Schedule a culv. pipe 24 in. diam. unit price, Washington
Low bidders on WSDOT contracts carried a median of $60.00 per LF for schedule a culv. pipe 24 in. diam., from 11 JAN 2001 to 23 FEB 2023, across 41 low bids. Half of all 266 bids fell between $50.00 and $85.00.
- Owner
- Washington State DOT
- Item
- No code published
- Unit
- LF
- Latest letting
- 23 FEB 2023
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2001 | 3 | 3 | $33.00 | 12 | $47.50 |
| 2002 | 1 | 1 | $51.00 | 4 | $39.75 |
| 2003 | 1 | 1 | $58.00 | 5 | $70.00 |
| 2004 | 2 | 2 | $61.50 | 7 | $75.00 |
| 2005 | 1 | 1 | $50.00 | 4 | $46.67 |
| 2006 | 2 | 2 | $45.25 | 10 | $48.15 |
| 2007 | 4 | 4 | $78.30 | 36 | $72.20 |
| 2008 | 2 | 2 | $43.05 | 24 | $53.00 |
| 2009 | 3 | 3 | $44.50 | 36 | $60.00 |
| 2010 | 5 | 5 | $55.00 | 42 | $53.85 |
| 2011 | 1 | 1 | $58.00 | 5 | $55.00 |
| 2012 | 1 | 1 | $52.00 | 8 | $55.50 |
| 2013 | 2 | 2 | $77.00 | 15 | $73.00 |
| 2014 | 2 | 2 | $69.35 | 19 | $62.00 |
| 2015 | 1 | 1 | $60.00 | 6 | $70.50 |
| 2016 | 1 | 1 | $131.42 | 2 | $165.71 |
| 2017 | 2 | 2 | $116.50 | 10 | $98.00 |
| 2018 | 2 | 2 | $147.50 | 4 | $147.50 |
| 2019 | 2 | 2 | $202.50 | 5 | $230.00 |
| 2020 | 1 | 1 | $170.00 | 5 | $205.00 |
| 2023 | 2 | 2 | $181.05 | 7 | $204.00 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| NWR region | 10 | $59.75 | 69 | $55.00 |
| SCR region | 9 | $65.00 | 60 | $65.00 |
| SWR region | 8 | $62.00 | 55 | $70.00 |
| OR region | 3 | $50.00 | 32 | $54.04 |
| NCR region | 6 | $91.75 | 29 | $85.00 |
| ER region | 5 | $48.00 | 21 | $46.30 |
Regions with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 5 to 54 | 10 | $70.50 |
| 55 to 108 | 10 | $91.75 |
| 124 to 175 | 10 | $59.00 |
| 176 to 854 | 11 | $48.50 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 23 FEB 2023 | 009934 | NCR region | 72 | $275.00 | $275.00 | $100.00 | 3 | CENTRAL WASHINGTON ASPHALT, INC.INTERSTATE CONCRETE & ASPHALT | WSDOT |
| 11 JAN 2023 | 009909 | SWR region | 128 | $87.10 | $142.50 | $100.00 | 4 | THOMPSON BROS. EXCAVATING, INC | WSDOT |
| 01 APR 2020 | 009533 | SCR region | 143 | $170.00 | $205.00 | $170.00 | 5 | KRCI LLC | WSDOT |
| 13 MAR 2019 | 009396 | SCR region | 64 | $175.00 | $175.00 | $120.00 | 3 | SELLAND CONSTRUCTION, INC. | WSDOT |
| 09 JAN 2019 | 009362 | NWR region | 80 | $230.00 | $252.50 | $120.00 | 2 | GRANITE CONSTRUCTION COMPANY | WSDOT |
| 04 APR 2018 | 009238 | SWR region | 40 | $150.00 | $150.00 | $85.00 | 3 | ROGNLIN'S, INC. | WSDOT |
| 07 MAR 2018 | 009220 | NWR region | 80 | $145.00 | $145.00 | $100.00 | 1 | GRANITE CONSTRUCTION COMPANY | WSDOT |
| 13 DEC 2017 | 009172 | NWR region | 176 | $43.00 | $88.00 | $140.00 | 8 | COLACURCIO BROTHERS, INC. | WSDOT |
| 22 MAR 2017 | 009045 | SCR region | 329 | $190.00 | $185.00 | $70.00 | 2 | INTERSTATE CONCRETE & ASPHALT | WSDOT |
| 02 MAR 2016 | 008843 | SCR region | 5 | $131.42 | $165.71 | $35.00 | 2 | ACME CONCRETE PAVING, INC. | WSDOT |
| 01 APR 2015 | 008715 | SCR region | 124 | $60.00 | $70.50 | $35.00 | 6 | GUY F. ATKINSON CONSTRUCTION, | WSDOT |
| 30 APR 2014 | 008608 | NWR region | 362 | $65.00 | $60.00 | $55.00 | 7 | GRANITE CONSTRUCTION COMPANY | WSDOT |
| 29 JAN 2014 | 008572 | SWR region | 155 | $73.70 | $71.85 | $55.00 | 12 | SCARSELLA BROS., INC. | WSDOT |
| 24 APR 2013 | 008464 | SWR region | 40 | $54.00 | $72.75 | $70.00 | 8 | ROTSCHY, INC. | WSDOT |
| 10 JAN 2013 | 008409 | NCR region | 74 | $100.00 | $100.00 | $115.00 | 7 | SELLAND CONSTRUCTION, INC. | WSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.
How these prices were read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.