Conc. class 4000 for retaining wall unit price, Washington
Low bidders on WSDOT contracts carried a median of $575.00 per CY for conc. class 4000 for retaining wall, from 20 MAR 2002 to 09 FEB 2022, across 41 low bids. Half of all 299 bids fell between $500.00 and $862.50.
- Owner
- Washington State DOT
- Item
- No code published
- Unit
- CY
- Latest letting
- 09 FEB 2022
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2002 | 1 | 1 | $305.00 | 6 | $307.50 |
| 2003 | 1 | 1 | $335.00 | 8 | $330.00 |
| 2004 | 1 | 1 | $520.00 | 7 | $600.00 |
| 2005 | 1 | 1 | $472.00 | 5 | $472.00 |
| 2006 | 1 | 1 | $375.00 | 9 | $575.00 |
| 2007 | 4 | 4 | $867.50 | 24 | $750.00 |
| 2008 | 3 | 3 | $545.00 | 18 | $537.50 |
| 2009 | 4 | 4 | $513.00 | 31 | $650.00 |
| 2010 | 5 | 5 | $600.00 | 44 | $705.00 |
| 2011 | 3 | 3 | $510.00 | 28 | $600.00 |
| 2012 | 2 | 2 | $650.00 | 21 | $650.00 |
| 2013 | 2 | 2 | $536.01 | 12 | $815.00 |
| 2014 | 2 | 2 | $575.00 | 20 | $525.00 |
| 2017 | 3 | 3 | $900.00 | 21 | $728.00 |
| 2020 | 3 | 3 | $825.00 | 17 | $825.00 |
| 2021 | 4 | 4 | $937.50 | 21 | $973.00 |
| 2022 | 1 | 1 | $1,000.00 | 7 | $1,000.00 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| NWR region | 22 | $650.00 | 155 | $675.00 |
| OR region | 5 | $575.00 | 39 | $640.00 |
| SWR region | 4 | $516.05 | 34 | $538.00 |
| SCR region | 4 | $465.00 | 33 | $575.00 |
| ER region | 3 | $820.00 | 16 | $701.50 |
Regions with at least three low bids, over all lettings.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 12 to 109 | 10 | $730.00 |
| 140 to 259 | 10 | $637.50 |
| 312 to 773 | 10 | $735.00 |
| 795.20 to 5,647 | 11 | $472.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 09 FEB 2022 | 009763 | OR region | 312 | $1,000.00 | $1,000.00 | $1,000.00 | 7 | KRAEMER NORTH AMERICA, LLC. | WSDOT |
| 21 APR 2021 | 009662 | NWR region | 381 | $1,055.00 | $1,012.50 | $900.00 | 4 | SCARSELLA BROS., INC. | WSDOT |
| 24 MAR 2021 | 009636 | OR region | 243.60 | $575.00 | $1,171.90 | $840.00 | 4 | GRAHAM CONTRACTING, LTD. | WSDOT |
| 03 FEB 2021 | 009625 | SCR region | 395 | $1,140.00 | $978.50 | $550.00 | 8 | SCARSELLA BROS., INC. | WSDOT |
| 13 JAN 2021 | 009623 | ER region | 727 | $820.00 | $734.09 | $650.00 | 5 | MAX J. KUNEY COMPANY | WSDOT |
| 20 FEB 2020 | 009516 | OR region | 625 | $450.00 | $600.00 | $600.00 | 8 | INTERWEST CONSTRUCTION, INC. | WSDOT |
| 05 FEB 2020 | 009501 | NWR region | 182 | $1,575.00 | $1,800.00 | $1,000.00 | 5 | TITAN EARTHWORK LLC | WSDOT |
| 23 JAN 2020 | 009509 | ER region | 109 | $825.00 | $1,012.50 | $850.00 | 4 | GARCO CONSTRUCTION, INC. | WSDOT |
| 15 MAR 2017 | 009042 | NWR region | 20 | $900.00 | $830.00 | $1,000.00 | 6 | STRIDER CONSTRUCTION CO., INC. | WSDOT |
| 15 FEB 2017 | 009020 | NCR region | 43 | $900.00 | $885.00 | $600.00 | 8 | INTERWEST CONSTRUCTION, INC. | WSDOT |
| 25 JAN 2017 | 009011 | ER region | 795.20 | $500.00 | $512.00 | $400.00 | 7 | MAX J. KUNEY COMPANY | WSDOT |
| 20 FEB 2014 | 008569 | NWR region | 450 | $650.00 | $702.50 | $475.00 | 8 | MIDMOUNTAIN CONTRACTORS, INC. | WSDOT |
| 29 JAN 2014 | 008572 | SWR region | 259 | $500.00 | $500.00 | $500.00 | 12 | SCARSELLA BROS., INC. | WSDOT |
| 11 DEC 2013 | 008549 | NWR region | 698 | $542.03 | $767.50 | $550.00 | 6 | WALSH CONSTRUCTION CO II LLC | WSDOT |
| 27 MAR 2013 | 008436 | NWR region | 53 | $530.00 | $815.00 | $400.00 | 6 | RAM CONSTRUCTION GENERAL | WSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.
How these prices were read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.