Retaining wall (cast - in - place) unit price, Texas
Low bidders on TxDOT contracts carried a median of $75.00 per SF for item 4236008, retaining wall (cast - in - place), from 09 JAN 2020 to 03 AUG 2023, across 63 low bids. Half of all 324 bids fell between $62.98 and $105.00.
- Owner
- Texas DOT
- Item
- 4236008
- Unit
- SF
- Latest letting
- 03 AUG 2023
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 23 | 23 | $70.00 | 131 | $80.00 |
| 2021 | 15 | 15 | $70.00 | 95 | $75.00 |
| 2022 | 17 | 17 | $90.00 | 80 | $96.28 |
| 2023 | 8 | 8 | $100.26 | 18 | $110.26 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Houston District | 10 | $80.85 | 64 | $80.00 |
| Dallas District | 11 | $76.00 | 62 | $84.41 |
| Austin District | 7 | $82.00 | 42 | $79.70 |
| San Antonio District | 5 | $69.00 | 28 | $80.00 |
| Fort Worth District | 4 | $80.00 | 24 | $85.00 |
| San Angelo District | 3 | $90.00 | 17 | $100.00 |
| Brownwood District | 3 | $68.00 | 7 | $68.00 |
| Beaumont District | 3 | $100.00 | 7 | $99.50 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (SF) | Low bids | Low-bid median |
|---|---|---|
| 10 to 366 | 15 | $93.50 |
| 376 to 1,191 | 16 | $72.50 |
| 1,338 to 4,412 | 16 | $73.00 |
| 4,428 to 35,632 | 16 | $73.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 03 AUG 2023 | 08233246 | Houston District | 30 | $150.00 | $150.00 | $72.62 | 1 | MAIN LANE INDUSTRIES LTD. | TxDOT |
| 02 AUG 2023 | 08233025 | Beaumont District | 95 | $330.75 | $330.75 | $106.00 | 1 | TEXAS MATERIALS GROUP, INC. | TxDOT |
| 02 AUG 2023 | 08233053 | Houston District | 10 | $50.00 | $50.00 | $72.62 | 1 | MAIN LANE INDUSTRIES LTD. | TxDOT |
| 05 MAY 2023 | 05233201 | Houston District | 2,235 | $105.52 | $105.52 | $65.00 | 5 | JAMES CONSTRUCTION GROUP, LLC | TxDOT |
| 05 MAY 2023 | 05233231 | Dallas District | 1,895 | $85.00 | $62.50 | $135.00 | 2 | O. TREVINO CONSTRUCTION, LLC | TxDOT |
| 05 APR 2023 | 04233231 | Brownwood District | 62 | $200.00 | $200.00 | $185.00 | 3 | JAY MILLS CONTRACTING, INCORPORATED | TxDOT |
| 08 MAR 2023 | 03233201 | Brownwood District | 1,338 | $68.00 | $68.00 | $75.00 | 1 | JAY MILLS CONTRACTING, INCORPORATED | TxDOT |
| 07 MAR 2023 | 03233003 | Fort Worth District | 4,412 | $95.00 | $113.58 | $95.00 | 4 | RAGLE CONSTRUCTION, INC. | TxDOT |
| 01 DEC 2022 | 12223004 | Dallas District | 221 | $135.53 | $140.00 | $150.00 | 5 | COPASA INC | TxDOT |
| 02 NOV 2022 | 11223010 | Houston District | 4,428 | $30.96 | $67.75 | $70.00 | 8 | ISI CONTRACTING, INC. | TxDOT |
| 07 OCT 2022 | 10223223 | Houston District | 2,693 | $68.20 | $94.86 | $51.00 | 5 | SER CONSTRUCTION PARTNERS, LLC | TxDOT |
| 04 AUG 2022 | 08223253 | Houston District | 4,428 | $93.60 | $78.00 | $65.00 | 9 | SER CONSTRUCTION PARTNERS, LLC | TxDOT |
| 03 AUG 2022 | 08223038 | Paris District | 787 | $58.00 | $125.00 | $85.00 | 3 | TI-ZACK CONCRETE, INC. | TxDOT |
| 30 JUN 2022 | 06223603 | Dallas District | 2,164 | $137.00 | $137.00 | $130.00 | 3 | WEBBER, LLC | TxDOT |
| 30 JUN 2022 | 06223613 | Lubbock District | 1,608 | $121.00 | $111.14 | $80.00 | 3 | ALLEN BUTLER CONSTRUCTION, INC. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.