Removing drainage structure unit price, Washington

Low bidders on WSDOT contracts carried a median of $500.00 per EACH for removing drainage structure, from 01 MAR 2000 to 23 FEB 2023, across 97 low bids. Half of all 563 bids fell between $300.00 and $745.00.

Owner
Washington State DOT
Item
No code published
Unit
EACH
Latest letting
23 FEB 2023
$500.00Low bidder's median, per EACH
$500.00Median of all bids, per EACH
97Contracts in the window
$500.00Engineer's estimate, median per EACH

By year of letting

Removing drainage structure, WSDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
200055$500.0028$350.00
200155$500.0027$500.00
200233$250.0018$400.00
200366$500.0032$500.00
200477$362.0039$362.00
200566$450.0035$400.00
200644$404.0024$400.00
20071010$525.0062$500.00
200833$500.0014$477.50
200966$308.6039$330.00
20101010$400.0074$400.00
201144$325.0025$350.00
201211$500.0011$400.00
201344$864.1919$629.00
201411$500.008$987.50
201533$1,650.0014$1,112.50
201644$565.4124$505.00
201722$3,125.0013$1,000.00
201822$4,850.005$1,080.00
201922$1,047.5011$800.00
202033$400.0017$625.00
202133$600.0011$700.00
202211$1,500.007$1,500.00
202322$842.506$1,675.00
Removing drainage structure, WSDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By region

Removing drainage structure, WSDOT: unit prices by region, all lettings
RegionLow bidsLow-bid medianAll bidsMedian, all bids
NWR region54$500.00333$500.00
OR region11$350.0078$400.00
ER region15$425.0058$625.00
SWR region9$400.0056$367.50
NCR region3$500.0015$400.00
SCR region3$630.8213$1,000.00
Removing drainage structure, WSDOT: unit prices by region, all lettings

Regions with at least three low bids, over all lettings.

By quantity

Removing drainage structure, WSDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 224$525.00
2 to 524$450.00
5 to 1524$500.00
15 to 10625$360.00
Removing drainage structure, WSDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest WSDOT contracts carrying Removing drainage structure
LetContractRegionQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
23 FEB 2023009925ER region13$625.00$1,312.50$650.002MAX J. KUNEY COMPANYWSDOT
11 JAN 2023009909SWR region2$1,060.00$1,675.00$1,500.004THOMPSON BROS. EXCAVATING, INCWSDOT
09 FEB 2022009763OR region7$1,500.00$1,500.00$1,006.007KRAEMER NORTH AMERICA, LLC.WSDOT
24 MAR 2021009656NWR region3$600.00$662.50$2,400.004MARSHBANK CONSTRUCTION, INC.WSDOT
25 FEB 2021009655ER region1$100.00$1,550.00$500.002ROB'S DEMOLITION, INC.WSDOT
13 JAN 2021009623ER region3$700.00$700.00$500.005MAX J. KUNEY COMPANYWSDOT
20 FEB 2020009516OR region10$350.00$700.00$617.008INTERWEST CONSTRUCTION, INC.WSDOT
05 FEB 2020009501NWR region3$400.00$600.00$700.005TITAN EARTHWORK LLCWSDOT
23 JAN 2020009509ER region5$625.00$562.50$350.004GARCO CONSTRUCTION, INC.WSDOT
13 MAR 2019009374NWR region1$1,325.00$1,000.00$1,200.007MARSHBANK CONSTRUCTION, INC.WSDOT
24 JAN 2019009369ER region1$770.00$740.00$1,000.004SHAMROCK PAVING, INC.WSDOT
18 APR 2018009233NWR region1$8,700.00$5,350.00$1,200.002A-1 LANDSCAPING AND CONSTRUCTIWSDOT
04 APR 2018009238SWR region2$1,000.00$1,000.00$2,500.003ROGNLIN'S, INC.WSDOT
15 MAR 2017009036SCR region3$6,000.00$2,500.00$1,000.006IMCO GENERAL CONSTRUCTION, INCWSDOT
01 FEB 2017009008ER region4$250.00$460.00$500.007RED DIAMOND CONSTRUCTION INCWSDOT
Latest WSDOT contracts carrying Removing drainage structure

Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.

How these prices were read

WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy