Schedule a storm sewer pipe 18 in. diam. unit price, Washington

Low bidders on WSDOT contracts carried a median of $81.00 per LF for schedule a storm sewer pipe 18 in. diam., over the 24 months to 07 OCT 2026, across 1 low bids. Half of all 5 bids fell between $114.00 and $122.00.

Owner
Washington State DOT
Item
No code published
Unit
LF
Latest letting
15 JUL 2026
$81.00Low bidder's median, per LF
$115.00Median of all bids, per LF
1Contracts in the window
$150.00Engineer's estimate, median per LF

By year of letting

Schedule a storm sewer pipe 18 in. diam., WSDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
200011$25.006$31.00
200211$32.006$27.00
200322$31.5011$30.00
200422$30.0011$30.00
200555$33.0026$32.00
200633$28.0015$35.00
200799$38.0055$38.00
200855$36.3039$36.00
200944$34.2531$35.50
20101010$30.1079$36.00
201144$51.5035$46.00
201211$40.008$40.00
201322$59.7314$59.00
201422$37.2510$37.00
201511$46.006$58.00
201622$50.4315$52.40
201733$42.0016$48.00
201811$35.006$53.50
201922$98.509$110.00
202022$77.5012$69.08
202133$105.0012$122.50
202322$206.126$156.12
202611$81.005$115.00
Schedule a storm sewer pipe 18 in. diam., WSDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By region

Schedule a storm sewer pipe 18 in. diam., WSDOT: unit prices by region, all lettings
RegionLow bidsLow-bid medianAll bidsMedian, all bids
NWR region37$35.00247$36.30
SWR region7$39.1658$43.00
OR region7$40.0049$44.00
ER region8$27.1538$33.75
SCR region5$46.0024$58.00
NCR region4$36.0017$43.00
Schedule a storm sewer pipe 18 in. diam., WSDOT: unit prices by region, all lettings

Regions with at least three low bids, over all lettings.

By quantity

Schedule a storm sewer pipe 18 in. diam., WSDOT: low bidder's median by quantity band
Quantity (LF)Low bidsLow-bid median
14 to 21117$39.81
231 to 55417$45.00
626 to 1,46017$35.00
1,514 to 21,37117$30.00
Schedule a storm sewer pipe 18 in. diam., WSDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest WSDOT contracts carrying Schedule a storm sewer pipe 18 in. diam.
LetContractRegionQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
15 JUL 2026XE3755SCR region262$81.00$115.00$150.005INTERWEST CONSTRUCTION, INC.WSDOT
23 FEB 2023009925ER region1,460$250.00$200.00$55.002MAX J. KUNEY COMPANYWSDOT
01 FEB 2023009921NCR region403$162.25$146.12$70.004JOHANSEN CONSTRUCTION COMPANY,WSDOT
15 DEC 2021009742NWR region231$80.00$110.00$100.004GRANITE CONSTRUCTION COMPANYWSDOT
24 MAR 2021009636OR region45$105.00$118.30$100.004GRAHAM CONTRACTING, LTD.WSDOT
24 MAR 2021009656NWR region33$115.00$125.00$135.004MARSHBANK CONSTRUCTION, INC.WSDOT
20 FEB 2020009516OR region360$60.00$60.00$52.008INTERWEST CONSTRUCTION, INC.WSDOT
23 JAN 2020009509ER region71$95.00$92.50$60.004GARCO CONSTRUCTION, INC.WSDOT
13 MAR 2019009374NWR region494$73.00$110.00$100.007MARSHBANK CONSTRUCTION, INC.WSDOT
21 FEB 2019009382NWR region31$124.00$107.00$150.002SRV CONSTRUCTION, INC.WSDOT
07 FEB 2018009196SCR region551.53$35.00$53.50$60.006CENTRAL WASHINGTON ASPHALT, INWSDOT
13 DEC 2017009177NWR region250$73.00$73.00$60.003TAPANI, INC.WSDOT
01 FEB 2017009010NCR region761$42.00$45.50$30.256STRIDER CONSTRUCTION CO., INC.WSDOT
25 JAN 2017009011ER region365$36.00$41.20$60.007MAX J. KUNEY COMPANYWSDOT
21 DEC 2016008993OR region2,175$61.05$50.00$40.009SCARSELLA BROS., INC.WSDOT
Latest WSDOT contracts carrying Schedule a storm sewer pipe 18 in. diam.

Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.

How these prices were read

WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way