Pavement repair excavation incl. haul unit price, Washington

Low bidders on WSDOT contracts carried a median of $37.50 per SY for pavement repair excavation incl. haul, over the 24 months to 07 OCT 2026, across 2 low bids. Half of all 7 bids fell between $41.97 and $122.50.

Owner
Washington State DOT
Item
No code published
Unit
SY
Latest letting
08 JUL 2026
$37.50Low bidder's median, per SY
$60.00Median of all bids, per SY
2Contracts in the window
$37.50Engineer's estimate, median per SY

By year of letting

Pavement repair excavation incl. haul, WSDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
200144$16.2712$14.53
200277$11.0018$17.20
2003109$13.0033$17.00
20041616$16.8858$19.00
20052323$15.5085$18.00
200677$17.6523$17.00
20071010$17.7526$20.25
200877$19.8023$19.80
20091313$18.5558$24.00
20101515$15.0089$16.00
20111818$13.9066$15.75
201266$22.5022$23.00
20131413$14.2555$20.00
20141212$18.5033$22.00
20152323$30.0070$29.40
20162020$28.0054$23.18
20173333$44.0087$44.00
20183131$30.0082$33.00
20192222$25.5066$35.00
20201010$11.0034$17.25
20211515$16.0042$30.00
20221616$28.6145$55.00
2023109$11.0031$12.00
202622$37.507$60.00
Pavement repair excavation incl. haul, WSDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By region

Pavement repair excavation incl. haul, WSDOT: unit prices by region, all lettings
RegionLow bidsLow-bid medianAll bidsMedian, all bids
NWR region115$31.00384$32.00
OR region75$34.00262$31.00
ER region53$11.65168$12.00
NCR region41$5.00106$5.75
SCR region29$12.3093$14.00
SWR region23$18.0091$16.50
Region 95$50.0015$19.00
Pavement repair excavation incl. haul, WSDOT: unit prices by region, all lettings

Regions with at least three low bids, over all lettings.

By quantity

Pavement repair excavation incl. haul, WSDOT: low bidder's median by quantity band
Quantity (SY)Low bidsLow-bid median
2.50 to 38085$40.00
382 to 1,03085$28.50
1,030 to 3,61085$17.80
3,643 to 41,91186$7.75
Pavement repair excavation incl. haul, WSDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest WSDOT contracts carrying Pavement repair excavation incl. haul
LetContractRegionQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
08 JUL 2026XE3751SCR region59$25.00$46.97$40.004TAPANI, INC.WSDOT
01 JUL 2026XE3749SCR region884$50.00$115.00$35.003CENTRAL WASHINGTON ASPHALT, INC.WSDOT
29 MAR 2023009954NWR region9,875$11.00$20.50$4.002GRANITE CONSTRUCTION COMPANYWSDOT
22 MAR 2023009949SCR region500n/a$22.00$50.002CENTRAL WASHINGTON ASPHALT, INC.GRANITE CONSTRUCTION COMPANYWSDOT
01 MAR 2023009936NCR region4,257$12.00$10.00$20.002CENTRAL WASHINGTON ASPHALT, INC.GRANITE CONSTRUCTION COMPANYWSDOT
01 MAR 2023009938ER region9,145$4.50$4.50$26.003CENTRAL WASHINGTON ASPHALT, INWSDOT
23 FEB 2023009934NCR region6,100$10.00$10.00$5.003CENTRAL WASHINGTON ASPHALT, INC.INTERSTATE CONCRETE & ASPHALTWSDOT
01 FEB 2023009928OR region78.50$95.00$97.50$125.004TUCCI & SONS, INC.WSDOT
01 FEB 2023009916NWR region4,660$12.00$14.00$29.722GRANITE CONSTRUCTION COMPANYWSDOT
01 FEB 2023009921NCR region1,350$7.00$9.50$30.004JOHANSEN CONSTRUCTION COMPANY,WSDOT
25 JAN 2023009910NWR region60$100.00$100.00$90.005ACME CONCRETE PAVING, INC.WSDOT
25 JAN 2023009914ER region4,870$7.50$7.50$12.004POE ASPHALT PAVING, INC.WSDOT
13 APR 2022009781NWR region1,556$104.00$102.00$46.004TUCCI & SONS, INC.WSDOT
13 APR 2022009796NWR region17,840$29.72$47.36$46.002GRANITE CONSTRUCTION COMPANYWSDOT
06 APR 2022009787SWR region6,141$20.00$17.09$12.003CENTRAL WASHINGTON ASPHALT, INWSDOT
Latest WSDOT contracts carrying Pavement repair excavation incl. haul

Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.

How these prices were read

WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.