Raised pavement marker type 2 unit price, Washington

Low bidders on WSDOT contracts carried a median of $4,500.00 per HUND for raised pavement marker type 2, over the 24 months to 07 OCT 2026, across 1 low bids. Half of all 5 bids fell between $4,300.00 and $4,500.00.

Owner
Washington State DOT
Item
No code published
Unit
HUND
Latest letting
07 OCT 2026
$4,500.00Low bidder's median, per HUND
$4,500.00Median of all bids, per HUND
1Contracts in the window
$5,000.00Engineer's estimate, median per HUND

By year of letting

Raised pavement marker type 2, WSDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20001010$320.0046$350.00
20012121$400.0096$400.00
20021212$405.0065$500.00
20031413$325.0070$325.50
20041818$320.0084$332.50
20051818$300.0078$325.00
20061313$421.0044$420.50
20071919$395.0082$400.00
20081212$405.0045$441.00
20092121$367.50141$458.97
20101616$425.0088$425.00
20111616$382.5091$425.00
201222$461.0012$477.50
20131313$420.0063$500.00
20141414$500.0070$625.00
20151514$480.0053$460.00
20161616$447.5074$500.00
20172120$552.5074$655.00
20182929$700.0095$750.00
20191313$715.0056$1,000.00
202055$600.0025$840.00
202188$950.0028$900.00
20221111$1,100.0040$1,382.50
202377$900.0026$1,700.00
202611$4,500.005$4,500.00
Raised pavement marker type 2, WSDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By region

Raised pavement marker type 2, WSDOT: unit prices by region, all lettings
RegionLow bidsLow-bid medianAll bidsMedian, all bids
NWR region208$425.00925$450.00
OR region81$500.00387$550.00
SWR region42$500.00184$550.00
NCR region5$600.0022$625.00
SCR region3$625.0020$687.50
Raised pavement marker type 2, WSDOT: unit prices by region, all lettings

Regions with at least three low bids, over all lettings.

By quantity

Raised pavement marker type 2, WSDOT: low bidder's median by quantity band
Quantity (HUND)Low bidsLow-bid median
0.02 to 0.8085$1,000.00
0.80 to 4.4886$431.00
4.60 to 12.5085$375.00
12.90 to 282.8886$390.00
Raised pavement marker type 2, WSDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest WSDOT contracts carrying Raised pavement marker type 2
LetContractRegionQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
07 OCT 2026XE3773OR region0.26$4,500.00$4,500.00$5,000.005LAKESIDE INDUSTRIES, INC.WSDOT
08 MAR 2023009942NWR region1$2,400.00$2,400.00$600.003PENHALL COMPANYWSDOT
23 FEB 2023009932NWR region0.80$1,873.00$1,725.00$550.004FABER CONSTRUCTION CORP.WSDOT
01 FEB 2023009916NWR region8.20$880.00$905.00$950.002GRANITE CONSTRUCTION COMPANYWSDOT
25 JAN 2023009910NWR region15.40$750.00$750.00$610.005ACME CONCRETE PAVING, INC.WSDOT
19 JAN 2023009891OR region0.09$10,000$11,350$2,424.007CECCANTI, INC.WSDOT
11 JAN 2023009901NWR region60.60$900.00$900.00$700.001GARY MERLINO CONSTRUCTION CO.,WSDOT
11 JAN 2023009909SWR region1.13$900.00$908.00$800.004THOMPSON BROS. EXCAVATING, INCWSDOT
13 APR 2022009781NWR region35.39$850.00$875.00$500.004TUCCI & SONS, INC.WSDOT
23 MAR 2022009783NWR region0.60$1,850.00$1,820.00$1,322.007INTERWEST CONSTRUCTION, INC.WSDOT
23 MAR 2022009771OR region10.40$670.00$670.00$590.003TUCCI & SONS, INC.WSDOT
09 MAR 2022009777OR region1.10$1,500.00$1,800.00$1,000.003MASSANA CONSTRUCTION, INC.WSDOT
09 MAR 2022009774OR region0.02$8,500.00$9,750.00$10,0002KRAEMER NORTH AMERICA, LLC.WSDOT
02 MAR 2022009762NWR region20.50$725.00$725.00$650.003MIDMOUNTAIN CONTRACTORS, INC.WSDOT
02 MAR 2022009772OR region0.28$1,100.00$1,100.00$600.003TUCCI & SONS, INC.WSDOT
Latest WSDOT contracts carrying Raised pavement marker type 2

Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.

How these prices were read

WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy