Low bidders on TxDOT contracts carried a median of $6.00 per GAL for item 310-7013, prime coat(mc-30 or ae-p), over the 24 months to 19 NOV 2026, across 111 low bids. Half of all 771 bids fell between $4.84 and $10.00.
- Owner
- Texas DOT
- Item
- 310-7013
- Unit
- GAL
- Latest letting
- 04 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2024 | 2 | 2 | $4.50 | 13 | $4.90 |
| 2025 | 52 | 52 | $5.42 | 335 | $6.00 |
| 2026 | 61 | 59 | $6.27 | 436 | $6.45 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Dallas District | 39 | $6.27 | 280 | $6.29 |
| San Antonio District | 21 | $4.95 | 135 | $5.00 |
| Fort Worth District | 16 | $9.00 | 115 | $8.50 |
| Austin District | 11 | $4.25 | 83 | $4.00 |
| Bryan District | 6 | $7.38 | 44 | $6.25 |
| San Angelo District | 6 | $8.54 | 31 | $7.17 |
| Waco District | 4 | $5.50 | 20 | $5.19 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (GAL) | Low bids | Low-bid median |
|---|---|---|
| 8 to 551 | 27 | $10.00 |
| 586 to 2,445 | 28 | $7.00 |
| 2,484 to 10,529 | 28 | $5.00 |
| 14,553 to 65,056 | 28 | $4.95 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 04 NOV 2026 | A00124162 | Bryan District | 24,532 | $4.20 | $4.90 | $6.00 | 12 | FLUOR ENTERPRISES, INC. | TxDOT |
| 04 NOV 2026 | A00222905 | Fort Worth District | 184 | $6.00 | $18.00 | $16.00 | 7 | XIT PAVING AND CONSTRUCTION INC. | TxDOT |
| 04 NOV 2026 | A00222974 | San Angelo District | 1,000 | $11.63 | $9.75 | $4.44 | 4 | REECE ALBERT, INC. | TxDOT |
| 07 OCT 2026 | A00064192 | San Antonio District | 46,109 | $4.94 | $4.00 | $4.54 | 8 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 06 OCT 2026 | A00066946 | Dallas District | 18,470 | $5.99 | $5.34 | $5.50 | 8 | A. K. GILLIS & SONS, LLC | TxDOT |
| 06 OCT 2026 | A00134683 | Houston District | 425 | $10.00 | $12.00 | $15.79 | 9 | GARRET SHIELDS INFRASTRUCTURE | TxDOT |
| 03 SEP 2026 | A00206794 | San Antonio District | 3,149 | $4.73 | $5.00 | $4.38 | 5 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 02 SEP 2026 | A00192185 | Houston District | 889 | $6.50 | $6.50 | $5.00 | 11 | R CONSTRUCTION CIVIL, LLC | TxDOT |
| 02 SEP 2026 | A00193937 | Dallas District | 588 | $6.97 | $6.97 | $4.75 | 7 | AUSTIN BRIDGE & ROAD SERVICES, LP | TxDOT |
| 06 AUG 2026 | A00187792 | Dallas District | 51,390 | $6.27 | $4.85 | $5.25 | 7 | D. L. LENNON INCORPORATED - CONTRACTOR | TxDOT |
| 06 AUG 2026 | A00062075 | Fort Worth District | 3,194 | $3.40 | $6.50 | $6.00 | 7 | INDUS ROAD & BRIDGE, INC. | TxDOT |
| 06 AUG 2026 | A00136986 | San Antonio District | 1,806 | $4.93 | $5.65 | $4.00 | 8 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 06 AUG 2026 | A00214454 | Fort Worth District | 270 | $10.00 | $22.50 | $15.00 | 8 | HODGES AND SON CONSTRUCTION COMPANY, INC. | TxDOT |
| 06 AUG 2026 | A00193246 | San Angelo District | 834 | $7.09 | $8.24 | $9.00 | 2 | REECE ALBERT, INC. | TxDOT |
| 06 AUG 2026 | A00140254 | San Angelo District | 10,234 | $5.00 | $5.50 | $8.00 | 6 | RAGLE CONSTRUCTION, INC. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way