Removing raised pavement marker unit price, Washington
Low bidders on WSDOT contracts carried a median of $140.00 per HUND for removing raised pavement marker, from 24 FEB 2000 to 08 MAR 2023, across 106 low bids. Half of all 487 bids fell between $98.50 and $255.00.
- Owner
- Washington State DOT
- Item
- No code published
- Unit
- HUND
- Latest letting
- 08 MAR 2023
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2000 | 5 | 5 | $100.00 | 20 | $95.00 |
| 2001 | 7 | 7 | $125.00 | 30 | $100.00 |
| 2002 | 4 | 4 | $189.50 | 16 | $141.00 |
| 2003 | 8 | 6 | $163.00 | 40 | $110.00 |
| 2004 | 4 | 4 | $94.00 | 19 | $95.00 |
| 2005 | 7 | 7 | $80.00 | 32 | $90.00 |
| 2006 | 2 | 2 | $347.62 | 7 | $195.00 |
| 2007 | 9 | 9 | $100.00 | 44 | $107.50 |
| 2008 | 6 | 6 | $100.00 | 21 | $120.00 |
| 2009 | 8 | 8 | $117.50 | 37 | $125.00 |
| 2010 | 7 | 7 | $155.00 | 43 | $130.00 |
| 2011 | 5 | 5 | $100.00 | 16 | $100.00 |
| 2012 | 1 | 1 | $500.00 | 5 | $500.00 |
| 2013 | 4 | 4 | $205.00 | 18 | $307.50 |
| 2014 | 8 | 8 | $205.00 | 31 | $225.00 |
| 2015 | 4 | 4 | $145.00 | 19 | $140.00 |
| 2016 | 3 | 3 | $160.00 | 20 | $150.00 |
| 2017 | 4 | 3 | $1,875.00 | 17 | $1,875.00 |
| 2018 | 5 | 5 | $200.00 | 19 | $420.00 |
| 2020 | 1 | 1 | $500.00 | 8 | $475.00 |
| 2021 | 3 | 3 | $350.00 | 16 | $976.00 |
| 2022 | 2 | 2 | $565.00 | 5 | $730.00 |
| 2023 | 2 | 2 | $3,040.00 | 4 | $1,350.00 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| NWR region | 92 | $140.00 | 416 | $135.00 |
| SWR region | 8 | $262.50 | 39 | $340.00 |
| OR region | 5 | $110.00 | 27 | $120.00 |
Regions with at least three low bids, over all lettings.
By quantity
| Quantity (HUND) | Low bids | Low-bid median |
|---|---|---|
| 0.10 to 1.98 | 26 | $350.00 |
| 2 to 8.90 | 27 | $200.00 |
| 8.90 to 40.50 | 26 | $102.00 |
| 41 to 376.90 | 27 | $90.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 08 MAR 2023 | 009937 | NWR region | 0.10 | $5,650.00 | $2,270.00 | $1,500.00 | 3 | INTERWEST CONSTRUCTION, INC. | WSDOT |
| 11 JAN 2023 | 009901 | NWR region | 60.60 | $430.00 | $430.00 | $175.00 | 1 | GARY MERLINO CONSTRUCTION CO., | WSDOT |
| 13 APR 2022 | 009781 | NWR region | 7.60 | $730.00 | $755.00 | $250.00 | 4 | TUCCI & SONS, INC. | WSDOT |
| 12 JAN 2022 | 009758 | NWR region | 5 | $400.00 | $400.00 | $300.00 | 1 | AWARD CONSTRUCTION, INC. | WSDOT |
| 28 APR 2021 | 009678 | SWR region | 4.02 | $350.00 | $375.00 | $240.00 | 4 | CONSTRUCTION AHEAD, INC. DBA | WSDOT |
| 21 APR 2021 | 009662 | NWR region | 2 | $300.00 | $313.75 | $400.00 | 4 | SCARSELLA BROS., INC. | WSDOT |
| 10 FEB 2021 | 009643 | NWR region | 0.20 | $2,200.00 | $2,225.00 | $700.00 | 8 | STRIDER CONSTRUCTION CO., INC. | WSDOT |
| 20 FEB 2020 | 009516 | OR region | 3.90 | $500.00 | $475.00 | $350.00 | 8 | INTERWEST CONSTRUCTION, INC. | WSDOT |
| 04 APR 2018 | 009235 | NWR region | 24.80 | $115.00 | $120.00 | $200.00 | 3 | MIDMOUNTAIN CONTRACTORS, INC. | WSDOT |
| 04 APR 2018 | 009232 | SWR region | 0.50 | $200.00 | $200.00 | $1,000.00 | 1 | GRANITE CONSTRUCTION COMPANY | WSDOT |
| 14 MAR 2018 | 009217 | SWR region | 0.70 | $420.00 | $420.00 | $440.00 | 9 | LIBERTY MAINTENANCE, INC. | WSDOT |
| 22 FEB 2018 | 009198 | NWR region | 46.60 | $50.00 | $115.00 | $150.00 | 2 | CADMAN MATERIALS, INC. | WSDOT |
| 10 JAN 2018 | 009194 | NWR region | 0.85 | $700.00 | $625.00 | $400.00 | 4 | ROAD CONSTRUCTION NORTHWEST, I | WSDOT |
| 20 DEC 2017 | 009185 | SWR region | 1.11 | $400.00 | $460.00 | $1,950.00 | 3 | MASSANA CONSTRUCTION, INC. | WSDOT |
| 13 DEC 2017 | 009172 | NWR region | 0.40 | $2,500.00 | $2,680.00 | $500.00 | 8 | COLACURCIO BROTHERS, INC. | WSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.
How these prices were read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.