Removing guardrail anchor unit price, Washington

Low bidders on WSDOT contracts carried a median of $365.00 per EACH for removing guardrail anchor, over the 24 months to 07 OCT 2026, across 2 low bids. Half of all 18 bids fell between $350.00 and $531.88.

Owner
Washington State DOT
Item
No code published
Unit
EACH
Latest letting
23 SEP 2026
$365.00Low bidder's median, per EACH
$388.09Median of all bids, per EACH
3Contracts in the window
$500.00Engineer's estimate, median per EACH

By year of letting

Removing guardrail anchor, WSDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20001515$160.0058$158.75
20012222$162.5080$160.00
20021212$175.0046$177.50
20031817$150.0072$150.00
20042323$160.0088$160.00
20052525$160.0092$160.00
20061515$200.0057$200.00
20072727$221.00118$213.50
20081616$215.0071$235.00
20092220$230.00110$225.00
20102121$200.0098$200.00
20111515$200.0063$200.00
20121212$212.5081$225.00
20131515$250.0096$250.00
201455$225.0036$225.00
201577$250.0032$300.00
20161414$300.0062$262.50
20171515$410.0067$489.28
20181010$237.5043$300.00
20191414$312.5055$300.00
202077$250.0032$280.43
202177$266.9332$272.50
202244$272.5016$297.50
202377$260.0026$281.10
202632$365.0018$388.09
Removing guardrail anchor, WSDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By region

Removing guardrail anchor, WSDOT: unit prices by region, all lettings
RegionLow bidsLow-bid medianAll bidsMedian, all bids
NWR region106$205.00529$215.00
OR region53$215.00266$225.50
SCR region59$200.00243$215.00
NCR region60$200.00218$207.50
SWR region32$200.00153$210.00
ER region35$200.00133$196.00
Removing guardrail anchor, WSDOT: unit prices by region, all lettings

Regions with at least three low bids, over all lettings.

By quantity

Removing guardrail anchor, WSDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 286$230.00
2 to 487$220.00
4 to 1187$200.00
11 to 23287$180.00
Removing guardrail anchor, WSDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest WSDOT contracts carrying Removing guardrail anchor
LetContractRegionQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
23 SEP 2026XE3772SCR region2n/a$500.00n/a7SCARSELLA BROS., INC.WSDOT
26 AUG 2026XE3764SCR region1$400.00$350.00$500.006INTERWEST CONSTRUCTION, INC.WSDOT
15 JUL 2026XE3755SCR region1$330.00$376.18$500.005INTERWEST CONSTRUCTION, INC.WSDOT
29 MAR 2023009954NWR region14$279.00$277.00$500.002GRANITE CONSTRUCTION COMPANYWSDOT
29 MAR 2023009953NCR region47$250.00$275.00$225.004M2 INDUSTRIAL INC.WSDOT
08 MAR 2023009937NWR region4$260.00$270.00$210.003INTERWEST CONSTRUCTION, INC.WSDOT
23 FEB 2023009925ER region2$275.00$387.50$600.002MAX J. KUNEY COMPANYWSDOT
01 FEB 2023009928OR region1$325.00$325.50$320.004TUCCI & SONS, INC.WSDOT
19 JAN 2023009891OR region11$250.00$450.00$331.007CECCANTI, INC.WSDOT
11 JAN 2023009915SWR region90$175.00$241.09$314.294MASSANA CONSTRUCTION, INC.WSDOT
24 FEB 2022009769NWR region3$330.00$315.00$200.004GRANITE CONSTRUCTION COMPANYWSDOT
09 FEB 2022009763OR region8$210.00$350.00$251.007KRAEMER NORTH AMERICA, LLC.WSDOT
12 JAN 2022009756NCR region6$250.00$255.00$275.003CPM DEVELOPMENT CORPORATIONWSDOT
05 JAN 2022009752NCR region4$295.00$287.50$310.002CENTRAL WASHINGTON ASPHALT, INWSDOT
21 APR 2021009672NWR region4$180.00$237.50$350.006GRANITE CONSTRUCTION COMPANYWSDOT
Latest WSDOT contracts carrying Removing guardrail anchor

Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.

How these prices were read

WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy