Prime coat(mc-30 or ae-p) unit price, Texas
Low bidders on TxDOT contracts carried a median of $4.70 per GAL for item 3106027, prime coat(mc-30 or ae-p), from 09 JAN 2020 to 10 JUL 2024, across 101 low bids. Half of all 544 bids fell between $3.75 and $7.59.
- Owner
- Texas DOT
- Item
- 3106027
- Unit
- GAL
- Latest letting
- 10 JUL 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 15 | 15 | $3.83 | 123 | $4.44 |
| 2021 | 28 | 28 | $3.77 | 178 | $4.00 |
| 2022 | 15 | 15 | $5.00 | 69 | $5.05 |
| 2023 | 24 | 24 | $5.80 | 86 | $5.62 |
| 2024 | 19 | 19 | $7.00 | 88 | $7.97 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| San Antonio District | 43 | $4.25 | 256 | $4.08 |
| Dallas District | 21 | $8.00 | 118 | $8.85 |
| Waco District | 22 | $4.50 | 93 | $5.00 |
| Austin District | 6 | $3.56 | 40 | $3.85 |
| Wichita Falls District | 3 | $3.15 | 14 | $2.90 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (GAL) | Low bids | Low-bid median |
|---|---|---|
| 47 to 753 | 25 | $10.00 |
| 911 to 4,246 | 25 | $5.60 |
| 4,352 to 18,815 | 25 | $4.30 |
| 19,799 to 132,254 | 26 | $3.95 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 10 JUL 2024 | 07243207 | Dallas District | 4,184 | $8.00 | $8.18 | $10.00 | 6 | HARPER BROTHERS CONSTRUCTION LLC | TxDOT |
| 10 JUL 2024 | 07243208 | San Antonio District | 5,802 | $7.30 | $6.67 | $10.00 | 8 | ACME BRIDGE COMPANY, INC. | TxDOT |
| 06 JUN 2024 | 06243201 | San Antonio District | 58,278 | $4.00 | $4.30 | $5.50 | 5 | WEBBER, LLC | TxDOT |
| 06 JUN 2024 | 06243205 | Wichita Falls District | 24,070 | $7.00 | $7.00 | $4.50 | 3 | A. L. HELMCAMP, INC. | TxDOT |
| 06 JUN 2024 | 06243213 | Dallas District | 3,764 | $7.00 | $6.00 | $8.00 | 3 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 05 JUN 2024 | 06243007 | Dallas District | 16,154 | $6.75 | $7.50 | $8.57 | 3 | KNIFE RIVER CORPORATION - SOUTH | TxDOT |
| 03 MAY 2024 | 05243215 | San Antonio District | 297 | $5.50 | $8.92 | $11.19 | 7 | RELMCO, INC. | TxDOT |
| 03 MAY 2024 | 05243223 | Waco District | 1,442 | $7.50 | $7.70 | $8.00 | 5 | KNIFE RIVER CORPORATION - SOUTH | TxDOT |
| 03 MAY 2024 | 05243239 | San Antonio District | 121 | $10.00 | $15.70 | $5.00 | 4 | RELMCO, INC. | TxDOT |
| 02 MAY 2024 | 05243003 | Waco District | 8,876 | $5.00 | $5.25 | $8.00 | 4 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 05 APR 2024 | 04243220 | Waco District | 427 | $8.00 | $6.00 | $9.00 | 3 | KNIFE RIVER CORPORATION - SOUTH | TxDOT |
| 06 MAR 2024 | 03243209 | Dallas District | 189 | $14.00 | $15.40 | $8.00 | 5 | RAGLE CONSTRUCTION, INC. | TxDOT |
| 06 MAR 2024 | 03243210 | Dallas District | 704.20 | $12.00 | $12.00 | $11.00 | 5 | HODGES AND SON CONSTRUCTION COMPANY, INC. | TxDOT |
| 05 MAR 2024 | 03243017 | San Antonio District | 1,526 | $6.00 | $4.83 | $4.15 | 6 | J3 COMPANY, LLC | TxDOT |
| 02 FEB 2024 | 02243201 | Waco District | 32,668 | $4.42 | $4.25 | $6.00 | 3 | JAMES CONSTRUCTION GROUP, LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way