Wk zn pav mrk remov (w)12"(sld) unit price, Texas
Low bidders on TxDOT contracts carried a median of $4.18 per LF for item 6626073, wk zn pav mrk remov (w)12"(sld), from 06 FEB 2020 to 10 JUL 2024, across 59 low bids. Half of all 252 bids fell between $3.00 and $5.50.
- Owner
- Texas DOT
- Item
- 6626073
- Unit
- LF
- Latest letting
- 10 JUL 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 19 | 18 | $4.50 | 88 | $4.00 |
| 2021 | 13 | 13 | $3.05 | 73 | $3.30 |
| 2022 | 8 | 8 | $5.08 | 31 | $5.00 |
| 2023 | 9 | 9 | $4.99 | 26 | $5.00 |
| 2024 | 11 | 11 | $5.00 | 34 | $3.50 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Houston District | 11 | $3.68 | 57 | $3.00 |
| San Antonio District | 8 | $3.00 | 37 | $3.00 |
| Fort Worth District | 5 | $4.50 | 30 | $4.47 |
| Dallas District | 7 | $5.00 | 28 | $5.00 |
| El Paso District | 4 | $4.46 | 25 | $4.18 |
| Austin District | 5 | $5.30 | 14 | $3.21 |
| Corpus Christi District | 4 | $2.77 | 14 | $2.77 |
| Pharr District | 3 | $1.66 | 12 | $3.67 |
| Yoakum District | 3 | $7.00 | 7 | $3.50 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 3 to 285 | 14 | $3.87 |
| 300 to 900 | 15 | $4.50 |
| 904 to 2,011 | 15 | $4.50 |
| 2,150 to 16,271 | 15 | $4.18 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 10 JUL 2024 | 07243201 | Dallas District | 2,750 | $3.80 | $3.80 | $6.00 | 2 | AUSTIN BRIDGE & ROAD SERVICES, LP | TxDOT |
| 09 JUL 2024 | 07243001 | Fort Worth District | 16,271 | $3.06 | $3.03 | $5.00 | 2 | ZACHRY CONSTRUCTION CORPORATION | TxDOT |
| 09 JUL 2024 | 07243013 | Dallas District | 300 | $7.26 | $7.41 | $4.25 | 2 | O. TREVINO CONSTRUCTION, LLC | TxDOT |
| 06 JUN 2024 | 06243201 | San Antonio District | 754 | $1.80 | $2.20 | $2.68 | 5 | WEBBER, LLC | TxDOT |
| 03 MAY 2024 | 05243201 | Yoakum District | 353 | $9.00 | $3.50 | $6.00 | 3 | PULICE CONSTRUCTION, INC. | TxDOT |
| 02 MAY 2024 | 05243005 | Austin District | 2,335 | $7.00 | $6.00 | $2.75 | 2 | HARPER BROTHERS CONSTRUCTION LLC | TxDOT |
| 05 APR 2024 | 04243202 | Wichita Falls District | 781 | $7.00 | $3.73 | $4.00 | 2 | AUSTIN BRIDGE & ROAD SERVICES, LP ZACHRY CONSTRUCTION CORPORATION | TxDOT |
| 04 APR 2024 | 04243002 | Corpus Christi District | 1,415 | $6.30 | $6.10 | $4.50 | 3 | BAY LTD. | TxDOT |
| 02 FEB 2024 | 02243202 | Houston District | 1,516 | $2.85 | $1.58 | $6.00 | 8 | BRICE CONSTRUCTION AND DESIGN LLC | TxDOT |
| 01 FEB 2024 | 02243001 | Dallas District | 1,643 | $5.00 | $5.00 | $6.35 | 3 | FLATIRON CONSTRUCTORS, INC. | TxDOT |
| 01 FEB 2024 | 02243033 | Houston District | 1,690 | $2.79 | $2.70 | $6.35 | 2 | TEXAS MATERIALS GROUP, INC. | TxDOT |
| 03 AUG 2023 | 08233201 | Paris District | 155 | $4.99 | $4.75 | $2.27 | 4 | SEMA CONSTRUCTION, INC. | TxDOT |
| 03 AUG 2023 | 08233203 | Dallas District | 2,544 | $6.00 | $6.35 | $4.75 | 2 | WEBBER, LLC | TxDOT |
| 03 AUG 2023 | 08233214 | Paris District | 500 | $6.00 | $6.00 | $1.20 | 2 | HIGHWAY 19 CONSTRUCTION LLC | TxDOT |
| 02 AUG 2023 | 08233002 | San Antonio District | 115 | $3.60 | $5.60 | $3.25 | 2 | JORDAN FOSTER CONSTRUCTION, LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.