Refl pav mrk ty i (w)8"(sld)(060MIL) unit price, Texas
Low bidders on TxDOT contracts carried a median of $0.61 per LF for item 666-7022, refl pav mrk ty i (w)8"(sld)(060mil), over the 24 months to 19 NOV 2026, across 49 low bids. Half of all 227 bids fell between $0.60 and $1.00.
- Owner
- Texas DOT
- Item
- 666-7022
- Unit
- LF
- Latest letting
- 03 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2024 | 4 | 4 | $0.69 | 18 | $0.80 |
| 2025 | 21 | 21 | $0.60 | 111 | $0.75 |
| 2026 | 27 | 27 | $0.68 | 112 | $0.70 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Austin District | 8 | $0.56 | 50 | $0.68 |
| San Antonio District | 10 | $1.05 | 36 | $1.23 |
| Dallas District | 7 | $0.70 | 31 | $0.75 |
| Paris District | 3 | $0.65 | 19 | $0.57 |
| Fort Worth District | 4 | $0.65 | 15 | $0.80 |
| Wichita Falls District | 3 | $0.60 | 15 | $0.60 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 250 to 2,055 | 12 | $1.00 |
| 3,088 to 15,000 | 12 | $0.62 |
| 15,000 to 30,416 | 12 | $0.60 |
| 34,324 to 112,000 | 13 | $0.57 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 03 NOV 2026 | A00197271 | Austin District | 21,645 | $0.50 | $0.53 | $0.58 | 4 | TRP INFRASTRUCTURE SERVICES, LLC | TxDOT |
| 03 NOV 2026 | A00220202 | Wichita Falls District | 66,784 | $0.60 | $0.60 | n/a | 6 | BREEDON INVESTMENTS USA INC. | TxDOT |
| 03 NOV 2026 | A00196926 | Paris District | 85,178 | $0.68 | $0.61 | $0.65 | 4 | STRIPING TECHNOLOGY, L.P. | TxDOT |
| 06 OCT 2026 | A00219449 | Brownwood District | 30,416 | $0.48 | $0.67 | $0.83 | 7 | DOUBLE A CONTRACTING, L.P. | TxDOT |
| 06 OCT 2026 | A00219476 | Tyler District | 12,000 | $0.60 | $0.80 | $0.75 | 2 | STRIPING TECHNOLOGY, L.P. | TxDOT |
| 08 SEP 2026 | A00220768 | Houston District | 1,000 | $1.00 | $1.00 | $0.50 | 1 | TRP INFRASTRUCTURE SERVICES, LLC | TxDOT |
| 05 AUG 2026 | A00196824 | Bryan District | 1,427 | $1.00 | $0.95 | n/a | 6 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 05 AUG 2026 | A00222959 | Corpus Christi District | 60,000 | $0.58 | $0.58 | $0.50 | 3 | TRP INFRASTRUCTURE SERVICES, LLC | TxDOT |
| 08 JUL 2026 | A00219981 | Dallas District | 4,505 | $0.75 | $0.71 | $0.55 | 2 | STRIPE-A-ZONE, LLC | TxDOT |
| 02 JUN 2026 | A00221074 | Wichita Falls District | 25,000 | $0.61 | $0.63 | $1.50 | 2 | TRP INFRASTRUCTURE SERVICES, LLC | TxDOT |
| 02 JUN 2026 | A00196419 | San Antonio District | 3,934 | $2.00 | $1.93 | $1.00 | 5 | TAYLOR BRIDGE LLC | TxDOT |
| 02 JUN 2026 | A00196423 | San Antonio District | 20,000 | $0.60 | $0.70 | $0.90 | 3 | INTERSTATE BARRICADES & MARKINGS, INC. | TxDOT |
| 13 MAY 2026 | A00218146 | Dallas District | 260 | $1.00 | $0.80 | $0.57 | 2 | D. I. J. CONSTRUCTION, INC. | TxDOT |
| 07 MAY 2026 | A00206590 | Fort Worth District | 500 | $0.80 | $1.00 | $0.59 | 3 | TRP INFRASTRUCTURE SERVICES, LLC | TxDOT |
| 06 MAY 2026 | A00196412 | San Antonio District | 250 | $1.55 | $1.84 | $1.00 | 3 | E-Z BEL CONSTRUCTION, LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.