Low bidders on WSDOT contracts carried a median of $2,800.00 per EACH for resetting impact attenuator, over the 24 months to 07 OCT 2026, across 1 low bids. Half of all 6 bids fell between $2,915.75 and $3,650.00.

Owner
Washington State DOT
Item
No code published
Unit
EACH
Latest letting
01 JUL 2026
$2,800.00Low bidder's median, per EACH
$3,381.50Median of all bids, per EACH
1Contracts in the window
$2,500.00Engineer's estimate, median per EACH

By year of letting

Resetting impact attenuator, WSDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
200044$500.0023$750.00
200166$700.0043$760.00
200266$805.0033$900.00
200388$875.0054$810.00
200499$890.0057$900.00
200599$850.0035$915.00
200644$817.0012$856.38
200799$1,500.0056$1,000.00
200855$910.0025$925.00
200954$1,100.0019$1,500.00
201088$950.0053$1,000.00
201155$750.0032$1,000.00
201244$950.0030$1,000.00
201399$1,000.0052$1,029.50
201455$1,000.0031$1,080.00
201533$1,050.0014$1,025.00
201666$1,300.0039$1,910.00
201777$1,230.0033$1,000.00
201888$950.0046$1,139.50
201922$1,200.0011$1,300.00
202011$900.008$962.50
202143$1,600.0016$1,600.00
202233$1,100.0012$1,247.50
202311$3,500.005$2,900.00
202611$2,800.006$3,381.50
Resetting impact attenuator, WSDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By region

Resetting impact attenuator, WSDOT: unit prices by region, all lettings
RegionLow bidsLow-bid medianAll bidsMedian, all bids
NWR region65$990.00385$1,000.00
OR region19$1,000.00133$1,000.00
SCR region25$1,000.00123$1,000.00
NCR region10$1,150.0045$1,000.00
SWR region7$900.0044$1,000.00
ER region3$1,500.0010$550.00
Resetting impact attenuator, WSDOT: unit prices by region, all lettings

Regions with at least three low bids, over all lettings.

By quantity

Resetting impact attenuator, WSDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 132$1,050.00
1 to 333$900.00
3 to 532$900.00
5 to 2233$1,000.00
Resetting impact attenuator, WSDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest WSDOT contracts carrying Resetting impact attenuator
LetContractRegionQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
01 JUL 2026XE3756SCR region1$2,800.00$3,381.50$2,500.006N.A. DEGERSTROM, INC.WSDOT
11 JAN 2023009908NWR region2$3,500.00$2,900.00$1,700.005KONNERUP CONSTRUCTION, INC.WSDOT
09 MAR 2022009774OR region6$1,100.00$1,225.00$1,200.002KRAEMER NORTH AMERICA, LLC.WSDOT
02 MAR 2022009762NWR region1$990.00$990.00$5,000.003MIDMOUNTAIN CONTRACTORS, INC.WSDOT
09 FEB 2022009763OR region2$1,700.00$1,700.00$800.007KRAEMER NORTH AMERICA, LLC.WSDOT
15 DEC 2021009742NWR region2n/a$1,800.00$1,100.003GRANITE CONSTRUCTION COMPANYWSDOT
21 APR 2021009662NWR region1$1,925.00$2,000.00$1,500.004SCARSELLA BROS., INC.WSDOT
07 APR 2021009668NWR region2$1,600.00$780.00$1,500.005INTERWEST CONSTRUCTION, INC.WSDOT
24 MAR 2021009636OR region8$1,000.00$1,250.00$800.004GRAHAM CONTRACTING, LTD.WSDOT
20 FEB 2020009516OR region3$900.00$962.50$800.008INTERWEST CONSTRUCTION, INC.WSDOT
13 MAR 2019009385SCR region2$900.00$946.33$1,350.005MAX J. KUNEY COMPANYWSDOT
09 JAN 2019009357NWR region7$1,500.00$1,500.00$1,500.006MASSANA CONSTRUCTION, INC.WSDOT
14 MAR 2018009217SWR region1$900.00$1,200.00$2,000.009LIBERTY MAINTENANCE, INC.WSDOT
07 MAR 2018009214SCR region8$1,100.00$1,125.00$1,000.006GRAHAM CONTRACTING, LTD.WSDOT
28 FEB 2018009213NWR region4$1,750.00$1,500.00$1,000.003ACME CONCRETE PAVING, INC.WSDOT
Latest WSDOT contracts carrying Resetting impact attenuator

Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.

How these prices were read

WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.