Tree removal (42" - 48" dia) unit price, Texas
Low bidders on TxDOT contracts carried a median of $500.00 per EACH for item 7526011, tree removal (42" - 48" dia), from 12 FEB 2020 to 12 JUN 2024, across 34 low bids. Half of all 170 bids fell between $340.00 and $900.00.
- Owner
- Texas DOT
- Item
- 7526011
- Unit
- EACH
- Latest letting
- 12 JUN 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 3 | 3 | $500.00 | 23 | $500.00 |
| 2021 | 18 | 14 | $425.00 | 77 | $550.00 |
| 2022 | 14 | 12 | $500.00 | 51 | $500.00 |
| 2023 | 3 | 2 | $210.00 | 10 | $358.50 |
| 2024 | 3 | 3 | $500.00 | 9 | $987.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Lufkin District | 6 | $250.00 | 50 | $398.00 |
| Atlanta District | 7 | $500.00 | 24 | $500.00 |
| Waco District | 3 | $750.00 | 23 | $800.00 |
| Bryan District | 7 | $500.00 | 22 | $575.00 |
| Tyler District | 3 | $300.00 | 11 | $550.00 |
| Beaumont District | 3 | $600.00 | 11 | $600.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 3 | 8 | $625.00 |
| 4 to 7 | 9 | $550.00 |
| 7 to 10 | 8 | $395.00 |
| 10 to 40 | 9 | $500.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 12 JUN 2024 | 06241403 | Austin District | 1 | $2,000.00 | $1,050.00 | $5,000.00 | 3 | JCW CONSTRUCTION, LLC | TxDOT |
| 12 JUN 2024 | 06241707 | Bryan District | 5 | $500.00 | $400.00 | $390.00 | 2 | LONGHORN SERVICES NORTH TEXAS, LLC. | TxDOT |
| 02 FEB 2024 | 02244227 | Bryan District | 10 | $500.00 | $818.50 | $500.00 | 4 | ICOS MANAGEMENT, LLC | TxDOT |
| 04 MAY 2023 | 05234026 | Tyler District | 2 | $100.00 | $275.00 | $347.00 | 2 | FIREMAN EXCAVATING, INC. | TxDOT |
| 22 MAR 2023 | 03231104 | Lufkin District | 10 | $320.00 | $210.00 | $472.00 | 4 | AZA CONSTRUCTION INC | TxDOT |
| 16 MAR 2023 | 03230101 | Paris District | 10 | n/a | $468.50 | $500.00 | 4 | CATOCON, INC. | TxDOT |
| 17 NOV 2022 | 11220101 | Paris District | 10 | n/a | $500.00 | $400.00 | 5 | BRYDL CONTRACTING, LLC | TxDOT |
| 16 NOV 2022 | 11221704 | Bryan District | 10 | $400.00 | $650.00 | $475.00 | 2 | GV LANDSCAPE AND CONSTRUCTION LLC | TxDOT |
| 15 NOV 2022 | 11221703 | Bryan District | 10 | $390.00 | $645.00 | $475.00 | 2 | GV LANDSCAPE AND CONSTRUCTION LLC | TxDOT |
| 09 NOV 2022 | 11221101 | Lufkin District | 15 | $200.00 | $500.00 | $450.00 | 5 | K & R CONTRACTORS | TxDOT |
| 08 NOV 2022 | 11221705 | Bryan District | 10 | $1,000.00 | $1,000.00 | $475.00 | 1 | ROAD SOLUTIONS L.L.C. | TxDOT |
| 03 NOV 2022 | 11224208 | Fort Worth District | 19 | $700.00 | $700.00 | $266.00 | 5 | SHALOM SERVICES CORPORATION | TxDOT |
| 08 SEP 2022 | 09224204 | Atlanta District | 20 | $500.00 | $500.00 | $300.00 | 5 | CATOCON, INC. | TxDOT |
| 08 SEP 2022 | 09224205 | Atlanta District | 20 | $500.00 | $475.00 | $300.00 | 6 | CATOCON, INC. | TxDOT |
| 07 SEP 2022 | 09224017 | Beaumont District | 6 | $600.00 | $600.00 | $3,042.00 | 3 | ROY JORGENSEN ASSOCIATES, INC. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.