Permanent impact attenuator unit price, Washington
Low bidders on WSDOT contracts carried a median of $27,000 per EACH for permanent impact attenuator, from 27 JAN 2000 to 19 APR 2023, across 79 low bids. Half of all 373 bids fell between $18,000 and $37,200.
- Owner
- Washington State DOT
- Item
- No code published
- Unit
- EACH
- Latest letting
- 19 APR 2023
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2000 | 2 | 2 | $19,348 | 6 | $15,750 |
| 2001 | 5 | 5 | $40,000 | 23 | $20,000 |
| 2002 | 2 | 2 | $8,767.50 | 10 | $9,750.00 |
| 2003 | 3 | 3 | $39,000 | 19 | $40,000 |
| 2004 | 3 | 3 | $37,200 | 18 | $40,000 |
| 2005 | 5 | 5 | $40,000 | 24 | $33,500 |
| 2006 | 4 | 4 | $27,250 | 12 | $23,250 |
| 2007 | 5 | 5 | $20,000 | 22 | $19,250 |
| 2008 | 4 | 4 | $13,188 | 19 | $15,000 |
| 2009 | 9 | 8 | $22,673 | 46 | $23,623 |
| 2010 | 6 | 6 | $29,890 | 33 | $30,725 |
| 2011 | 5 | 5 | $28,000 | 28 | $26,975 |
| 2012 | 1 | 1 | $12,000 | 8 | $12,193 |
| 2013 | 5 | 5 | $27,500 | 20 | $24,250 |
| 2014 | 2 | 2 | $17,500 | 15 | $22,800 |
| 2015 | 3 | 3 | $30,000 | 12 | $30,000 |
| 2017 | 3 | 3 | $25,000 | 8 | $26,000 |
| 2018 | 3 | 3 | $26,000 | 11 | $27,025 |
| 2019 | 3 | 3 | $37,500 | 7 | $39,000 |
| 2020 | 1 | 1 | $25,000 | 2 | $27,100 |
| 2021 | 2 | 2 | $33,403 | 12 | $35,695 |
| 2022 | 1 | 1 | $50,000 | 7 | $46,100 |
| 2023 | 3 | 3 | $49,000 | 11 | $46,000 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| NWR region | 41 | $25,000 | 194 | $23,500 |
| SWR region | 6 | $27,185 | 46 | $23,520 |
| OR region | 9 | $37,200 | 41 | $37,200 |
| SCR region | 10 | $28,285 | 40 | $32,500 |
| NCR region | 7 | $21,500 | 25 | $21,000 |
| ER region | 5 | $35,000 | 22 | $39,925 |
Regions with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 19 | $22,000 |
| 1 to 2 | 20 | $30,250 |
| 2 to 3 | 20 | $25,685 |
| 3 to 17 | 20 | $26,535 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 19 APR 2023 | 009952 | SCR region | 3 | $49,000 | $52,000 | $32,000 | 4 | INTERSTATE CONCRETE & ASPHALT | WSDOT |
| 08 MAR 2023 | 009937 | NWR region | 2 | $46,000 | $45,000 | $37,700 | 3 | INTERWEST CONSTRUCTION, INC. | WSDOT |
| 01 FEB 2023 | 009928 | OR region | 2 | $50,000 | $45,750 | $49,000 | 4 | TUCCI & SONS, INC. | WSDOT |
| 23 MAR 2022 | 009783 | NWR region | 1 | $50,000 | $46,100 | $30,000 | 7 | INTERWEST CONSTRUCTION, INC. | WSDOT |
| 21 APR 2021 | 009662 | NWR region | 1 | $30,915 | $32,500 | $35,000 | 4 | SCARSELLA BROS., INC. | WSDOT |
| 03 FEB 2021 | 009625 | SCR region | 1 | $35,890 | $37,547 | $26,000 | 8 | SCARSELLA BROS., INC. | WSDOT |
| 15 APR 2020 | 009547 | NWR region | 1 | $25,000 | $27,100 | $35,000 | 2 | NORTHEAST ELECTRIC, LLC | WSDOT |
| 17 APR 2019 | 009422 | NCR region | 2 | $37,500 | $40,000 | $60,000 | 3 | NEPPEL ELECTRICAL & CONTROLS, | WSDOT |
| 06 MAR 2019 | 009380 | NWR region | 1 | $31,868 | $31,868 | $37,000 | 3 | FABER CONSTRUCTION CORP. | WSDOT |
| 06 FEB 2019 | 009361 | NWR region | 6 | $39,000 | $39,000 | $20,000 | 1 | C.A. CAREY CORPORATION | WSDOT |
| 18 APR 2018 | 009233 | NWR region | 1 | $26,000 | $28,500 | $30,000 | 2 | A-1 LANDSCAPING AND CONSTRUCTI | WSDOT |
| 11 APR 2018 | 009251 | NWR region | 1 | $12,000 | $21,000 | $10,000 | 5 | KLB CONSTRUCTION, INC. | WSDOT |
| 28 FEB 2018 | 009215 | OR region | 2 | $35,000 | $35,000 | $33,621 | 4 | INTERWEST CONSTRUCTION, INC. | WSDOT |
| 13 DEC 2017 | 009177 | NWR region | 2 | $20,000 | $23,000 | $25,000 | 3 | TAPANI, INC. | WSDOT |
| 08 MAR 2017 | 009034 | SCR region | 1 | $27,000 | $28,000 | $30,000 | 3 | INTERSTATE CONCRETE & ASPHALT | WSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.
How these prices were read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.