | $12.84 | $15.00 | 6 | CASTILLO ARANDA LLC | TxDOT |
| 06 AUG 2026 | A00193174 | Fort Worth District | 57.80 | $55.00 | $41.30 | n/a | 5 | DURABLE SPECIALTIES, INC. | TxDOT |
| 06 AUG 2026 | A00187526 | Bryan District | 1,512 | $6.00 | $6.25 | $5.10 | 6 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 05 AUG 2026 | A00196824 | Bryan District | 83 | $10.00 | $10.25 | $10.00 | 6 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 05 AUG 2026 | A00187841 | Odessa District | 98,092 | $5.00 | $5.00 | $5.00 | 1 | FNF CONSTRUCTION, INC. | TxDOT |
| 05 AUG 2026 | A00193149 | Austin District | 3,450 | $5.00 | $5.00 | $5.00 | 6 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 02 JUL 2026 | A00208465 | Odessa District | 4,910 | $6.50 | $6.38 | $5.00 | 2 | GILVIN-TERRILL, LTD. | TxDOT |
| 01 JUL 2026 | A00080576 | Odessa District | 39,409 | $4.60 | $4.60 | $5.00 | 5 | JONES BROS. DIRT & PAVING CONTRACTORS, INC. | TxDOT |
| 01 JUL 2026 | A00215754 | Beaumont District | 2,962 | $8.00 | $4.89 | $5.00 | 4 | ELITE CONTRACTORS AND EQUIPMENT LTD | TxDOT |
| 03 JUN 2026 | A00183477 | Beaumont District | 575 | $7.00 | $12.50 | $7.45 | 4 | R CONSTRUCTION CIVIL, LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way