Replace single gdrail terminal rail unit price, Texas
Low bidders on TxDOT contracts carried a median of $35.00 per LF for item 770-7016, replace single gdrail terminal rail, over the 24 months to 19 NOV 2026, across 80 low bids. Half of all 300 bids fell between $29.75 and $50.00.
- Owner
- Texas DOT
- Item
- 770-7016
- Unit
- LF
- Latest letting
- 19 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2024 | 2 | 2 | $24.00 | 13 | $28.00 |
| 2025 | 55 | 53 | $38.00 | 210 | $40.00 |
| 2026 | 25 | 25 | $35.00 | 77 | $40.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Houston District | 15 | $30.00 | 66 | $33.00 |
| Lufkin District | 13 | $40.00 | 44 | $50.00 |
| Dallas District | 6 | $15.00 | 23 | $29.00 |
| Atlanta District | 6 | $42.50 | 19 | $42.84 |
| Beaumont District | 3 | $120.00 | 18 | $52.50 |
| Fort Worth District | 3 | $50.00 | 17 | $35.00 |
| Bryan District | 5 | $40.00 | 17 | $35.00 |
| Paris District | 4 | $30.00 | 14 | $37.00 |
| Austin District | 4 | $62.50 | 14 | $50.00 |
| El Paso District | 3 | $27.00 | 12 | $36.00 |
| Abilene District | 3 | $40.00 | 10 | $35.00 |
| San Antonio District | 3 | $35.00 | 8 | $32.50 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 5 to 110 | 20 | $50.00 |
| 200 to 500 | 20 | $45.00 |
| 500 to 1,600 | 20 | $30.00 |
| 1,900 to 5,700 | 20 | $27.50 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 19 NOV 2026 | A00224139 | Paris District | 600 | $30.00 | $35.00 | $35.00 | 2 | AUSTIN BARRICADE COMPANY, L.L.C. | TxDOT |
| 12 AUG 2026 | A00223094 | Bryan District | 500 | $30.00 | $30.00 | $35.00 | 2 | RHINO EQUITY, LLC | TxDOT |
| 11 AUG 2026 | A00223019 | Bryan District | 500 | $30.00 | $27.50 | $35.00 | 2 | T&L CLEANING SERVICES LLC | TxDOT |
| 14 JUL 2026 | A00220506 | Houston District | 1,600 | $10.00 | $31.50 | $18.00 | 4 | T&L CLEANING SERVICES LLC | TxDOT |
| 01 JUL 2026 | A00218278 | Dallas District | 250 | $10.00 | $15.00 | $35.20 | 2 | ROY JORGENSEN ASSOCIATES, INC. | TxDOT |
| 09 JUN 2026 | A00220019 | Houston District | 2,000 | $24.00 | $27.00 | $39.63 | 2 | ROY JORGENSEN ASSOCIATES, INC. | TxDOT |
| 27 MAY 2026 | A00221790 | Amarillo District | 100 | $64.62 | $30.00 | $30.00 | 3 | TI-ZACK CONCRETE, LLC | TxDOT |
| 13 MAY 2026 | A00220031 | Lufkin District | 215 | $10.00 | $35.00 | $45.00 | 3 | BK FIELD OPERATIONS LLC | TxDOT |
| 13 MAY 2026 | A00220032 | Lufkin District | 25 | $50.00 | $125.00 | $45.00 | 3 | ACE CONTRACTORS, INC. | TxDOT |
| 13 MAY 2026 | A00219922 | Austin District | 2,000 | $50.00 | $40.00 | $32.00 | 4 | RHINO EQUITY, LLC | TxDOT |
| 12 MAY 2026 | A00220799 | Tyler District | 500 | $43.00 | $43.00 | $40.00 | 1 | CATOCON, INC. | TxDOT |
| 12 MAY 2026 | A00218435 | Tyler District | 300 | $40.00 | $40.00 | $40.00 | 1 | CATOCON, INC. | TxDOT |
| 16 APR 2026 | A00212377 | San Angelo District | 800 | $30.00 | $30.00 | $35.00 | 4 | T&L CLEANING SERVICES LLC | TxDOT |
| 14 APR 2026 | A00218618 | Houston District | 1,500 | $5.00 | $40.00 | $19.00 | 3 | ROSS SA ENTERPRISE LLC | TxDOT |
| 18 MAR 2026 | A00218937 | Atlanta District | 250 | $60.00 | $50.00 | $32.00 | 3 | CATOCON, INC. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.