Removing chain link fence unit price, Washington
Low bidders on WSDOT contracts carried a median of $4.50 per LF for removing chain link fence, from 05 MAR 2003 to 23 MAR 2022, across 63 low bids. Half of all 380 bids fell between $2.50 and $6.00.
- Owner
- Washington State DOT
- Item
- No code published
- Unit
- LF
- Latest letting
- 23 MAR 2022
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2003 | 3 | 3 | $2.70 | 14 | $4.10 |
| 2004 | 4 | 4 | $2.25 | 27 | $2.00 |
| 2005 | 5 | 5 | $5.40 | 25 | $3.25 |
| 2006 | 3 | 3 | $5.00 | 14 | $5.00 |
| 2007 | 5 | 5 | $3.50 | 28 | $4.00 |
| 2008 | 6 | 6 | $4.50 | 38 | $5.00 |
| 2009 | 7 | 7 | $5.00 | 48 | $3.90 |
| 2010 | 5 | 5 | $2.15 | 43 | $2.27 |
| 2011 | 5 | 5 | $3.00 | 40 | $3.00 |
| 2012 | 2 | 2 | $2.25 | 10 | $2.75 |
| 2013 | 1 | 1 | $4.50 | 11 | $6.00 |
| 2014 | 1 | 1 | $7.00 | 3 | $20.00 |
| 2015 | 1 | 1 | $40.00 | 3 | $20.00 |
| 2016 | 3 | 3 | $3.67 | 10 | $14.88 |
| 2017 | 2 | 2 | $3.50 | 14 | $2.80 |
| 2018 | 2 | 2 | $18.00 | 9 | $12.00 |
| 2019 | 1 | 1 | $10.00 | 6 | $10.00 |
| 2020 | 2 | 2 | $26.00 | 12 | $15.50 |
| 2021 | 3 | 3 | $3.00 | 11 | $7.00 |
| 2022 | 2 | 2 | $5.00 | 14 | $9.00 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| NWR region | 30 | $4.75 | 188 | $4.62 |
| OR region | 7 | $3.00 | 62 | $3.00 |
| ER region | 10 | $3.00 | 49 | $2.60 |
| SWR region | 6 | $3.25 | 44 | $3.00 |
| SCR region | 4 | $4.33 | 17 | $5.00 |
| Region 9 | 4 | $12.50 | 12 | $13.51 |
Regions with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 24 to 110 | 15 | $10.00 |
| 120 to 480 | 16 | $5.00 |
| 520 to 1,155 | 16 | $3.50 |
| 1,190 to 11,110 | 16 | $2.75 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 23 MAR 2022 | 009783 | NWR region | 360 | $5.00 | $6.00 | $10.00 | 7 | INTERWEST CONSTRUCTION, INC. | WSDOT |
| 09 FEB 2022 | 009763 | OR region | 300 | $5.00 | $10.00 | $5.00 | 7 | KRAEMER NORTH AMERICA, LLC. | WSDOT |
| 21 APR 2021 | 009662 | NWR region | 32 | $10.00 | $12.50 | $20.00 | 4 | SCARSELLA BROS., INC. | WSDOT |
| 25 FEB 2021 | 009655 | ER region | 734 | $1.00 | $0.75 | $1.00 | 2 | ROB'S DEMOLITION, INC. | WSDOT |
| 13 JAN 2021 | 009623 | ER region | 1,100 | $3.00 | $5.00 | $5.00 | 5 | MAX J. KUNEY COMPANY | WSDOT |
| 20 FEB 2020 | 009516 | OR region | 40 | $22.00 | $15.50 | $14.00 | 8 | INTERWEST CONSTRUCTION, INC. | WSDOT |
| 23 JAN 2020 | 009509 | ER region | 24 | $30.00 | $22.50 | $10.00 | 4 | GARCO CONSTRUCTION, INC. | WSDOT |
| 09 JAN 2019 | 009357 | NWR region | 30 | $10.00 | $10.00 | $20.00 | 6 | MASSANA CONSTRUCTION, INC. | WSDOT |
| 18 APR 2018 | 009255 | Region 9 | 120 | $20.00 | $20.00 | $10.00 | 3 | PURCELL P & C, LLC DBA PURCELL | WSDOT |
| 07 FEB 2018 | 009196 | SCR region | 260 | $16.00 | $7.97 | $9.50 | 6 | CENTRAL WASHINGTON ASPHALT, IN | WSDOT |
| 01 FEB 2017 | 009008 | ER region | 2,573 | $3.00 | $3.85 | $3.00 | 7 | RED DIAMOND CONSTRUCTION INC | WSDOT |
| 25 JAN 2017 | 009011 | ER region | 1,485 | $4.00 | $1.50 | $3.00 | 7 | MAX J. KUNEY COMPANY | WSDOT |
| 20 APR 2016 | 008883 | NWR region | 30 | $14.75 | $20.86 | $23.00 | 6 | JOHANSEN EXCAVATING, INC. | WSDOT |
| 20 APR 2016 | 008881 | ER region | 2,480 | $2.25 | $3.23 | $3.60 | 2 | SHAMROCK PAVING, INC. | WSDOT |
| 02 MAR 2016 | 008843 | SCR region | 1,330 | $3.67 | $4.33 | $2.50 | 2 | ACME CONCRETE PAVING, INC. | WSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.
How these prices were read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.