Removing wire fence unit price, Washington
Low bidders on WSDOT contracts carried a median of $6.50 per LF for removing wire fence, over the 24 months to 07 OCT 2026, across 1 low bids. Half of all 6 bids fell between $5.12 and $6.25.
- Owner
- Washington State DOT
- Item
- No code published
- Unit
- LF
- Latest letting
- 26 AUG 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2000 | 1 | 1 | $2.00 | 9 | $1.25 |
| 2001 | 1 | 1 | $2.00 | 2 | $3.00 |
| 2002 | 1 | 1 | $4.80 | 4 | $17.40 |
| 2004 | 3 | 3 | $4.00 | 18 | $2.50 |
| 2005 | 5 | 4 | $1.30 | 19 | $2.00 |
| 2006 | 2 | 2 | $1.85 | 7 | $1.70 |
| 2007 | 7 | 7 | $1.60 | 59 | $1.50 |
| 2008 | 7 | 7 | $1.50 | 68 | $2.00 |
| 2009 | 4 | 4 | $3.00 | 31 | $2.50 |
| 2010 | 7 | 7 | $1.00 | 56 | $1.27 |
| 2011 | 7 | 6 | $1.10 | 50 | $1.80 |
| 2012 | 4 | 4 | $1.00 | 35 | $1.50 |
| 2013 | 3 | 3 | $2.00 | 24 | $3.75 |
| 2016 | 2 | 2 | $6.00 | 16 | $7.00 |
| 2017 | 2 | 2 | $3.25 | 11 | $5.00 |
| 2018 | 4 | 4 | $8.50 | 17 | $5.00 |
| 2019 | 3 | 3 | $4.75 | 16 | $4.00 |
| 2020 | 1 | 1 | $17.00 | 8 | $4.50 |
| 2021 | 1 | 1 | $1.00 | 2 | $0.68 |
| 2022 | 2 | 2 | $6.00 | 11 | $7.75 |
| 2026 | 1 | 1 | $6.50 | 6 | $5.50 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| NWR region | 20 | $2.00 | 167 | $2.00 |
| SCR region | 12 | $1.35 | 77 | $1.35 |
| ER region | 13 | $3.00 | 71 | $2.00 |
| OR region | 8 | $4.50 | 69 | $3.00 |
| SWR region | 10 | $2.00 | 67 | $2.00 |
| NCR region | 3 | $1.50 | 18 | $1.60 |
Regions with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 14 to 225 | 16 | $4.78 |
| 225 to 766 | 17 | $2.00 |
| 770 to 3,160 | 16 | $1.20 |
| 3,260 to 40,230 | 17 | $1.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 26 AUG 2026 | XE3764 | SCR region | 766 | $6.50 | $5.50 | $10.00 | 6 | INTERWEST CONSTRUCTION, INC. | WSDOT |
| 24 FEB 2022 | 009769 | NWR region | 329 | $7.00 | $7.00 | $5.00 | 4 | GRANITE CONSTRUCTION COMPANY | WSDOT |
| 09 FEB 2022 | 009763 | OR region | 310 | $5.00 | $10.00 | $6.00 | 7 | KRAEMER NORTH AMERICA, LLC. | WSDOT |
| 25 FEB 2021 | 009655 | ER region | 225 | $1.00 | $0.68 | $1.00 | 2 | ROB'S DEMOLITION, INC. | WSDOT |
| 20 FEB 2020 | 009516 | OR region | 710 | $17.00 | $4.50 | $5.50 | 8 | INTERWEST CONSTRUCTION, INC. | WSDOT |
| 10 APR 2019 | 009419 | SWR region | 870 | $3.50 | $2.50 | $6.00 | 8 | FARLINE BRIDGE, INCORPORATED | WSDOT |
| 03 APR 2019 | 009414 | SWR region | 60 | $10.00 | $9.00 | $8.00 | 4 | QUIGG BROS., INC. | WSDOT |
| 24 JAN 2019 | 009369 | ER region | 14 | $4.75 | $13.00 | $10.00 | 4 | SHAMROCK PAVING, INC. | WSDOT |
| 25 APR 2018 | 009258 | ER region | 760 | $6.00 | $5.50 | $5.00 | 2 | CPM DEVELOPMENT CORPORATION | WSDOT |
| 07 MAR 2018 | 009214 | SCR region | 86 | $11.00 | $10.00 | $5.00 | 6 | GRAHAM CONTRACTING, LTD. | WSDOT |
| 22 FEB 2018 | 009211 | OR region | 450 | $11.00 | $5.50 | $6.15 | 6 | ROGNLIN'S, INC. | WSDOT |
| 22 FEB 2018 | 009210 | ER region | 100 | $3.00 | $3.00 | $6.00 | 3 | N.A. DEGERSTROM, INC. | WSDOT |
| 15 FEB 2017 | 009026 | SCR region | 36 | $1.00 | $5.00 | $5.00 | 3 | KIEWIT INFRASTRUCTURE WEST CO. | WSDOT |
| 15 FEB 2017 | 009020 | NCR region | 546 | $5.50 | $5.00 | $4.00 | 8 | INTERWEST CONSTRUCTION, INC. | WSDOT |
| 13 APR 2016 | 008869 | OR region | 150 | $4.00 | $5.00 | $5.00 | 5 | M.J. HUGHES CONSTRUCTION, INC. | WSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.
How these prices were read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way