Tree removal (18" - 24" dia) unit price, Texas
Low bidders on TxDOT contracts carried a median of $200.00 per EACH for item 7526007, tree removal (18" - 24" dia), from 12 FEB 2020 to 12 JUN 2024, across 75 low bids. Half of all 359 bids fell between $125.00 and $795.00.
- Owner
- Texas DOT
- Item
- 7526007
- Unit
- EACH
- Latest letting
- 12 JUN 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 10 | 9 | $250.00 | 71 | $325.00 |
| 2021 | 28 | 28 | $150.00 | 142 | $190.00 |
| 2022 | 26 | 25 | $200.00 | 91 | $200.00 |
| 2023 | 8 | 8 | $584.50 | 32 | $617.50 |
| 2024 | 5 | 5 | $125.00 | 23 | $1,000.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Lufkin District | 9 | $100.00 | 56 | $105.00 |
| Fort Worth District | 7 | $500.00 | 50 | $500.00 |
| Dallas District | 8 | $200.00 | 46 | $300.00 |
| Bryan District | 9 | $125.00 | 28 | $162.50 |
| Austin District | 6 | $575.00 | 25 | $500.00 |
| Atlanta District | 7 | $121.00 | 24 | $140.00 |
| Waco District | 3 | $450.00 | 23 | $300.00 |
| San Antonio District | 3 | $1,000.00 | 22 | $1,010.00 |
| Wichita Falls District | 4 | $1,475.00 | 21 | $950.00 |
| Paris District | 3 | $90.00 | 18 | $125.00 |
| Beaumont District | 5 | $300.00 | 17 | $300.00 |
| Tyler District | 3 | $100.00 | 11 | $150.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 5 | 18 | $1,310.00 |
| 5 to 31 | 19 | $300.00 |
| 34 to 200 | 19 | $125.00 |
| 200 to 800 | 19 | $100.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 12 JUN 2024 | 06241403 | Austin District | 48 | $125.00 | $220.00 | $300.00 | 3 | JCW CONSTRUCTION, LLC | TxDOT |
| 12 JUN 2024 | 06241707 | Bryan District | 150 | $125.00 | $137.50 | $175.00 | 2 | LONGHORN SERVICES NORTH TEXAS, LLC. | TxDOT |
| 02 MAY 2024 | 05243039 | San Antonio District | 3 | $1,000.00 | $1,650.00 | $940.00 | 9 | DIAMOND R CONTRACTING, LLC | TxDOT |
| 04 APR 2024 | 04243020 | Dallas District | 1 | $7,423.80 | $6,300.00 | $500.00 | 5 | YUNEX LLC | TxDOT |
| 02 FEB 2024 | 02244227 | Bryan District | 300 | $100.00 | $182.50 | $120.00 | 4 | ICOS MANAGEMENT, LLC | TxDOT |
| 28 JUN 2023 | 06233612 | San Antonio District | 10 | $969.00 | $1,200.00 | $484.64 | 5 | ACME BRIDGE COMPANY, INC. | TxDOT |
| 28 JUN 2023 | 06233618 | Wichita Falls District | 4 | $2,000.00 | $5,000.00 | $1,000.00 | 2 | JAGOE-PUBLIC COMPANY | TxDOT |
| 01 JUN 2023 | 06233009 | Wichita Falls District | 4 | $3,500.00 | $2,995.00 | $270.00 | 3 | A. L. HELMCAMP, INC. | TxDOT |
| 04 MAY 2023 | 05233018 | Dallas District | 2 | $2,000.00 | $2,200.00 | $500.00 | 5 | AUSTIN BRIDGE & ROAD SERVICES, LP | TxDOT |
| 04 MAY 2023 | 05234026 | Tyler District | 150 | $100.00 | $175.00 | $140.00 | 2 | FIREMAN EXCAVATING, INC. | TxDOT |
| 22 MAR 2023 | 03231104 | Lufkin District | 200 | $80.00 | $100.00 | $116.00 | 5 | AZA CONSTRUCTION INC | TxDOT |
| 16 MAR 2023 | 03230101 | Paris District | 150 | $90.00 | $200.00 | $135.00 | 5 | CATOCON, INC. | TxDOT |
| 14 MAR 2023 | 03231805 | Dallas District | 2 | $200.00 | $200.00 | $500.00 | 5 | AZA CONSTRUCTION INC | TxDOT |
| 17 NOV 2022 | 11220101 | Paris District | 350 | $75.00 | $80.00 | $70.00 | 6 | BRYDL CONTRACTING, LLC | TxDOT |
| 16 NOV 2022 | 11221704 | Bryan District | 200 | $200.00 | $200.00 | $120.00 | 2 | GV LANDSCAPE AND CONSTRUCTION LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.