Removing plastic traffic marking unit price, Washington
Low bidders on WSDOT contracts carried a median of $55.00 per EACH for removing plastic traffic marking, from 13 DEC 2000 to 08 MAR 2023, across 113 low bids. Half of all 481 bids fell between $40.00 and $125.00.
- Owner
- Washington State DOT
- Item
- No code published
- Unit
- EACH
- Latest letting
- 08 MAR 2023
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2000 | 2 | 2 | $65.00 | 7 | $55.00 |
| 2001 | 5 | 5 | $49.00 | 12 | $52.50 |
| 2002 | 5 | 5 | $31.50 | 13 | $39.00 |
| 2003 | 9 | 8 | $35.00 | 37 | $37.00 |
| 2004 | 7 | 6 | $34.00 | 25 | $35.00 |
| 2005 | 9 | 9 | $30.00 | 41 | $42.00 |
| 2006 | 5 | 5 | $65.00 | 15 | $57.12 |
| 2007 | 6 | 6 | $55.00 | 26 | $55.00 |
| 2008 | 6 | 6 | $79.50 | 36 | $106.00 |
| 2009 | 5 | 5 | $52.00 | 11 | $50.00 |
| 2010 | 8 | 8 | $45.50 | 53 | $45.00 |
| 2011 | 6 | 6 | $39.00 | 42 | $39.00 |
| 2012 | 2 | 2 | $106.00 | 10 | $160.00 |
| 2013 | 4 | 4 | $62.50 | 14 | $75.00 |
| 2014 | 7 | 7 | $150.00 | 28 | $155.00 |
| 2015 | 5 | 5 | $250.00 | 22 | $250.00 |
| 2016 | 5 | 5 | $135.00 | 18 | $155.00 |
| 2017 | 6 | 6 | $217.57 | 23 | $345.00 |
| 2018 | 2 | 2 | $210.50 | 6 | $187.50 |
| 2019 | 3 | 3 | $230.00 | 8 | $235.00 |
| 2020 | 2 | 2 | $350.00 | 15 | $375.00 |
| 2021 | 3 | 3 | $85.00 | 12 | $85.00 |
| 2022 | 1 | 1 | $160.00 | 3 | $160.00 |
| 2023 | 2 | 2 | $502.50 | 4 | $502.50 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| NWR region | 73 | $55.00 | 329 | $56.00 |
| SWR region | 9 | $45.00 | 46 | $45.00 |
| SCR region | 7 | $50.00 | 37 | $50.00 |
| OR region | 9 | $35.00 | 31 | $100.00 |
| NCR region | 12 | $67.50 | 28 | $62.75 |
| ER region | 3 | $47.25 | 10 | $48.62 |
Regions with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 4 | 28 | $167.50 |
| 4 to 12 | 28 | $55.00 |
| 13 to 45 | 28 | $49.00 |
| 46 to 663 | 29 | $50.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 08 MAR 2023 | 009937 | NWR region | 2 | $900.00 | $900.00 | $360.50 | 3 | INTERWEST CONSTRUCTION, INC. | WSDOT |
| 11 JAN 2023 | 009901 | NWR region | 391 | $105.00 | $105.00 | $120.00 | 1 | GARY MERLINO CONSTRUCTION CO., | WSDOT |
| 02 MAR 2022 | 009762 | NWR region | 115 | $160.00 | $160.00 | $70.00 | 3 | MIDMOUNTAIN CONTRACTORS, INC. | WSDOT |
| 21 APR 2021 | 009662 | NWR region | 67 | $50.00 | $50.00 | $400.00 | 4 | SCARSELLA BROS., INC. | WSDOT |
| 24 MAR 2021 | 009664 | SWR region | 4 | $85.00 | $85.00 | $200.00 | 3 | MCDONALD EXCAVATING, INC. | WSDOT |
| 03 FEB 2021 | 009646 | NWR region | 16 | $125.00 | $130.00 | $10.00 | 5 | OCEANSIDE CONSTRUCTION, INC. | WSDOT |
| 20 FEB 2020 | 009516 | OR region | 13 | $400.00 | $400.00 | $130.00 | 8 | INTERWEST CONSTRUCTION, INC. | WSDOT |
| 05 FEB 2020 | 009515 | OR region | 2 | $300.00 | $322.56 | $400.00 | 7 | NORTHEAST ELECTRIC, LLC | WSDOT |
| 06 MAR 2019 | 009380 | NWR region | 2 | $559.00 | $550.00 | $300.00 | 3 | FABER CONSTRUCTION CORP. | WSDOT |
| 21 FEB 2019 | 009382 | NWR region | 5 | $230.00 | $235.00 | $350.00 | 2 | SRV CONSTRUCTION, INC. | WSDOT |
| 24 JAN 2019 | 009367 | NCR region | 227 | $60.00 | $60.00 | $39.00 | 3 | INTERSTATE CONCRETE & ASPHALT | WSDOT |
| 10 JAN 2018 | 009194 | NWR region | 2 | $375.00 | $312.50 | $200.00 | 4 | ROAD CONSTRUCTION NORTHWEST, I | WSDOT |
| 10 JAN 2018 | 009181 | NCR region | 135 | $46.00 | $48.00 | $75.00 | 2 | CENTRAL WASHINGTON ASPHALT, IN | WSDOT |
| 20 DEC 2017 | 009185 | SWR region | 3 | $500.00 | $575.00 | $190.00 | 3 | MASSANA CONSTRUCTION, INC. | WSDOT |
| 13 DEC 2017 | 009177 | NWR region | 2 | $340.00 | $345.00 | $200.00 | 3 | TAPANI, INC. | WSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.
How these prices were read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.