Removing and resetting beam guardrail unit price, Washington
Low bidders on WSDOT contracts carried a median of $16.00 per LF for removing and resetting beam guardrail, from 04 JAN 2001 to 22 MAR 2023, across 111 low bids. Half of all 456 bids fell between $11.00 and $30.00.
- Owner
- Washington State DOT
- Item
- No code published
- Unit
- LF
- Latest letting
- 22 MAR 2023
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2001 | 10 | 10 | $11.35 | 37 | $15.70 |
| 2002 | 4 | 4 | $8.50 | 13 | $9.50 |
| 2003 | 7 | 7 | $8.00 | 22 | $9.00 |
| 2004 | 10 | 10 | $10.32 | 33 | $10.00 |
| 2005 | 9 | 9 | $11.00 | 32 | $11.00 |
| 2006 | 4 | 4 | $10.88 | 19 | $15.00 |
| 2007 | 7 | 7 | $15.00 | 23 | $18.25 |
| 2008 | 3 | 3 | $16.30 | 16 | $27.75 |
| 2009 | 4 | 4 | $21.50 | 17 | $23.00 |
| 2010 | 4 | 4 | $11.60 | 22 | $12.75 |
| 2011 | 4 | 4 | $19.12 | 17 | $13.00 |
| 2012 | 3 | 3 | $16.50 | 26 | $16.00 |
| 2013 | 3 | 3 | $36.00 | 31 | $35.00 |
| 2014 | 2 | 2 | $15.75 | 7 | $18.91 |
| 2015 | 1 | 1 | $13.00 | 5 | $15.00 |
| 2016 | 7 | 7 | $25.00 | 31 | $20.25 |
| 2017 | 3 | 3 | $35.00 | 10 | $35.00 |
| 2018 | 4 | 4 | $17.00 | 16 | $18.00 |
| 2019 | 9 | 9 | $31.00 | 30 | $42.05 |
| 2020 | 2 | 2 | $29.00 | 8 | $30.00 |
| 2021 | 2 | 2 | $19.00 | 6 | $19.00 |
| 2022 | 5 | 5 | $40.00 | 21 | $41.50 |
| 2023 | 4 | 4 | $84.50 | 14 | $89.00 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| NWR region | 27 | $30.00 | 147 | $28.00 |
| NCR region | 28 | $11.75 | 101 | $13.75 |
| SCR region | 20 | $15.10 | 77 | $15.75 |
| OR region | 12 | $21.50 | 56 | $20.00 |
| ER region | 18 | $15.00 | 52 | $14.10 |
| SWR region | 5 | $10.75 | 18 | $10.95 |
Regions with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 12.50 to 125 | 27 | $25.00 |
| 135 to 287.50 | 28 | $19.00 |
| 290 to 750 | 28 | $16.27 |
| 800 to 9,025 | 28 | $10.62 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 22 MAR 2023 | 009950 | NWR region | 40 | $180.00 | $175.00 | $40.00 | 2 | COMBINED CONSTRUCTION, INC. | WSDOT |
| 23 FEB 2023 | 009932 | NWR region | 24 | $59.00 | $73.50 | $75.00 | 4 | FABER CONSTRUCTION CORP. | WSDOT |
| 23 FEB 2023 | 009934 | NCR region | 150 | $27.00 | $27.00 | $23.00 | 3 | CENTRAL WASHINGTON ASPHALT, INC.INTERSTATE CONCRETE & ASPHALT | WSDOT |
| 11 JAN 2023 | 009908 | NWR region | 150 | $110.00 | $110.00 | $70.00 | 5 | KONNERUP CONSTRUCTION, INC. | WSDOT |
| 13 APR 2022 | 009781 | NWR region | 135 | $99.00 | $100.00 | $60.00 | 4 | TUCCI & SONS, INC. | WSDOT |
| 23 MAR 2022 | 009783 | NWR region | 238 | $90.00 | $69.00 | $55.00 | 7 | INTERWEST CONSTRUCTION, INC. | WSDOT |
| 23 MAR 2022 | 009784 | ER region | 37.50 | $40.00 | $40.00 | $25.00 | 1 | CENTRAL WASHINGTON ASPHALT, IN | WSDOT |
| 09 FEB 2022 | 009763 | OR region | 175 | $30.00 | $35.00 | $36.00 | 7 | KRAEMER NORTH AMERICA, LLC. | WSDOT |
| 09 FEB 2022 | 009765 | ER region | 563 | $23.00 | $34.50 | $20.00 | 2 | SHAMROCK PAVING, INC. | WSDOT |
| 24 MAR 2021 | 009636 | OR region | 1,640 | $18.00 | $17.65 | $15.00 | 4 | GRAHAM CONTRACTING, LTD. | WSDOT |
| 27 JAN 2021 | 009638 | NCR region | 846 | $20.00 | $25.00 | $25.00 | 2 | CENTRAL WASHINGTON ASPHALT, INC.INTERSTATE CONCRETE & ASPHALT | WSDOT |
| 15 APR 2020 | 009542 | SCR region | 12.50 | $28.00 | $30.00 | $30.00 | 3 | APOLLO, INC. | WSDOT |
| 01 APR 2020 | 009533 | SCR region | 50 | $30.00 | $30.00 | $50.00 | 5 | KRCI LLC | WSDOT |
| 17 APR 2019 | 009418 | SCR region | 630 | $26.00 | $21.00 | $30.00 | 3 | ASCORP, INC. DBA DEBCO | WSDOT |
| 20 MAR 2019 | 009407 | ER region | 675 | $15.00 | $15.75 | $30.00 | 3 | CENTRAL WASHINGTON ASPHALT, IN | WSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.
How these prices were read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.