Refl pav mrk ty i (w)8"(dot)(100MIL) unit price, Texas
Low bidders on TxDOT contracts carried a median of $1.75 per LF for item 666-7018, refl pav mrk ty i (w)8"(dot)(100mil), over the 24 months to 19 NOV 2026, across 243 low bids. Half of all 1,209 bids fell between $1.14 and $2.40.
- Owner
- Texas DOT
- Item
- 666-7018
- Unit
- LF
- Latest letting
- 04 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2024 | 13 | 13 | $2.70 | 60 | $2.58 |
| 2025 | 118 | 116 | $2.00 | 515 | $1.90 |
| 2026 | 121 | 120 | $1.65 | 659 | $1.65 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Dallas District | 32 | $2.33 | 192 | $2.12 |
| Tyler District | 25 | $2.00 | 129 | $2.00 |
| Austin District | 23 | $1.50 | 115 | $2.00 |
| San Antonio District | 18 | $1.75 | 89 | $2.00 |
| Odessa District | 19 | $2.00 | 85 | $1.66 |
| Waco District | 14 | $1.15 | 77 | $1.25 |
| Bryan District | 9 | $1.65 | 60 | $1.83 |
| Lubbock District | 11 | $1.10 | 55 | $1.20 |
| Fort Worth District | 7 | $1.55 | 43 | $1.55 |
| Houston District | 11 | $1.75 | 41 | $1.75 |
| Abilene District | 6 | $1.54 | 40 | $1.17 |
| Pharr District | 11 | $3.60 | 34 | $3.74 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 8 to 100 | 60 | $2.01 |
| 100 to 240 | 61 | $2.10 |
| 240 to 750 | 61 | $1.65 |
| 797 to 18,710 | 61 | $1.20 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 04 NOV 2026 | A00206631 | Bryan District | 40 | $2.00 | $1.94 | $1.20 | 7 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 04 NOV 2026 | A00188206 | Austin District | 177 | $1.05 | $1.00 | $1.48 | 6 | BOBCAT SERVICES, INC. | TxDOT |
| 04 NOV 2026 | A00140672 | Abilene District | 710 | $1.00 | $1.06 | $1.50 | 9 | LONE STAR PAVING COMPANY | TxDOT |
| 03 NOV 2026 | A00190779 | El Paso District | 708 | $2.38 | $1.30 | $1.20 | 6 | ALLEN CONCRETE, LLC | TxDOT |
| 03 NOV 2026 | A00197970 | Pharr District | 240 | $2.53 | $2.83 | $3.88 | 2 | FOREMOST PAVING, INC. | TxDOT |
| 03 NOV 2026 | A00184974 | Austin District | 228 | $1.00 | $1.80 | $1.40 | 6 | AUSTIN BRIDGE & ROAD SERVICES, LP | TxDOT |
| 03 NOV 2026 | A00220202 | Wichita Falls District | 648 | $0.70 | $0.75 | n/a | 6 | BREEDON INVESTMENTS USA INC. | TxDOT |
| 03 NOV 2026 | A00223911 | Odessa District | 33 | $1.25 | $1.59 | $4.50 | 4 | RAGLE CONSTRUCTION, INC. | TxDOT |
| 03 NOV 2026 | A00196926 | Paris District | 850 | $1.50 | $0.97 | $1.84 | 4 | STRIPING TECHNOLOGY, L.P. | TxDOT |
| 07 OCT 2026 | A00131942 | San Angelo District | 271 | $1.00 | $1.00 | $1.00 | 7 | FLAT LINE, INC. | TxDOT |
| 06 OCT 2026 | A00195499 | Wichita Falls District | 104 | $2.00 | $2.10 | $0.90 | 5 | OVERLAND CORPORATION | TxDOT |
| 06 OCT 2026 | A00186301 | Waco District | 1,944 | $1.10 | $1.10 | $1.00 | 6 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 06 OCT 2026 | A00219476 | Tyler District | 350 | $2.00 | $2.00 | $1.50 | 2 | STRIPING TECHNOLOGY, L.P. | TxDOT |
| 03 SEP 2026 | A00184830 | Amarillo District | 113 | $1.50 | $1.60 | $1.50 | 7 | GILVIN-TERRILL, LTD. | TxDOT |
| 03 SEP 2026 | A00196194 | Atlanta District | 58 | $1.20 | $5.25 | $3.00 | 4 | LONGVIEW BRIDGE AND ROAD, LTD. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.