Removing plastic crosswalk line unit price, Washington
Low bidders on WSDOT contracts carried a median of $3.00 per SF for removing plastic crosswalk line, from 21 DEC 2000 to 16 MAR 2022, across 49 low bids. Half of all 180 bids fell between $2.00 and $5.50.
- Owner
- Washington State DOT
- Item
- No code published
- Unit
- SF
- Latest letting
- 16 MAR 2022
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2000 | 1 | 1 | $8.00 | 2 | $6.25 |
| 2002 | 2 | 2 | $1.79 | 5 | $2.00 |
| 2003 | 3 | 2 | $1.00 | 8 | $1.30 |
| 2004 | 2 | 2 | $1.50 | 6 | $2.00 |
| 2005 | 4 | 4 | $2.65 | 11 | $1.30 |
| 2006 | 2 | 2 | $3.65 | 14 | $1.70 |
| 2007 | 4 | 4 | $4.22 | 11 | $6.30 |
| 2008 | 4 | 4 | $2.75 | 14 | $3.25 |
| 2009 | 1 | 1 | $4.00 | 2 | $4.00 |
| 2010 | 1 | 1 | $2.20 | 4 | $2.95 |
| 2011 | 4 | 4 | $1.91 | 29 | $2.00 |
| 2012 | 2 | 2 | $2.12 | 9 | $2.70 |
| 2013 | 3 | 3 | $4.20 | 8 | $4.10 |
| 2014 | 1 | 1 | $8.75 | 2 | $7.00 |
| 2015 | 3 | 3 | $8.00 | 13 | $7.00 |
| 2016 | 1 | 1 | $3.75 | 6 | $3.92 |
| 2017 | 5 | 5 | $6.00 | 16 | $6.47 |
| 2018 | 2 | 2 | $10.83 | 4 | $10.12 |
| 2019 | 1 | 1 | $5.50 | 3 | $5.50 |
| 2021 | 3 | 3 | $3.00 | 11 | $3.00 |
| 2022 | 1 | 1 | $6.00 | 2 | $5.50 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| NWR region | 25 | $2.50 | 104 | $2.77 |
| SCR region | 6 | $4.92 | 28 | $2.20 |
| NCR region | 9 | $6.66 | 22 | $5.88 |
| OR region | 4 | $1.62 | 12 | $2.00 |
| ER region | 3 | $2.95 | 9 | $5.00 |
Regions with at least three low bids, over all lettings.
By quantity
| Quantity (SF) | Low bids | Low-bid median |
|---|---|---|
| 70 to 190 | 12 | $6.55 |
| 200 to 504 | 12 | $4.60 |
| 540 to 1,090 | 12 | $2.50 |
| 1,107 to 5,184 | 13 | $2.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 16 MAR 2022 | 009782 | Region 9 | 320 | $6.00 | $5.50 | $10.00 | 2 | LAKESIDE INDUSTRIES, INC. | WSDOT |
| 21 APR 2021 | 009662 | NWR region | 720 | $2.50 | $2.50 | $10.00 | 4 | SCARSELLA BROS., INC. | WSDOT |
| 24 MAR 2021 | 009664 | SWR region | 1,242 | $3.00 | $3.00 | $5.00 | 3 | MCDONALD EXCAVATING, INC. | WSDOT |
| 13 JAN 2021 | 009633 | NCR region | 592 | $6.66 | $6.83 | $6.00 | 4 | MORENO & NELSON CONSTRUCTION | WSDOT |
| 24 JAN 2019 | 009367 | NCR region | 1,200 | $5.50 | $5.50 | $5.00 | 3 | INTERSTATE CONCRETE & ASPHALT | WSDOT |
| 10 JAN 2018 | 009181 | NCR region | 1,440 | $1.65 | $1.70 | $4.00 | 2 | CENTRAL WASHINGTON ASPHALT, IN | WSDOT |
| 10 JAN 2018 | 009188 | NCR region | 96 | $20.00 | $19.25 | $10.50 | 2 | CENTRAL WASHINGTON ASPHALT, IN | WSDOT |
| 13 DEC 2017 | 009177 | NWR region | 180 | $9.00 | $9.00 | $5.00 | 3 | TAPANI, INC. | WSDOT |
| 26 APR 2017 | 009072 | ER region | 2,535 | $2.95 | $3.00 | $2.00 | 3 | CPM DEVELOPMENT CORPORATION | WSDOT |
| 25 JAN 2017 | 009012 | SCR region | 504 | $6.75 | $7.50 | $4.00 | 4 | POWER CITY ELECTRIC, INC. | WSDOT |
| 25 JAN 2017 | 009006 | NCR region | 1,790 | $4.40 | $3.70 | $3.00 | 2 | GRANITE CONSTRUCTION COMPANY | WSDOT |
| 11 JAN 2017 | 008992 | NWR region | 422 | $6.00 | $6.22 | $4.00 | 4 | GARY MERLINO CONSTRUCTION CO., | WSDOT |
| 20 APR 2016 | 008883 | NWR region | 390 | $3.75 | $3.92 | $4.40 | 6 | JOHANSEN EXCAVATING, INC. | WSDOT |
| 16 DEC 2015 | 008816 | NWR region | 310 | $5.00 | $5.00 | $5.00 | 5 | MIDMOUNTAIN CONTRACTORS, INC. | WSDOT |
| 09 DEC 2015 | 008822 | NWR region | 85 | $8.00 | $8.00 | $5.00 | 5 | MIDMOUNTAIN CONTRACTORS, INC. | WSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.
How these prices were read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.