Low bidders on WSDOT contracts carried a median of $3.00 per HR for training, from 03 FEB 2000 to 05 APR 2023, across 175 low bids. Half of all 846 bids fell between $1.62 and $10.00.
- Owner
- Washington State DOT
- Item
- No code published
- Unit
- HR
- Latest letting
- 05 APR 2023
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2000 | 14 | 14 | $2.00 | 46 | $2.00 |
| 2001 | 18 | 18 | $2.00 | 63 | $2.00 |
| 2002 | 8 | 8 | $2.50 | 34 | $2.00 |
| 2003 | 13 | 11 | $2.00 | 67 | $2.00 |
| 2004 | 6 | 6 | $3.50 | 27 | $3.00 |
| 2005 | 6 | 6 | $2.00 | 23 | $3.00 |
| 2006 | 9 | 9 | $3.00 | 39 | $4.00 |
| 2007 | 11 | 11 | $4.00 | 35 | $4.00 |
| 2008 | 7 | 7 | $2.15 | 51 | $5.00 |
| 2009 | 8 | 8 | $2.00 | 52 | $4.62 |
| 2010 | 11 | 11 | $3.00 | 60 | $2.00 |
| 2011 | 7 | 6 | $8.50 | 35 | $2.00 |
| 2012 | 4 | 4 | $3.00 | 35 | $4.00 |
| 2013 | 7 | 7 | $3.00 | 37 | $5.00 |
| 2014 | 6 | 6 | $2.00 | 34 | $5.00 |
| 2015 | 4 | 4 | $15.00 | 16 | $9.25 |
| 2017 | 6 | 4 | $5.00 | 26 | $5.00 |
| 2018 | 9 | 9 | $5.00 | 42 | $9.00 |
| 2019 | 12 | 12 | $13.00 | 50 | $10.50 |
| 2020 | 2 | 2 | $1.50 | 12 | $4.50 |
| 2021 | 4 | 4 | $3.50 | 21 | $5.00 |
| 2022 | 4 | 4 | $30.00 | 21 | $25.00 |
| 2023 | 4 | 4 | $1.50 | 20 | $8.00 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| NWR region | 65 | $3.00 | 336 | $4.00 |
| OR region | 25 | $3.00 | 126 | $5.00 |
| SCR region | 24 | $1.75 | 122 | $2.25 |
| SWR region | 15 | $5.00 | 91 | $5.00 |
| ER region | 24 | $3.00 | 83 | $4.00 |
| NCR region | 17 | $2.00 | 62 | $2.00 |
Regions with at least three low bids, over all lettings.
By quantity
| Quantity (HR) | Low bids | Low-bid median |
|---|---|---|
| 1 to 400 | 43 | $2.00 |
| 400 to 400 | 44 | $3.50 |
| 400 to 850 | 44 | $4.00 |
| 1,000 to 22,500 | 44 | $2.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 05 APR 2023 | 009948 | SCR region | 800 | $1.00 | $10.00 | $1.00 | 3 | COMBINED CONSTRUCTION, INC. | WSDOT |
| 29 MAR 2023 | 009941 | OR region | 400 | $2.00 | $5.50 | $15.00 | 6 | JOHANSEN CONSTRUCTION COMPANY, | WSDOT |
| 19 JAN 2023 | 009913 | NWR region | 2,000 | $60.00 | $48.75 | $50.00 | 4 | VIMAS PAINTING COMPANY, INC. | WSDOT |
| 19 JAN 2023 | 009891 | OR region | 800 | $1.00 | $5.00 | $14.00 | 7 | CECCANTI, INC. | WSDOT |
| 27 APR 2022 | 009805 | SWR region | 600 | $15.00 | $50.00 | $61.00 | 7 | AMARI PAINTING AND LINING LLC | WSDOT |
| 16 MAR 2022 | 009780 | OR region | 400 | $45.00 | $25.00 | $15.00 | 2 | ROGNLIN'S, INC. | WSDOT |
| 09 FEB 2022 | 009763 | OR region | 1,600 | $5.00 | $5.00 | $1.00 | 7 | KRAEMER NORTH AMERICA, LLC. | WSDOT |
| 05 JAN 2022 | 009737 | Region 9 | 1,200 | $108.22 | $65.00 | $1.00 | 5 | CONTRACK WATTS, INC. | WSDOT |
| 24 MAR 2021 | 009636 | OR region | 400 | $2.00 | $4.00 | $25.00 | 4 | GRAHAM CONTRACTING, LTD. | WSDOT |
| 17 MAR 2021 | 009657 | NWR region | 400 | $8.48 | $4.74 | $15.00 | 4 | VALLEY ELECTRIC CO. OF MT. VERNON, | WSDOT |
| 03 FEB 2021 | 009625 | SCR region | 800 | $5.00 | $7.50 | $10.00 | 8 | SCARSELLA BROS., INC. | WSDOT |
| 13 JAN 2021 | 009623 | ER region | 400 | $1.00 | $5.00 | $10.00 | 5 | MAX J. KUNEY COMPANY | WSDOT |
| 20 FEB 2020 | 009516 | OR region | 800 | $2.00 | $4.50 | $17.00 | 8 | INTERWEST CONSTRUCTION, INC. | WSDOT |
| 23 JAN 2020 | 009509 | ER region | 5,200 | $1.00 | $3.50 | $3.00 | 4 | GARCO CONSTRUCTION, INC. | WSDOT |
| 24 APR 2019 | 009428 | ER region | 2,400 | $28.00 | $28.00 | $5.00 | 1 | ACME CONCRETE PAVING, INC. | WSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.
How these prices were read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.