Wk zn pav mrk remov (w)6"(brk) unit price, Texas
Low bidders on TxDOT contracts carried a median of $1.50 per LF for item 6626064, wk zn pav mrk remov (w)6"(brk), from 07 FEB 2020 to 01 AUG 2024, across 74 low bids. Half of all 269 bids fell between $0.92 and $2.25.
- Owner
- Texas DOT
- Item
- 6626064
- Unit
- LF
- Latest letting
- 01 AUG 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 2 | 2 | $1.73 | 14 | $0.81 |
| 2021 | 6 | 4 | $0.81 | 30 | $1.00 |
| 2022 | 1 | 1 | $0.90 | 5 | $0.90 |
| 2023 | 28 | 28 | $1.75 | 81 | $2.00 |
| 2024 | 40 | 39 | $1.50 | 139 | $1.50 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| San Antonio District | 8 | $1.00 | 47 | $1.02 |
| Tyler District | 11 | $1.85 | 41 | $2.00 |
| Atlanta District | 9 | $2.30 | 28 | $3.00 |
| Houston District | 5 | $1.60 | 27 | $1.35 |
| Dallas District | 7 | $1.65 | 27 | $1.65 |
| Austin District | 4 | $1.51 | 20 | $1.50 |
| Yoakum District | 8 | $0.75 | 17 | $1.25 |
| Odessa District | 5 | $1.15 | 17 | $1.08 |
| Beaumont District | 3 | $1.50 | 7 | $1.08 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 184 to 770 | 18 | $2.00 |
| 789 to 4,230 | 19 | $1.44 |
| 4,926 to 16,760 | 18 | $1.57 |
| 18,400 to 241,401 | 19 | $0.90 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 01 AUG 2024 | 08243001 | Houston District | 60,251 | $1.20 | $1.20 | $2.00 | 2 | WEBBER, LLC | TxDOT |
| 09 JUL 2024 | 07243001 | Fort Worth District | 78,007 | $1.00 | $1.00 | $2.10 | 2 | ZACHRY CONSTRUCTION CORPORATION | TxDOT |
| 09 JUL 2024 | 07243005 | Abilene District | 820 | $1.75 | $1.50 | $2.50 | 3 | FNF CONSTRUCTION, INC. | TxDOT |
| 06 JUN 2024 | 06243201 | San Antonio District | 37,822 | $0.38 | $1.00 | $2.45 | 5 | WEBBER, LLC | TxDOT |
| 06 JUN 2024 | 06243206 | Childress District | 184 | $0.75 | $0.84 | $1.36 | 4 | MORTMARA CONSTRUCTION, INC. | TxDOT |
| 06 JUN 2024 | 06243214 | San Antonio District | 1,490 | $1.34 | $1.34 | $0.85 | 5 | RELMCO, INC. | TxDOT |
| 06 JUN 2024 | 06243229 | Atlanta District | 743 | $1.85 | $3.00 | $2.00 | 3 | MADDEN CONTRACTING COMPANY, LLC. | TxDOT |
| 05 JUN 2024 | 06243013 | Yoakum District | 544 | $2.00 | $2.50 | $1.50 | 2 | CEKRA INC. | TxDOT |
| 05 JUN 2024 | 06243050 | Bryan District | 1,080 | $1.44 | $0.87 | $1.70 | 4 | KNIFE RIVER CORPORATION - SOUTH | TxDOT |
| 03 MAY 2024 | 05243201 | Yoakum District | 46,581 | $2.45 | $1.25 | $0.95 | 3 | PULICE CONSTRUCTION, INC. | TxDOT |
| 03 MAY 2024 | 05243226 | Houston District | 3,000 | n/a | $1.35 | $2.00 | 3 | ISI CONTRACTING, INC. | TxDOT |
| 02 MAY 2024 | 05243001 | Beaumont District | 67,850 | $1.85 | $1.85 | $2.50 | 1 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. | TxDOT |
| 02 MAY 2024 | 05243003 | Waco District | 7,662 | $1.20 | $1.44 | $2.00 | 4 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 02 MAY 2024 | 05243005 | Austin District | 2,000 | $1.60 | $2.30 | $2.25 | 2 | HARPER BROTHERS CONSTRUCTION LLC | TxDOT |
| 02 MAY 2024 | 05243010 | Corpus Christi District | 20,940 | $0.38 | $0.84 | $2.00 | 2 | HUNTER INDUSTRIES, LTD. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.